_R4_files/image002.jpg)
Contents
1.3 Construction Works Programme and Construction Works Area
1.4 Summary of Environmental Status
2.3 Monitoring Parameter and Frequency and Duration
2.5 Monitoring Methodology and QA/QC Procedure
2.6 Action and Limit Level for Air Quality Monitoring
3 Construction Noise Monitoring
3.3 Noise Monitoring Parameter, Frequency and Duration
3.4 Monitoring Equipment, Methodology and QA / QC Procedure
3.5 Maintenance and Calibration
8 Land Contamination (Ambient Arsenic Monitoring)
8.4 Monitoring Parameters, Frequency and Duration
8.5 Monitoring Methodology and QA/QC Procedure
8.7 Laboratory Measurement / Analysis
9.2 Monitoring Parameters and Frequency
10.3 Monitoring Parameters and Frequency
11 Environmental Site Inspection and Audit
11.1 Implementation Status of Environmental Mitigation Measures
12 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
12.2 Summary of Environmental Non-Compliance
12.3 Summary of Environmental Complaint
12.4 Summary of Environmental Summon and Successful Prosecution
13.1 Works and Potential Environmental Issues in the next Reporting Period
14.2 Comments/ Recommendations
Figures
Figure 1.1 Location and Site Layout Plan (KTN)
Figure 1.2 Location and Site Layout Plan (FLN)
Figure 2.1 Location of Air Quality Monitoring Stations for KTN NDA
Figure 2.2 Location of Air Quality Monitoring Stations for FLN NDA
Figure 3.1 Location of Noise Monitoring Stations for KTN NDA
Figure 3.2 Location of Noise Monitoring Stations for FLN NDA
Figure 8.1 Location of Ambient Arsenic Monitoring Stations for KTN NDA
Appendix 1.1 Construction Programme
Appendix 1.2 Project Organization Chart
Appendix 1.3 Implementation Status of Environmental Mitigation Measure
Appendix 2.1 Impact Monitoring Schedule during the reporting period
Appendix 2.2 Impact Air Quality Monitoring Data & Graphical Presentations & Calibration Certificates
Appendix 2.3 Weather Information during the Reporting Period
Appendix 2.4 Event and Action Plan for Construction Dust
Appendix 3.1 Impact Noise Monitoring Data & Graphical Presentations & Calibration Certificates
Appendix 3.2 Event and Action Plan for Construction Noise
Appendix 5.1 Summary of Monthly Waste Flow Table
Appendix 6.1 Detailed Results of the Ecological Waterbird Monitoring during this Reporting Period
Appendix 6.2 Detailed Results of the Ecological Aquatic Monitoring during this Reporting Period
Appendix 6.3 Detailed Results of the Ecological Non-aquatic Monitoring during this Reporting Period
Appendix 6.4 Event and Action Plan for Ecological Monitoring
Appendix 7.1 Event and Action Plan for Landscape and Visual
Appendix 8.2 Event and Action Plan for Ambient Arsenic Monitoring
Appendix 12.1 Statistical Summary of Environmental Complaints, Summons and Prosecution
Appendix 13.1 Impact Monitoring Schedule of Next Reporting Month
A1. This is the 20th Monthly Environment Monitoring and Audit (EM&A) Report for Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas (the Project) for the reporting period between 1 and 31 August 2026. This report was prepared by Aurecon Hong Kong Limited (Aurecon) under Service Contract No. NDO 05/2024 Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas - Environmental Team (hereinafter called the “Service Contract”).
A2. Construction works were undertaken under all Works Contracts including Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/05, Works Contract No. ND/2024/06, Works Contract No. ND/2024/07 and Works Contract No. ND/2024/08 during the reporting month. This report documents the findings of EM&A works at Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/05, Works Contract No. ND/2024/06 Works Contract No. ND/2024/07 and Works Contract No. ND/2024/08 under the Project during the reporting period.
A3. This Project involves eight (8) Environmental Permits (EPs) (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A and EP-476/2013). Details of each EPs are summarised in Table A1.
Table A1 Works Contracts under relevant Environmental Permits in the Reporting Month
|
Environmental Permit No. |
Works Contracts |
Title of Designated Project |
Designated Project (DP) |
|
EP-465/2013/A |
ND/2024/03 |
San Tin Highway and Fanling Highway Kwu Tung Section Widening (Between San Tin Interchange and Po Shek Wu Interchange) |
DP1 |
|
EP-466/2013/A |
ND/2024/03 |
Castle Peak Road Diversion |
DP2 |
|
EP-467/2013/A |
ND/2024/01 |
Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement |
DP3 |
|
EP-468/2013/A |
ND/2024/01 |
Kwu Tung North New Development Area Road D1 to D5 |
DP4 |
|
EP-469/2013 |
- |
Sewage Pumping Stations in Kwu Tung North New Development Area |
DP5 |
|
EP-470/2013/A |
ND/2024/06 |
Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
DP7 |
|
EP-471/2013/A |
ND/2024/04 |
Po Shek Wu Interchange Improvement |
DP8 |
|
EP-472/2013/A |
ND/2024/08 |
Fanling Bypass Western Section |
DP9 |
|
EP-473/2013/A |
- |
Fanling Bypass Eastern Section |
DP10 |
|
- |
Shek Wu Hui Sewage Treatment Works - Further Expansion at Fanling North New Development Area |
DP11 |
|
|
ND/2024/07 ND/2024/08 |
Sewage Pumping Stations in Fanling North New Development Area (FLNDA) |
DP13 |
A4. The construction works undertaken under Works Contract No. ND/2024/01 commenced since 20 January 2025, construction works under Works Contract No. ND/2024/07 commenced since 27 February 2025, construction works under Works Contract No. ND/2024/06 commenced since 10 March 2025, construction works under Works Contract No. ND/2024/04 commenced since 10 May 2025, construction works under Works Contract No. ND/2024/03 commenced since 1 June 2025, construction works under Works Contract No. ND/2024/02 commenced since 9 February 2026, construction works under Works Contract No. ND/2024/05 commenced since 11 May 2026 and construction works under Works Contract No. ND/2024/08 commenced since 3 June 2026. The commencement dates of each Works Contracts are summarized in Table A2.
Table A2 Commencement Dates of Each Works Contracts
|
Works Contracts |
Commencement Dates |
|
ND/2024/01 |
20 January 2025 |
|
ND/2024/02 |
9 February 2026 |
|
ND/2024/03 |
1 June 2025 |
|
ND/2024/04 |
10 May 2025 |
|
ND/2024/05 |
11 May 2026 |
|
ND/2024/06 |
10 March 2025 |
|
ND/2024/07 |
27 February 2025 [1] |
|
ND/2024/08 |
3 June 2026 [2] |
|
[1] According to the contractor’s and supervising team’s confirmation, the project commencement date is 27 February 2025 [2] According to the contractor’s and supervising team’s confirmation, the project commencement date is 3 June 2026 |
|
A5. A summary of construction activities undertaken during the reporting period is presented below:
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree Survey
2. Site Clearance
· Portion III (3), IV (4), V (5) and XXXV (35)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
3. Site Formation
· Portion VI (6), VIII (8), XI (11), XII (12), XVI (16), XXII (22), XXIII (23), XXXV (35), XLII (42), XLIV (44) and LIII (53)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
· Portion XVIII (18) and XXXVIII (38)
1. Excavation Works
2. Construction of CHC Box Culvert
· Portion XI (11) and XXIII (23)
1. Formwork Erection, Rebar Fixing, Concreting Works
2. Erection of Substructure of NM Core Exhibition Gallery
· Portion XL (40)
1. Retaining Wall Construction
2. Drainages System Construction
3. ELS work
· Portion LIX (59)
1. Treatment of High Arsenic-Containing Soil (HAS)
2. Erection of Shredding Facilities
· Portion XVII (17), XVIII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41) and XLII (42)
1. Excavation Works
2. Drainage Pipe Installation
3. ELS Works
· Portion V (5) and XLII (42)
1. Site Clearance
2. Site Formation
3. Construction of CHB Box Culvert
· Portion XXV (25), XXVII (27), XXXIII (33), XLII (42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of CHB and CHD Box Culvert
· Portion XII (12), XVI (16), XXX (30) and XLIV (44)
1. Archaeological Survey
· Portion XX (20)
1. Site Formation
2. Temporary Traffic Arrangement (TTA)
· Portion XV (15) and XXXI (31)
1. Site Clearance
Works Contract No. ND/2024/02:
· Portion 1, 2, 3, 4, 16, 18, 20, 25, 33, 43 & 57
1. Site clearance
· Portion 1, 3, 17, 18, 19 & 57
1. Ground investigation and Environmental Ground Investigation works
· Portion 1, 2, 3, 4, 18 & 33
1. Asbestos removal works
· Portion 2, 3, 4 & 18
1. Tree removal works
· Portion 2 & 34
1. Site formation works
Works Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road – Po Lau Road
1. Drainage
2. Watermain Pak Sau Road – Po Lau Road DN150
· Po Lau Road – Sheung Yue River
1. New Castle Peak Road & Fanling Highway E/B Temporary Work & Excavation
2. Tree Works
3. Box Culvert (Bay 37-42)
· TTA Stage 1 Works
1. Tree Works
2. High Voltage Post, Signage & Streetligting
· New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/ Watermains
1. Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 14
2. Box Culvert Bay 12 wall & Top slab
· Box Culvert Bay 17 to 19 & Drainage/Watermains
1. Drainage, sewerage & watermain with backfilling at Box Culvert Bay 19
· Box culvert Bay 3, 5 to 7 & Drainage/Watermains
1. Box Culvert Bay 7 & 7A ELS
2. Box Culvert Bay 7 & 7A Base Slab
3. Box Culvert Bay 7 & 7A Wall & Top Slab
4. Box Culvert Bay 3, 5 to 6 ELS
5. Box Culvert Bay 5 Base Slab
6. Box Culvert Bay 3 Base Slab
· Retaining Wall RW01
1. Pre-drilling
· Retaining Wall RW05A
1. RW05A Bay 11 to 16 Backfilling
2. RW05A Bay 11, 13 & 15 Wall
3. RW05A Bay 4, 6, 8 & 10 Wall
4. RW05A Bay 5, 7 & 9 Wall
· Kwu Tung Road Bridge
1. Foundation & Piling
2. Pile Cap (Piers KTR-P03)
3. Retaining Wall RW14 – Bay 1-6 Wall
· Works Areas – WA1, WA2, WA3 & WA4
1. Site Clearance
· Works Areas – WA5
1. Materials/Segment Storage Yard Initial Works & Set up
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion XI – RW15 Foundation, Base Slab & Wall
1. Approach ramp wall RW15-Piling Works
Kwu Tung Interchange Foundation & Substructure
· Bridge A1
1. Piling Works
2. Excavation
3. Pile Cap
· Bridge B2 & C2
1. ELS
2. Pile Cap
· Bridge B1(NW) & C1(NW)
1. Piling
2. ELS & Pile Cap
· Widening of Existing Bridge No.N526
1. Tree Works
2. Pre-drilling
3. Piling
· Footbridges No. 5 at TTA Stage 2
1. Installation of Temporary Footbridge No. 5
Works Contract No. ND/2024/04:
· Portion I
1. Site Clearance
2. Site Establishment
3. Tree Works
4. Ground Investigation
5. Haul Road Construction
6. Existing Sewage Diversion
7. Formworks
8. Demolition of Existing Structures
9. Road Diversion Works
10.Sheet Pilling
11.ELS Construction
12.Pipe Cap Construction
13.Slope Works
· Portion II
1. Site Clearance
2. Site Establishment
3. Tree Works
4. Trial Pit
5. Haul Road Construction
6. Bored Piling
7. Socket H Piling
8. Pile Cap Construction
· Portion III
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Formworks
5. Haul Road Construction
6. Road Diversion Works
7. Bored Piling
8. Sheet Piling
9. ELS Construction
10.Slope Works
· Portion IV
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Pre-drilling
5. Formworks
6. Demolition of Existing Structures
· Portion V
1. Site Clearance
2. Site Establishment
3. Formworks
· Portion VI
1. Site Clearance
2. Site Establishment
3. Demolition of Existing Structures
· Portion VII
1. Site Clearance
2. Site Establishment
3. Trial Pit
· Portion VIII
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Tree Works
5. Demolition of Existing Structures
Works Contract No. ND/2024/05:
· Portion I
1. UU Survey and diversion
· Portion III
1. Site formation works
· Portion IIIA
1. Site Facilities Erection
2. Ground Investigation and Backfilling Works
· Portion XI and XII
1. Archaeological Survey
· Portion XVII
1. UU Diversion and Installation
2. Site Clearance
Works Contract No. ND/2024/06:
· Portion A
1. Excavation to +85 mPD of Portion A
2. Carry Out Soil Nails of Portion A
· Portion C, Portion E and Portion F
1. Trench and Watermains Laying Works
· Portion D
1. Construction of Pit
· Pit A and Pit C
1. Pre-boring
· Pit B
1. Excavation
· Pit F
1. Sheet Piling
· Chuk Yuen
1. Construction of Accommodation
Works Contract No. ND/2024/07:
· Area B
1. Drainage & Sewerage Construction
· Area D
1. Site Formation
· Area E
1. Site Formation
· Area F
1. Sewerage Construction
2. Site Clearance
3. Site Formation
· Area G
1. Site Formation
2. Site Clearance
· Area I
1. Sewerage Construction
· Area J
1. Road Construction
· Area K
1. Sewerage Construction
2. Site Clearance
3. Asbestos Removal
· Area M
1. Site Clearance
2. Sewage Pumping Station (SPS4) Construction
· Area O
1. Asbestos Removal
2. Site Clearance
· Area P
1. Site Formation
2. Drainage Construction
· Area Q
1. Drainage Construction
2. Box Culvert 5 Construction
3. Storm Pipe Construction
· Area T
1. Asbestos Removal
2. Site Clearance
· Footbridge FB-4 (North)
1. ABWF Works
· Footbridge FB-4 (South)
1. ABWF Works
2. Pile Cap Construction
· Footbridge FB-5
1. Lift Tower Construction
2. Sump Pit Construction
3. ABWF Works
· Portion 3b
1. Sewerage Construction
2. Drainage Construction
· Portion 6c
1. Improvement of Junction
· Portion 9b
1. Rebar Yard
Works Contract No. ND/2024/08:
· Site Area A
1. Demolition Works
2. Asbestos Investigation
· Site Area C1 & C2
1. Asbestos inspection
· Site Area D & E
1. Site Appraisal
2. Asbestos inspection
· Site Area G, H1 & H2
1. Site Appraisal
2. Asbestos inspection
· Site Area I, V2 & V4
1. Site Formation
2. Asbestos inspection
3. Rebar Bending
· Site Area L6, K & U
1. Road Works
2. Site Formation Works
3. Predrilling Works
· Site Area L1, L2, L3, L4, L5 & L7
1. Predrilling Works
· Site Area M1, M2, M3, N1, N2, O & P
1. Retaining Wall Construction
2. Tree Felling
3. Site Formation
· Site Area Q & R
1. Site Preparation Wroks
2. Tree Felling
· Site Area T
1. Site Appraisal
2. Asbestos Investigation
3. Archaeological Rescue Excavation Survey
· Site Area W
1. Site Clearance
2. Asbestos Abatement
3. Tree Felling
4. Fill Material Stockpile
· Site Area V1 & V3
1. Retaining Wall Construction
A6. The environmental monitoring activities, including 1-hour Total Suspended Particulates (TSP) monitoring, 24-hour TSP monitoring, noise monitoring, ecological survey, 24-hour Respirable Suspended Particulates (RSP) (Ambient Arsenic) monitoring for land contamination and environmental site inspection, were undertaken by Environmental Team (ET) under Service Contract No. NDO 04/2019 (i.e. First Phase ET – Wellab) and under Service Contract No. NDO 05/2024 (i.e. Remaining Phase ET - Aurecon) during the reporting period in accordance with the approved Updated EM&A Manual. A summary of the monitoring and audit activities during the reporting period is presented in Table A3.
Table A3 Summary of EM&A Activities in the Reporting Period
|
EM&A |
Monitoring Station(s) |
Works Contract(s)(5) |
|||||||
|
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
||
|
1-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 24, 28 Aug 2026 |
6, 12, 18, 24, 28 Aug 2026 |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
5, 11, 17, 21, 27 Aug 2026 |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
4, 10, 14, 20, 26 Aug 2026 (6) |
4, 10, 14, 20, 26 Aug 2026 (6) |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
24-hour TSP Monitoring(1) |
KTN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
KTN-DMS4(B)(2)(3) |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
N/A |
N/A |
|
|
FLN-DMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
5, 11, 17, 21, 27 Aug 2026 |
|
|
FLN-DMS2(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS5(A)(2)(3) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
5, 11, 17, 21, 27 Aug 2026 |
|
|
FLN-DMS6(A)(2)(3) |
N/A |
N/A |
4, 10, 14, 20, 26 Aug 2026 (6) |
4, 10, 14, 20, 26 Aug 2026 (6) |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-DMS7(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Noise Monitoring(1) |
CP-KTN-NMS1(2) |
7, 13, 19, 25 Aug 2026 (6) |
7, 13, 19, 25 Aug 2026 (6) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
CP-KTN-NMS2(2) |
5, 11, 17, 27 Aug 2026 |
5, 11, 17, 27 Aug 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS3(2) |
5, 11, 17, 27 Aug 2026 |
5, 11, 17, 27 Aug 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS4(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
5, 11, 17, 27 Aug 2026 |
N/A |
5, 11, 17, 27 Aug 2026 |
|
|
CP-KTN-NMS6(2) |
5, 11, 17, 27 Aug 2026 |
5, 11, 17, 27 Aug 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-KTN-NMS7(2) |
7, 13, 19, 25 Aug 2026 (6) |
7, 13, 19, 25 Aug 2026 (6) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS1(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 12, 18, 24 Aug 2026 |
6, 12, 18, 24 Aug 2026 |
N/A |
|
|
CP-FLN-NMS3(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS4(A)(2)(3) |
N/A |
N/A |
N/A |
4, 10, 20, 26 Aug 2026 (6) |
N/A |
N/A |
N/A |
N/A |
|
|
CP-FLN-NMS5(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 20, 26 Aug 2026 (6) |
4, 10, 20, 26 Aug 2026 (6) |
|
|
CP-FLN-NMS6(2) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
4, 10, 20, 26 Aug 2026 (6) |
4, 10, 20, 26 Aug 2026 (6) |
|
|
Ecological Monitoring (4) |
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley |
Weekly Monitoring: 3, 5, 11, 13, 18, 19, 25, 27 Aug 2026 (Transect T1, T2, T3 and T5) |
Weekly Monitoring: 3, 5, 11, 13, 18, 19, 25, 27 Aug 2026 (Transect T1, T2, T3, T4 and T5) |
Weekly Monitoring: 3, 5, 11, 13, 18, 19, 25, 27 Aug 2026 (Transect T1, T2, T3 and T5) |
Weekly Monitoring: 3, 5, 12, 13, 17, 19, 24, 27 Aug 2026 (Transect T4) |
N/A |
Weekly Monitoring: 3, 5, 11, 13, 18, 19, 25, 27 Aug 2026 (Transect T1, T2 and T3) |
Weekly Monitoring: 3, 5, 11, 12, 13, 17, 18, 19, 24, 25, 27 Aug 2026 (Transect T1, T2, T3, and T4) |
Weekly Monitoring: 3, 5, 11, 12, 13, 17, 18, 19, 24, 25, 27 Aug 2026 (Transect T1, T2, T3, and T4) |
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream |
Monthly Monitoring: 4 Aug 2026 (MS_01 – MS_10) |
Monthly Monitoring: 4 Aug 2026 (MS_01 – MS_10) |
N/A |
N/A |
N/A |
N/A |
Monthly Monitoring: 4 Aug 2026 (MS_11 – MS_15) |
Monthly Monitoring: 4 Aug 2026 (MS_11 – MS_15) |
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
Monthly Monitoring: 26 Aug 2026 (Transect T1) |
Monthly Monitoring: 26 Aug 2026 (Transect T1 and T6) |
Monthly Monitoring: 17 Aug 2026 (Transect T4) |
N/A |
Monthly Monitoring: 17, 26 Aug 2026 (Transect T4 and T6) |
Monthly Monitoring: 26 Aug 2026 (Transect T2) |
Monthly Monitoring: 17 Aug 2026 (Transect T3) |
Monthly Monitoring: 17 Aug 2026 (Transect T3) |
|
|
24-hour RSP (Ambient Arsenic) Monitoring for Land Contamination (1) |
KTN-DMS4(C)(2)(3) |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
5, 11, 17, 21, 27 Aug 2026 |
N/A |
N/A |
N/A |
|
Water Quality Monitoring(1) |
KTN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
KTN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-IS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
FLN-CS1 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Landfill Gas Monitoring |
250m Landfill Consultation Zone of Ma Tso Lung Landfill |
N/A(7) |
N/A(7) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Built Heritage Monitoring |
G102, G202, G203 G302, G303, G308, KT26, KT53, KT65, HKT03 |
N/A(8) |
N/A |
N/A(8) |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Environmental Site Inspection |
Site Area under Works Contract No. ND/2024/01 |
4, 11, 20, 25 Aug 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Site Area under Works Contract No. ND/2024/02 |
N/A |
4, 11, 21, 25 Aug 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/03 |
N/A |
N/A |
3, 10, 18, 24, 31 Aug 2026 |
N/A |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/04 |
N/A |
N/A |
N/A |
7, 12, 21, 28 Aug 2026 |
N/A |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/05 |
N/A |
N/A |
N/A |
N/A |
4, 11, 17, 26 Aug 2026 |
N/A |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/06 |
N/A |
N/A |
N/A |
N/A |
N/A |
3, 10, 17, 27, 31 Aug 2026 |
N/A |
N/A |
|
|
Site Area under Works Contract No. ND/2024/07 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
6, 13, 20, 27 Aug 2026 |
N/A |
|
|
Site Area under Works Contract No. ND/2024/08 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
5, 12, 19, 26 Aug 2026 |
|
Remarks:
(1) For 1-hour and 24-hour TSP & 24-hour RSP (Ambient Arsenic) monitoring, monitoring stations that are specifically within the 500m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.
For Noise Monitoring, monitoring stations that are specifically within the 300m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.
(2)
New monitoring station
IDs are presented. The corresponding monitoring station IDs are as follows:
|
1-hour and 24-hour TSP / 24-hour RSP (Ambient Arsenic) KTN-DMS1
= DMS1 |
Noise CP-KTN-NMS1
= CP-NMS1 CP-KTN-NMS7 =
CP-NMS4 |
(3) Alternative monitoring stations to the corresponding original monitoring stations.
(4) The monitoring date for the reporting month was conducted by the ET from the First Phase of KTN/FLN NDAs Project, except Transect T4 for the ecological monitoring item Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley, and Transect T2 for the ecological monitoring item Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution. No ecological monitoring was conducted for the Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream for this reporting month as this monitoring is only conducted during wet season (April – October). Detailed divisions of work between First Phase ET and Remaining Phase can be referred to Section 6 and relevant appendix.
(5) N/A – No relevant monitoring is required according to the approved updated EM&A Manual.
(7) As confirmed by the Supervisor Team, no ground disturbance works were carried out in the work area within 250m Landfill Consultation Zone of Ma Tso Lung Landfill including construction of the infrastructure, development works, excavation works and works involve confined spaces. Routine gas monitoring should be undertaken during groundwork construction and in all excavations.
(8) As confirmed by the Contractors, related works were not conducted within the assessment area in the reporting month.
A7. Summary of the environmental exceedances of the reporting period is tabulated in Table A4.
Table A4 Summary of Exceedances in the Reporting Period
|
Environmental Monitoring |
Parameter(s) |
No. of Exceedances |
Total No. of Exceedances |
No. of Non-project Related Exceedances |
Total No. of Non-project Related Exceedances |
No. of Exceedances Related to the Project |
Total No. of Exceedances Related to the Project |
|||
|
AL |
LL |
AL |
LL |
AL |
LL |
|||||
|
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hourTSP |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
24-hour RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Noise |
Leq(30mins) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Ecological Monitoring |
Avifauna |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Non-aquatic fauna |
0 |
3 |
3 |
0 |
3 |
3 |
0 |
0 |
0 |
|
|
Built Heritage Monitoring |
Tilting |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Settlement |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Ground Settlement |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Vibration (PPV) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Air Quality
A8. No AL or LL exceedance was recorded for air quality monitoring in the reporting period.
Noise
A9. No AL exceedance for construction noise was recorded during the reporting month, corresponding to no noise-related complaint received. No LL exceedance was recorded for construction noise monitoring in the reporting period.
Ambient Arsenic
A10. No AL or LL exceedance was recorded for ambient arsenic monitoring in the reporting period.
Ecological Monitoring
A11. Three LL exceedances were recorded for the monitoring of measures to minimise impacts on ecological sensitive habitats from disturbance and pollution. All exceedances were deemed as non-project related with potential influences by abiotic factors.
Built Heritage Monitoring (Vibration Monitoring)
A12. As confirmed by the Contractors, related works were not conducted within the assessment area in the reporting month, hence no vibration monitoring was required to be conducted in the reporting month. No exceedance of limits was recorded for vibration monitoring in the reporting period.
A13. One environmental complaint was logged during the reporting period. The complaint was regarding wastewater runoff and nighttime construction noise impact.
A14. The environmental complaint was related to wastewater runoff on road near the site area at Tsung Pak Long and the nighttime construction noise impact under works contract ND/2024/03. The complaint was received by the EPD on 7 August 2026 and referred to CEDD, the Resident Engineers’ Team, ET, and IEC on 10 August 2026. The complaint case has been investigated by the Contractor and ET, and the investigation was closed out on 18 August 2026. The investigation findings have shown that the contractor has provided and implemented necessary mitigation measures on site. No non-compliance was observed.
A15. The details of the complaint and investigation result are shown in Appendix 12.1.
A16. No notification of summons or successful prosecutions was received in the reporting period.
A17. There was no reporting change in the reporting month.
A18. The major site activities for the next reporting period are summarized below and shown in Appendix 1.1:
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
· Portion III (3), IV (4), V (5) and XXXV (35)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
3. Site Formation
· Portion VI (6), VIII (8), Portion XI (11), XII (12), XVI (16), XXII (22), XXIII (23), XXXV (35), XLII (42), XLIV (44) and LIII (53)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
· Portion XVIII (18), XXXVIII (38)
1. Excavation works
2. Construction of CHC Box Culvert
· Portion XI (11), XXIII (23)
1. Formwork Erection, Rebar Fixing, Concreting Works
2. Erection of Substructure of NM Core Exhibition Gallery
3. Fitting out
· Portion XL (40)
1. Drainages System Construction
· Portion LIX (59)
1. Treatment of High Arsenic-Containing Soil (HAS)
2. Erection of Shredding Facilities
· Portion XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)
1. Excavation Works
2. Drainage Pipe Installation
3. ELS Works
· Portion V (5) and XLII (42)
1. Site Clearance
2. Site Formation
3. Construction of CHB Box Culvert
· Portion XXV (25), XXVII (27), XXXIII (33), XLII (42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of CHB and CHD Box Culvert
· Portion XII (12), XVI (16), XXX (30), XLIV (44)
1. Archaeological Survey
· Portion XX (20)
1. Site Formation
2. Temporary Traffic Arrangement (TTA)
Works Contract No. ND/2024/02:
· Portion 1, 2, 3, 4, 16, 18, 20, 25, 33, 43 & 57
1. Site clearance
· Portion 2, 3, & 20
1. Ground Investigation and Environmental Ground Investigation Works
· Portion 1, 2, 4 and 33
1. Asbestos removal works
· Portion 1, 2, 3, 4, 18 & 33
1. Tree removal works
· Portion 2 & 34
1. Site Formation
Works Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road – Po Lau Road
1. Tree Works
2. Watermain DN150
· Po Lau Road – Sheung Yue River
1. Tree Works
2. Box Culvert Bay 37 – Bay 42 New Castle Peak Road & Fanling Highway
· TTA Stage 1 Works
1. Tree Works
2. Demolish of Central Divider & Barrier along FL Highway E/B
New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1. Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
· Box culvert Bay 17 to 19 & Drainage/Watermains
1. Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 19
· TTA Stage 1B
1. Box Culvert Bay 3, 5 to 7, 7A ELS
2. Box Culvert Base Slab
· Retaining Wall RW05A
1. RW05A Base Slab and Wall
· Kwu Tung Road Bridge
1. Site clearance and tree works
2. Site formation and cutback the existing slope
3. Foundation & Piling
· Works Areas – WA1, WA2, WA3, WA4 & WA5
1. Temporary Drainage
2. Material/ Segments Storage Yard
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion X – West Abutment
1. Site clearance & preparation, survey and tree works
· Road L3 Viaduct
1. Piling Works
2. Pile Cap L3A-01
Kwu Tung Interchange Foundation & Substructure
· Bridge A1
1. Piling Works
2. Excavation
3. Pile Cap
· Bridge B2 & C2
1. ELS
2. Pile Cap
· Bridge B1(NW) & C1(NW)
1. Piling
2. ELS & Pile Cap
· Footbridges No. 3 at TTA Stage 1
1. Clearance
2. Demolishing the existing Footbridge NF157
3. Removal of Temporary Wokrs
· Footbridges No. 4 at TTA Stage 1
1. Ground Investigation
2. Underground Utilities Works
· Footbridges No. 5 at TTA Stage 2
1. Demolishing the existing Footbridge NF156
· Widening of Existing Bridge No.N526
1. Pile Cap
2. Predrilling
Works Contract No. ND/2024/04:
· Portion I
1. Site Clearance
2. Site Establishment
3. Tree Works
4. Ground Investigation
5. Haul Road Construction
6. Existing Sewage Diversion
7. Formworks
8. Demolition of Existing Structures
9. Road Diversion Works
10.Sheet Piling
11.ELS Construction
12.Pipe Cap Construction
13.Slope Works
· Portion II
1. Site Clearance
2. Site Establishment
3. Tree Wroks
4. Trial Pit
5. Haul Road Construction
6. Socket H Piling
7. Pile Cap Construction
· Portion III
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Formworks
5. Haul Road Construction
6. Road Diversion Works
7. Bored Piling
8. Sheet Piling
9. ELS Construction
10.Slope Works
11.Demolition of Existing Structures
· Portion IV
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Pre-drilling
5. Formworks
6. Demolition of Existing Structures
· Portion V
1. Site Clearance
2. Site Establishment
3. Formworks
· Portion VI
1. Site Clearance
2. Site Establishment
3. Demolition of Existing Structures
· Portion VII
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Pre-drilling
5. Socket-H Piling
6. Demolition of Existing Structures
· Portion VIII
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Socket-H Piling
5. Tree Works
6. Demolition of Existing Structures
Works Contract No. ND/2024/05:
· Portion I
1. Ground Investigation
2. Site Formation Works
· Portion III
1. Tree Felling
2. Site Formation Works
3. Site Clearance
· Portion IIIA
1. Tree Felling Works
2. TTA Set up
· Portion VI
1. Asbestos Removal
2. Site Formation Works
· Portion IX
1. Asbestos Removal
· Portion XI and XII
1. Asbestos Survey & Removal
2. UU Detection
3. Site Clearance & Formation Works
4. Ground Investigation
· Portion XVII
1. Tree Felling
2. UU Detection
3. Site Clearance
4. Ground Investigation
Works Contract No. ND/2024/06:
· Portion A
1. Excavation to +85 mPD
2. Carry Out Soil Nail
· Portion C, E & F
1. Trench and Watermains Laying Works
· Portion D
1. Construction of Pit
· Pit A & C
1. Pre-boring and Sheet-Piling
· Pit B & F
1. Excavation
· Chuk Yuen
1. Construction of Accommodation
Works Contract No. ND/2024/07:
· Area B
1. Drainage and Sewage Construction
2. Open Landscape
· Area D
1. Site Formation
· Area E
1. Site Formation
· Area F
1. Sewerage Construction
2. Tree Felling
3. Site Formation
· Area G
1. Site Clearance
2. Site Formation
· Area H
1. Asbestos Removal
· Area I
1. Asbestos Removal
2. Sewerage Construction
· Area J
1. Road Works
2. Site Clearance
· Area K
1. Site Clearance
2. Asbestos Removal
3. Old Shrine Removal
4. Sewerage Construction
5. Environmental Ground Investigation
· Area M
1. Sewage Pumping Station (SPS4) Construction
· Area N
1. Sewage Construction
2. Road Works
· Area O
1. Site Clearance
2. Asbestos Removal
3. Box Culvert 4 Construction
· Area P
1. Site Formation
2. Drainage Construction
· Area Q
1. Drainage Construction
2. Storm Pipe Construction
3. Box Culvert 5 Construction
· Area R
1. Asbestos Removal
· Area T
1. Asbestos Removal
2. Site Clearance
3. Retaining Wall Construction
4. Site Formation
· Portion 3b
1. Sewerage Construction
2. Drainage Construction
3. Flushing Main Construction
· Portion 6c
1. Improvement of Junction
· Portion 9b
1. Rebar Yard
· Portion H3 and H5
1. Site Clearance
· Footbridge FB-4 (North)
1. Lift Installation
2. ABWF Works
· Footbridge FB-4 (South)
1. ABWF Works
2. Pile Cap Construction
· Footbridge FB-5
1. Lift Tower Construction
2. ABWF Works
3. UHPC Staircase Construction
Works Contract No. ND/2024/08:
· Site Area A
1. Demolition Works
2. Asbestos Abatement
3. Land Decontamination Works
· Site Area B
1. Tree Felling
2. Asbestos Abatement
· Site Area C1 & C2
1. Tree Felling
· Site Area D & E
1. Tree Felling
2. Asbestos Abatement
· Site Area G, H1 & H2
1. Tree Felling
2. Asbestos Abatement
3. Land Decontamination Works
· Site Area I, V2 & V4
1. Tree Felling
2. Asbestos Abatement
3. Land Decontamination Works
· Site Area J
1. Asbestos Investigation
· Site Area L6, K & U
1. Site Formation
2. Asbestos Abatement
3. Tree Felling
4. Road Works
5. UU Works
6. G.I. Works
7. Predrilling Wokrs
· Site Area L1, L2, L3, L4, L5 & L7
1. Site Clearance
2. Predrilling Woks
3. Retaining Wall Construction
4. Bored Pile Works
· Site Area M1, M2, M3, N1, N2, O & P
1. Retaining Wall Construction
2. Tree Felling
3. Rebar Fixing
4. Land Decontamination Works
· Site Area R
1. Tree Feling
2. Site Preparation Works
· Site Area S
1. Site Clearance
2. G.I. Works
· Site Area T
1. Asbestos Abatement
2. Tree Felling
3. Construction of MKT Road
4. Archaeological Rescue Excavation Survey
· Site Area W
1. Asbestos Abatement
2. Tree Felling
3. Land Decontamination Works
· Site Area Q
1. Sewerage Pumping Station Construction
2. Tree Felling
3. Site Preparation Works
· Site Area V1 & V3
1. Site Preparation Works
2. Retaining Wall Construction
1.1.1 The Kwu Tung North and Fanling North New Development Areas (KTN and FLN NDAs) development are implemented in two phases, comprising First Phase and Remaining Phase developments. The construction works for the First Phase development commenced in December 2019. The construction works for the Remaining Phase development (the Project), including site clearance and formation, roads, drainage, sewerage and water supply systems, commenced progressively from the January 2025.
1.1.2 The Project is delivered under eight (8) Works Contracts as below.
· Contract No. ND/2024/01: Site Formation and Infrastructure Works (South);
· Contract No. ND/2024/02: Site Formation and Infrastructure Works (North);
· Contract No. ND/2024/03: Improvement Works of Fanling Highway (Kwu Tung Portion) and Associated Works;
· Contract No. ND/2024/04: Improvement Works of Tai Tau Leng Roundabout and Po Shek Wu Road and Associated Works;
· Contract No. ND/2024/05: Improvement Works of Fanling Highway (Pak Shek Au Portion) and Associated Works;
· Contract No. ND/2024/06: Fresh Water and Flushing Water Service Reservoirs and Associated Works;
· Contract No. ND/2024/07: Site Formation and Infrastructure Works (East); and
· Contract No. ND/2024/08: Site Formation and Infrastructure Works (West).
1.1.3 The EIA Report (AEIAR-175/2013) for NENT NDA was approved with conditions under EIAO in 2013. The Environmental Permits for corresponding Designated Projects were also issued by DEP in November 2013. Subsequent to the findings of preliminary design and P&E Review for accommodating additional population in KTN and FLN NDAs, VEP were subsequently applied for eight EPs under the Project (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A and EP-476/2013).
1.1.4 Aurecon was commissioned by Civil Engineering and Development Department (CEDD) to provide EM&A services for the works contracts in relation to the Project pursuant to the requirements as specified in relevant EPs, the EM&A Manual issued in the EIA stage, the Updated EM&A Manual prepared for Contract No. NDO 14/2018 and the approved EIA Report for the Project to discharge the duties of the ET for the Project.
1.1.5 This is the 20th Monthly EM&A Report summarizing the findings of EM&A works at Works Contract No. ND/2024/01 under the Project with EP-467/2013/A and EP-468/2013/A, Works Contract No. ND/2024/02 under the Project with EP-467/2013/A and EP-468/2013/A, Works Contract No. ND/2024/03 under the Project with EP-465/2013/A, EP-466/2013/A and EP-467/2023/A, Works Contract No. ND/2024/04 under the Project with EP-465/2013/A and EP-471/2013/A, Works Contract No. ND/2024/05 under the Project with EP-465/2013/A, EP-466/2013/A and EP-467/2013/A, Works Contract No. ND/2024/06 under Environmental Permit No. EP-470/2013/A, Contract No. ND/2024/07 under Environmental Permit No. EP-476/2013 and Contract No. ND/2024/08 under Environmental Permit No. EP-472/2013/A and EP-476/2013 during the reporting period from 1 to 31 August 2026.
Table 1.1 Parties Involved in Project Organization for all Works Contracts
|
|
Works Contract(s) |
||||||||
|
Parties |
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
Project Proponent |
CEDD |
||||||||
|
Supervisor / Engineer’s Representative (ER) |
AECOM Asia Co. Ltd. |
AECOM Asia Co. Ltd. |
AECOM Asia Co. Ltd |
AECOM Asia Co. Ltd |
AECOM Asia Co. Ltd |
Binnies Hong Kong Limited |
AtkinsRéalis Asia Limited |
AtkinsRéalis Asia Limited |
|
|
Contractor |
Build King - Richwell Engineering Joint Venture |
Build King – Richwell Civil Joint Venture
|
China State - STEC Joint Venture |
CW – CRCC (ND202404) Joint Venture |
Lanon – Sinohydro – Excel JV |
Wo Hing-Tsun Yip Joint Venture |
Build King – Richwell Civil Joint Venture |
Gammon - STEC Joint Venture |
|
|
ET |
Aurecon Hong Kong Limited |
||||||||
|
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
||||||||
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree Survey
2. Site Clearance
· Portion III (3), IV (4), V (5) and XXXV (35)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
3. Site Formation
· Portion VI (6), VIII (8), XI (11), XII (12), XVI (16), XXII (22), XXIII (23), XXXV (35), XLII (42), XLIV (44) and LIII (53)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
· Portion XVIII (18) and XXXVIII (38)
1. Excavation Works
2. Construction of CHC Box Culvert
· Portion XI (11) and XXIII (23)
1. Formwork Erection, Rebar Fixing, Concreting Works
2. Erection of Substructure of NM Core Exhibition Gallery
· Portion XL (40)
1. Retaining Wall Construction
2. Drainages System Construction
3. ELS work
· Portion LIX (59)
1. Treatment of High Arsenic-Containing Soil (HAS)
2. Erection of Shredding Facilities
· Portion XVII (17), XVIII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41) and XLII (42)
1. Excavation Works
2. Drainage Pipe Installation
3. ELS Works
· Portion V (5) and XLII (42)
1. Site Clearance
2. Site Formation
3. Construction of CHB Box Culvert
· Portion XXV (25), XXVII (27), XXXIII (33), XLII (42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of CHB and CHD Box Culvert
· Portion XII (12), XVI (16), XXX (30) and XLIV (44)
1. Archaeological Survey
· Portion XX (20)
1. Site Formation
2. Temporary Traffic Arrangement (TTA)
· Portion XV (15) and XXXI (31)
1. Site Clearance
Works Contract No. ND/2024/02:
· Portion 1, 2, 3, 4, 16, 18, 20, 25, 33, 43 & 57
1. Site clearance
· Portion 1, 3, 17, 18, 19 & 57
1. Ground investigation and Environmental Ground Investigation works
· Portion 1, 2, 3, 4, 18 & 33
1. Asbestos removal works
· Portion 2, 3, 4 & 18
1. Tree removal works
· Portion 2 & 34
1. Site formation works
Works Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road – Po Lau Road
1. Drainage
2. Watermain Pak Sau Road – Po Lau Road DN150
· Po Lau Road – Sheung Yue River
1. New Castle Peak Road & Fanling Highway E/B Temporary Work & Excavation
2. Tree Works
3. Box Culvert (Bay 37-42)
· TTA Stage 1 Works
1. Tree Works
2. High Voltage Post, Signage & Streetligting
New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/ Watermains
1. Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 14
2. Box Culvert Bay 12 wall & Top slab
· Box Culvert Bay 17 to 19 & Drainage/Watermains
1. Drainage, sewerage & watermain with backfilling at Box Culvert Bay 19
· Box culvert Bay 3, 5 to 7 & Drainage/Watermains
1. Box Culvert Bay 7 & 7A ELS
2. Box Culvert Bay 7 & 7A Base Slab
3. Box Culvert Bay 7 & 7A Wall & Top Slab
4. Box Culvert Bay 3, 5 to 6 ELS
5. Box Culvert Bay 5 Base Slab
6. Box Culvert Bay 3 Base Slab
· Retaining Wall RW01
1. Pre-drilling
· Retaining Wall RW05A
1. RW05A Bay 11 to 16 Backfilling
2. RW05A Bay 11, 13 & 15 Wall
3. RW05A Bay 4, 6, 8 & 10 Wall
4. RW05A Bay 5, 7 & 9 Wall
· Kwu Tung Road Bridge
1. Foundation & Piling
2. Pile Cap (Piers KTR-P03)
3. Retaining Wall RW14 – Bay 1-6 Wall
· Works Areas – WA1, WA2, WA3 & WA4
1. Site Clearance
· Works Areas – WA5
1. Materials/Segment Storage Yard Initial Works & Set up
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion XI – RW15 Foundation, Base Slab & Wall
1. Approach ramp wall RW15-Piling Works
Kwu Tung Interchange Foundation & Substructure
· Bridge A1
1. Piling Works
2. Excavation
3. Pile Cap
· Bridge B2 & C2
1. ELS
2. Pile Cap
· Bridge B1(NW) & C1(NW)
1. Piling
2. ELS & Pile Cap
· Widening of Existing Bridge No.N526
1. Tree Works
2. Pre-drilling
3. Piling
· Footbridges No. 5 at TTA Stage 2
1. Installation of Temporary Footbridge No. 5
Works Contract No. ND/2024/04:
· Portion I
1. Site Clearance
2. Site Establishment
3. Tree Works
4. Ground Investigation
5. Haul Road Construction
6. Existing Sewage Diversion
7. Formworks
8. Demolition of Existing Structures
9. Road Diversion Works
10.Sheet Pilling
11.ELS Construction
12.Pipe Cap Construction
13.Slope Works
· Portion II
1. Site Clearance
2. Site Establishment
3. Tree Works
4. Trial Pit
5. Haul Road Construction
6. Bored Piling
7. Socket H Piling
8. Pile Cap Construction
· Portion III
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Formworks
5. Haul Road Construction
6. Road Diversion Works
7. Bored Piling
8. Sheet Piling
9. ELS Construction
10.Slope Works
· Portion IV
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Pre-drilling
5. Formworks
6. Demolition of Existing Structures
· Portion V
1. Site Clearance
2. Site Establishment
3. Formworks
· Portion VI
1. Site Clearance
2. Site Establishment
3. Demolition of Existing Structures
· Portion VII
1. Site Clearance
2. Site Establishment
3. Trial Pit
· Portion VIII
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Tree Works
5. Demolition of Existing Structures
Works Contract No. ND/2024/05:
· Portion I
1. UU Survey and diversion
· Portion III
1. Site formation works
· Portion IIIA
1. Site Facilities Erection
2. Ground Investigation and Backfilling Works
· Portion XI and XII
1. Archaeological Survey
· Portion XVII
1. UU Diversion and Installation
2. Site Clearance
Works Contract No. ND/2024/06:
· Portion A
1. Excavation to +85 mPD of Portion A
2. Carry Out Soil Nails of Portion A
· Portion C, Portion E and Portion F
1. Trench and Watermains Laying Works
· Portion D
1. Construction of Pit
· Pit A and Pit C
1. Pre-boring
· Pit B
1. Excavation
· Pit F
1. Sheet Piling
· Chuk Yuen
1. Construction of Accommodation
Works Contract No. ND/2024/07:
· Area B
1. Drainage & Sewerage Construction
· Area D
1. Site Formation
· Area E
1. Site Formation
· Area F
1. Sewerage Construction
2. Site Clearance
3. Site Formation
· Area G
1. Site Formation
2. Site Clearance
· Area I
1. Sewerage Construction
· Area J
1. Road Construction
· Area K
1. Sewerage Construction
2. Site Clearance
3. Asbestos Removal
· Area M
1. Site Clearance
2. Sewage Pumping Station (SPS4) Construction
· Area O
1. Asbestos Removal
2. Site Clearance
· Area P
1. Site Formation
2. Drainage Construction
· Area Q
1. Drainage Construction
2. Box Culvert 5 Construction
3. Storm Pipe Construction
· Area T
1. Asbestos Removal
2. Site Clearance
· Footbridge FB-4 (North)
1. ABWF Works
· Footbridge FB-4 (South)
1. ABWF Works
2. Pile Cap Construction
· Footbridge FB-5
1. Lift Tower Construction
2. Sump Pit Construction
3. ABWF Works
· Portion 3b
1. Sewerage Construction
2. Drainage Construction
· Portion 6c
1. Improvement of Junction
· Portion 9b
1. Rebar Yard
Works Contract No. ND/2024/08:
· Site Area A
1. Demolition Works
2. Asbestos Investigation
· Site Area C1 & C2
1. Asbestos inspection
· Site Area D & E
1. Site Appraisal
2. Asbestos inspection
· Site Area G, H1 & H2
1. Site Appraisal
2. Asbestos inspection
· Site Area I, V2 & V4
1. Site Formation
2. Asbestos inspection
3. Rebar Bending
· Site Area L6, K & U
1. Road Works
2. Site Formation Works
3. Predrilling Works
· Site Area L1, L2, L3, L4, L5 & L7
1. Predrilling Works
· Site Area M1, M2, M3, N1, N2, O & P
1. Retaining Wall Construction
2. Tree Felling
3. Site Formation
· Site Area Q & R
1. Site Preparation Wroks
2. Tree Felling
· Site Area T
1. Site Appraisal
2. Asbestos Investigation
3. Archaeological Rescue Excavation Survey
· Site Area W
1. Site Clearance
2. Asbestos Abatement
3. Tree Felling
4. Fill Material Stockpile
· Site Area V1 & V3
1. Retaining Wall Construction
Table 1.2 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/01
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10008709 |
02/09/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052236 |
20/09/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN: 5213-548-B2781-01 |
06/12/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045924-2024 |
15/01/2025 |
31/01/2030 |
Valid |
|
WT00046627-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046736-2025 |
10/06/2025 |
30/06/2030 |
Valid |
|
WT00046982-2025 |
03/10/2025 |
31/10/2030 |
Valid |
|
WT00047583-2025 |
19/01/2026 |
31/01/2031 |
Valid |
|
WT00048070-2026 |
28/01/2026 |
31/01/2031 |
Valid |
|
WT00048369-2026 |
14/04/2026 |
30/04/2031 |
Valid |
|
WT00048594-2026 |
08/05/2026 |
31/05/2031 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1014-26 |
26/07/2026 |
25/10/2026 |
Valid |
|
GW-RN1013-26 |
29/07/2026 |
28/10/2026 |
Valid |
|
GW-RN0709-26 |
02/06/2026 |
01/09/2026 |
Valid |
|
GW-RN0744-26 |
09/06/2026 |
26/09/2026 |
Valid |
|
GW-RN1043-26 |
31/07/2026 |
30/10/2026 |
Valid |
Table 1.3 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/02
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10024940 |
23/12/2025 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7057203 |
05/01/2026 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-545-B2803-01 |
11/02/2026 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00049211-2026 |
14/08/2026 |
31/08/2031 |
Valid |
|
10033969 |
-- |
-- |
Under Application |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0649-26 |
15/05/2026 |
14/08/2026 |
Valid till 14/08/2026 |
Table 1.4 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/03
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-466/2013/A |
18/08/2022 |
N/A |
Valid |
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10008101 |
15/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7052008 |
21/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-548-C5047-01 |
22/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00046044-2025 |
07/11/2025 |
28/02/2030 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0655-26 |
15/05/2026 |
14/08/2026 |
Valid till 14/08/2026 |
|
GW-RN0786-26 |
16/06/2026 |
15/09/2026 |
Valid |
|
GW-RN0840-26 |
25/06/2026 |
24/09/2026 |
Valid |
|
GW-RN0876-26 |
10/07/2026 |
09/10/2026 |
Valid |
|
GW-RN0877-26 |
10/07/2026 |
09/10/2026 |
Valid |
Table 1.5 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/04
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-471/2013/A |
10/10/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10012919 |
06/01/2025 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7053746 |
13/02/2025 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-626-C5043-01 |
28/01/2025 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00047165-2025 |
15/12/2025 |
31/08/2030 |
Valid |
|
WT00048760-2026 |
12/06/2026 |
31/03/2031 |
Valid (Variation of WT00048247-2026) |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0580-26 |
13/05/2026 |
12/08/2026 |
Valid till 12/08/2026 |
|
GW-RN0579-26 |
07/05/2026 |
06/08/2026 |
Valid till 06/08/2026 |
|
GW-RN0710-26 |
01/06/2026 |
31/08/2026 |
Valid till 31/08/2026 |
|
GW-RN0708-26 |
02/06/2026 |
31/08/2026 |
Valid till 31/08/2026 |
|
GW-RN0760-26 |
12/06/2026 |
11/09/2026 |
Valid |
|
GW-RN0762-26 |
12/06/2026 |
31/08/2026 |
Valid till 31/08/2026 |
|
GW-RN0842-26 |
01/07/2026 |
30/09/2026 |
Valid |
|
GW-RN0830-26 |
07/07/2026 |
06/10/2026 |
Valid |
|
GW-RN0886-26 |
03/07/2026 |
02/11/2026 |
Valid |
|
GW-RN0896-26 |
09/07/2026 |
08/10/2026 |
Valid |
|
GW-RN0900-26 |
10/07/2026 |
09/10/2026 |
Valid |
|
GW-RN0951-26 |
17/07/2026 |
16/10/2026 |
Valid |
|
GW-RN0954-26 |
17/07/2026 |
16/10/2026 |
Valid |
|
GW-RN0970-26 |
13/08/2026 |
31/10/2026 |
Valid |
|
GW-RN0991-26 |
24/07/2026 |
23/10/2026 |
Valid |
|
GW-RN0987-26 |
24/07/2026 |
30/09/2026 |
Valid |
|
GW-RN1004-26 |
04/08/2026 |
31/08/2026 |
Valid till 31/08/2026 |
Table 1.6 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/05
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-465/2013/A |
20/01/2017 |
N/A |
Valid |
|
EP-466/2013/A |
18/08/2022 |
N/A |
Valid |
|
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
100025962 |
23/01/2026 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7057565 |
03/02/2026 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-545-L3280-01 |
14/05/2026 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
10031886 |
-- |
-- |
Under Application |
|
10032855 |
-- |
-- |
Under Application |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN1021-26 |
28/07/2026 |
30/09/2026 |
Valid |
|
GW-RN1050-26 |
04/08/2026 |
03/11/2026 |
Valid |
Table 1.7 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/06
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-470/2013/A |
13/05/2022 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10007695 |
06/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051899 |
28/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-624-W3824-01 |
04/09/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00046560-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046847-2025 |
11/07/2025 |
31/07/2030 |
Valid |
|
WT00046588-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
WT00048275-2026 |
20/04/2026 |
31/04/2031 |
Valid |
|
WT00048499-2026 |
28/05/2026 |
31/05/2031 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0395-26 |
01/04/2026 |
30/09/2026 |
Valid |
|
GW-RN0592-26 |
12/05/2026 |
05/08/2026 |
Valid till 05/08/2026 |
|
PP-RN0037-26 |
24/08/2026 |
23/10/2026 |
Valid |
|
GW-RN1187-26 |
28/08/2026 |
05/11/2026 |
Valid |
Table 1.8 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/07
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-476/2013 |
21/11/2013 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10007874 |
09/08/2024 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7051974 |
20/08/2024 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-625-B2775-01 |
19/08/2024 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00045532-2024 |
10/12/2024 |
31/12/2029 |
Valid |
|
WT00046059-2025 (Part 1) |
17/06/2025 |
28/02/2030 |
Valid |
|
WT00046059-2025 (Part 2) |
17/06/2025 |
28/02/2030 |
Valid |
|
WT00046342-2025 |
15/05/2025 |
31/05/2030 |
Valid |
|
WT00046692-2025 |
29/05/2025 |
31/05/2030 |
Valid |
|
WT00046655-2025 |
03/06/2025 |
30/06/2030 |
Valid |
|
WT00046819-2025 |
31/07/2025 |
31/07/2030 |
Valid |
|
WT00047343-2025 |
29/09/2025 |
30/09/2030 |
Valid |
|
WT00047250-2025 |
12/11/2025 |
30/11/2030 |
Valid |
|
WT00048473-2026 |
17/04/2026 |
30/04/2031 |
Valid |
|
WT00048492-2026 |
30/04/2026 |
30/04/2031 |
Valid |
|
WT00048751-2026 |
06/07/2026 |
31/07/2031 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0179-26 |
23/02/2026 |
22/08/2026 |
Valid till 22/08/2026 |
|
GW-RN0560-26 |
07/05/2026 |
31/10/2026 |
Valid |
|
GW-RN0577-26 |
15/05/2026 |
14/08/2026 |
Valid till 14/08/2026 |
|
GW-RN0602-26 |
22/05/2026 |
21/08/2026 |
Valid till 21/08/2026 |
|
GW-RN0746-26 |
09/06/2026 |
08/09/2026 |
Valid |
|
GW-RN0765-26 |
19/06/2026 |
18/12/2026 |
Valid |
|
GW-RN0961-26 |
17/07/2026 |
14/01/2027 |
Valid |
|
GW-RN1073-26 |
23/08/2026 |
22/02/2027 |
Valid |
|
GW-RN1075-26 |
22/08/2026 |
21/12/2026 |
Valid |
Table 1.9 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/08
|
Permit / License Name/No. |
Valid Period |
Status |
|
|
From |
To |
||
|
Environmental Permit |
|||
|
EP-472/2013/A |
21/11/2013 |
N/A |
Valid |
|
EP-476/2013 |
21/11/2013 |
N/A |
Valid |
|
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
|
10025562 |
13/01/2026 |
N/A |
Valid |
|
Billing Account for Disposal of Construction Waste |
|||
|
7056971 |
16/12/2025 |
N/A |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN:5213-625-G3123-01 |
03/02/2026 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution Control Ordinance |
|||
|
WT00049068-2026 |
05/08/2026 |
31/07/2031 |
Valid |
|
WT00049073-2026 |
05/08/2026 |
31/07/2031 |
Valid |
|
WT00049078-2026 |
05/08/2026 |
31/07/2031 |
Valid |
|
Construction Noise Permit (CNP) |
|
|
|
|
GW-RN0806-26 |
17/06/2026 |
16/09/2026 |
Valid |
|
GW-RN0978-26 |
24/07/2026 |
23/09/2026 |
Valid |
|
GW-RN1123-26 |
29/08/2026 |
28/11/2026 |
Valid |
2.2.1 According to the EM&A Manual, the approved updated EM&A Manual for the First Phase, the designated locations for impact air quality monitoring in related to the work contracts in the reporting period are listed in Table 2.1 and their locations are shown in Figure 2.1 and Figure 2.2.
Table 2.1 Summary of Impact Air Quality Monitoring Stations in related to the Works Contracts in the Reporting Period
|
Monitoring Station(s) |
Works Contract(s) |
ASR ID in EIA |
Planned(3) or Existing |
Monitoring Location(s) |
|
KTN-DMS1 |
ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/05 |
KTN-19 |
Planned |
Nursery Classes and Kindergarten; Post Offices |
|
KTN-DMS2 |
ND/2024/01, ND/2024/02 |
KTN-90 |
Planned |
Nursery Classes and Kindergarten (2 nos); District Elderly Community Centre |
|
KTN-DMS3 |
ND/2024/01, ND/2024/02, ND/2024/03 |
KTN-326 |
Planned |
Village Resite |
|
KTN-DMS4(B)(1)(2) |
ND/2024/01, ND/2024/03, ND/2024/05 |
KTN-E70 |
Existing |
Temporary Structure at Pak Shek Au |
|
FLN-DMS1 |
ND/2024/07, ND/2024/08 |
FLN-E62 |
Existing |
Scattered Village Houses North of Proposed Potential Ecopark |
|
FLN-DMS2 |
ND/2024/06, ND/2024/07 |
FLN-E243 |
Planned |
Residential Building, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre, Residential Home for the Elderly, Post Office |
|
FLN-DMS5, FLN-DMS5(A) |
ND/2024/07, ND/2024/08 |
FLN-E124 |
Existing |
Noble Hill / Good View New Village |
|
FLN-DMS6(A) |
ND/2024/03, ND/2024/04 |
DMS-10 |
Existing |
Choi Ngan House, Choi Po Court |
|
FLN-DMS7 |
ND/2024/06, ND/2024/07, ND/2024/08 |
FLN-20 |
Planned |
Planned premise for Weapon Training Division |
Remarks:
(1) KTN-DMS4(B) is the alternative air monitoring stations proposed to replace KTN-DMS4.
(2) As KTN-DMS4 - Temporary structure near Fanling Highway (near Pak Shek Au) is no longer as existing ASR, air quality monitoring station should be relocated to the alternative dust monitoring location according to the updated EM&A Manual, Section 2.6.2. According to Figure 3.1 of Approved EIA report and site visits conducted in June 2022, ASR at near KTN-E70 – Temporary Structure near Fanling Highway near Pak Shek Au is considered as the most representative alternative station KTN-DMS4(B) for air quality monitoring for KTN-DMS4 (i.e. KTN-E162).
(3) Impact monitoring will be carried out when the planned sensitive receivers are commissioned.
Table 2.2 Parameters Measured in the Impact Air Quality Monitoring
|
Parameter(s) |
Frequency(1)(2) |
|
1-hour TSP |
Three times / 6 days |
|
24-hour TSP |
Once / 6 days |
Remarks:
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
|
Monitoring Station(s) |
Equipment |
Model |
Manufacturer |
Quantity |
|
KTN-DMS4(B)(1), FLN-DMS5(1), FLN-DMS5(A)(1) |
Dust Monitor (1-hour and 24-hour TSP) |
AEROCET-831 |
Met One Instruments |
5 |
|
FLN-DMS1(1) |
Dust Monitor (1-hour TSP) |
|||
|
HVS Sampler (24-hour TSP) |
TE-5170 |
Tisch |
1 |
|
|
FLN-DMS6(A)(2) |
Dust Monitor (1-hour and 24-hour TSP) |
LD-5R |
Sibata |
1 |
Table 2.3 Air Quality Monitoring Equipment
Remarks:
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
Instrumentation
(AEROCET-831)
· Place the dust meter at least 1.3 meters above ground;
· Press and hold the Power key momentarily to power on the unit and make sure that the battery level was not flash or in low level;
· Allow the instrument to stand for about 3 second to display the Sample Screen minutes;
· Press the START / STOP key to run the internal vacuum pump for 1 minute and be ready to use;
· Use the select dial to select the PM range and press the START / STOP key to start a measurement;
· Finally, push the START/STOP key to stop the measurement after 24-hour sampling;
· Information such as sampling date, time, value and site condition were recorded during the monitoring period; and
· All data were recorded in the data logger for further data processing.
Maintenance/Calibration
· Check and calibrate the meters by High Volume Sampler (HVS) to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.
Instrumentation
(TISCH Model: TE-5170 / TE-5170X)
· A horizontal platform with appropriate support was provided to secure the samplers against gusty wind. the dust meter at least 1.3 meters above ground;
· No two samplers were placed less than 2 metres apart.
· The distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler.
· A minimum of 2 metres of separation from walls, parapets and penthouses was required for rooftop samples.
· A minimum of 2 metres separation from any supporting structure, measured horizontally was required.
· No furnaces or incineration flues were nearby.
· Airflow around the sampler was unrestricted.
· The sampler were more than 20 metres from the drip line.
· Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.
· Permission and access to monitoring stations have been obtained to set up the samplers.
· A secured supply of electricity was provided to operate the samplers.
Filters Preparation
Operating/Analytical Procedures
· Prior to the commencement of dust sampling, the flow rate of the HVS was properly set (between 1.1 m3 /min. and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50;
· The power supply was checked to ensure the sampler worked properly;
· On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air quality monitoring station;
· The filter holding frame was then removed by loosening the four nuts and carefully a weighted and conditioned filter was centered with the stamped number upwards, on a supporting screen;
· The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame was then tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges;
· The shelter lid was closed and secured with the aluminium strip;
· The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number);
· After sampling, the filter was removed and kept in a clean and tightly sealed plastic bag. The filter paper was then returned to the HOKLAS accredited laboratory (Wellab Ltd.) for reconditioning in the humidity-controlled chamber followed by accurate weighting by an electronic balance with a readout down to 0.1mg. The elapsed time was also recorded; and
· Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature should be between 25°C and 30°C and did not vary by more than ±3°C; the RH should be < 50% and did not vary by more than ±5%. A convenient working RH is 40%. Weighing results were returned for further analysis of TSP concentrations collected by each filter
Maintenance/Calibration
· The high-volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply are in good working conditions; and
· All HVS were calibrated (five point calibration) using Calibration Kit prior to the commencement of baseline monitoring and thereafter at bi-monthly intervals.
Instrumentation
(Sibata Model: LD-5R)
· Placed the dust meters at least 1.3m above ground
· Set POWER to “ON” and make sure that the battery level not flashed or in low level;
· Pulled the air sampling inlet cover up;
· Pushed the knob at MEASURE position;
· Set time/mode setting to [BG] by pushing the time setting switch. Then, started the background measurement by pushing the start/stop switch once. It took 6 sec. to complete the background measurement;
· Turned knob to SENSI. ADJ position and pressed in;
· Pushed Start/Stop switch once;
· Gently returned knob to the MEASURE position;
· Pushed the time setting switch to change the time setting display to [LOG] at the bottom left of the liquid crystal display;
· Removed the cap and started measurement; and
· Information such as sampling date, time, count value and site condition were recorded during the monitoring period.
Maintenance/Calibration
· Direct reading dust meter shall be used in determining 1-hour TSP and 24-hour TSP at air quality monitoring points. The direct reading dust meters have been calibrated against high volume samplers (HVSs) bi-monthly. A 2-day, three 3-hour measurement results per day from direct reading dust meters were taken to compare with the sampling results from the HVSs. The correlation between the direct reading dust meters and the HVSs were then concluded. By accounting for the correlation factor, the direct reading dust meters are considered to achieve comparable results as that of the HVSs.
· The HVS used to calibrate the direct dust monitor will need to be calibrated bi-monthly. Details of maintenance and calibration for the HVS refers to Section 2.5.8. Calibration for the air quality monitoring equipment is attached to the Appendix 2.2.
Table 2.4 Action and Limit Levels for 1-hour TSP Air Quality Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
297 |
500 |
|
FLN-DMS1 |
303 |
500 |
|
FLN-DMS5 |
279 |
500 |
|
FLN-DMS6(A) |
286 |
500 |
Table 2.5 Action and Limit Levels for 24-hour of TSP Air Quality Monitoring
|
Monitoring Station |
AL (μg/m3) |
LL (μg/m3) |
|
KTN-DMS4(B) |
192 |
260 |
|
FLN-DMS1 |
150 |
260 |
|
FLN-DMS5(A) |
153 |
260 |
|
FLN-DMS6(A) |
157 |
260 |
Table 2.6 Summary Table of 1-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
60 |
106 |
32 |
297 |
500 |
|
FLN-DMS1(1) |
76 |
130 |
48 |
303 |
500 |
|
FLN-DMS5(1) |
63 |
108 |
35 |
279 |
500 |
|
FLN-DMS6(A)(2) |
77 |
97 |
49 |
286 |
500 |
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
Table 2.7 Summary Table of 24-hour TSP Monitoring Result during the Reporting Month
|
Monitoring Station |
Averaged Measured Value (μg/m3) |
Maximum Measured Value (μg/m3) |
Minimum Measured Value (μg/m3) |
Action Level (μg/m3) |
Limit Level, (μg/m3) |
|
KTN-DMS4(B)(1) |
60 |
95 |
35 |
192 |
260 |
|
FLN-DMS1(1) |
24 |
30 |
21 |
150 |
260 |
|
FLN-DMS5(A) (1) |
72 |
114 |
57 |
153 |
260 |
|
FLN-DMS6(A)(2) |
85 |
110 |
67 |
157 |
260 |
Remarks:
(1) The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.
(2) The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.
Table 3.1 Construction Noise Monitoring Stations near in related to the Works Contracts in the Reporting period
|
Monitoring Station(s) |
Works Contract(s) |
NSR EIA ID(s) |
Location(s) |
Planned(2) Or Existing |
Type of Measurement |
|
CP-KTN-NMS1 |
ND/2024/01, ND/2024/02 |
CP-NMS1 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS2 |
ND/2024/01, ND/2024/02 |
CP-NMS2 |
Residential Building at Ma Tso Lung |
Existing |
Free-Field(1) |
|
CP-KTN-NMS3 |
ND/2024/01, ND/2024/02 |
CP-NMS3 |
Fung Kong Garden |
Existing |
|
|
CP-KTN-NMS4(3) |
ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/05 |
CP-NMS5 |
Primary School |
Planned |
|
|
CP-KTN-NMS5 |
ND/2024/06, ND/2024/08 |
CP-NMS7 |
N/A |
Existing |
Free-Field(1) |
|
CP-KTN-NMS6 |
ND/2024/01, ND/2024/02 |
N/A |
Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Existing |
Façade |
|
CP-KTN-NMS7 |
ND/2024/01, ND/2024/02 |
CP-NMS4 |
Oi Lok Home |
Existing |
Free-Field(1) |
|
CP-FLN-NMS4(A)(4) |
ND/2024/04 |
CP-NMS6 |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Existing |
Free-Field(1) |
|
CP-FLN-NMS1 |
ND/2024/06, ND/2024/07 |
CP-NMS10 |
Belair Monte |
Existing |
Facade |
|
CP-FLN-NMS3(3) |
ND/2024/06, ND/2024/07 |
CP-NMS12 |
Secondary School |
Planned |
Free-Field(1) |
|
CP-FLN-NMS5 |
ND/2024/07, ND/2024/08 |
CP-NMS8 |
Man Kok Village |
Existing |
Free-Field(1) |
|
CP-FLN-NMS6 |
ND/2024/07, ND/2024/08 |
CP-NMS9 |
Woodland Crest |
Existing |
Façade |
Remarks:
(1) For Free Field measurement, +3 dB(A) should be added to the measured results.
(2) Impact monitoring will be carried out when the planned sensitive receivers are commissioned.
(3) As confirmed with Engineer Representative, the planned school at CP-KTN-NMS4 and CP-FLN-NMS3 are not constructed yet. Thus, the impact noise monitoring will be carried out at monitoring station CP-KTN-NMS4 and CP-FLN-NMS3 after the construction and occupation of the planned school. No noise monitoring of the mentioned station was carried out in this reporting period.
(4) Alternative monitoring stations to the corresponding original monitoring stations.
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
|
Monitoring Station |
Parameter |
Frequency and Duration |
|
CP-KTN-NMS1(2), CP-KTN-NMS2(1), CP-KTN-NMS3(1), CP-KTN-NMS5(1), CP-KTN-NMS6(1),CP-KTN-NMS7(2),CP-FLN-NMS1(1), CP-FLN-NMS4(A)(2), CP-FLN-NMS5(2), CP-FLN-NMS6(2) |
Leq(30mins), L10 and L90 (as six consecutive Leq,5min readings) |
Once every week throughout the construction phase |
Remark:
(1) The noise monitoring was conducted by First Phase ET during the reporting period.
(2) The noise monitoring was conducted by Remaining Phase Environmental Team during the reporting period.
· For façade measurement, the monitoring station was set at a point 1 m from the exterior of the sensitive receivers building façade and set at a position 1.2 m above the ground. For free-field measurement, the monitoring station was set at a position 1.2 m above the ground.
· The battery condition was checked to ensure good functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the interval were set as follows:
- Frequency weighting: A
- Time weighting: Fast
- Interval: 30 minutes (Leq(30mins))
· Prior to and after each noise measurement, the meter was calibrated using an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement will be required after re-calibration or repair the equipment.
· At the end of the monitoring period, the values of Leq, L10 and L90 were recorded. In addition, noise sources were recorded on a standard record sheet.
Table 3.3 Construction Noise Monitoring Equipment
|
Equipment |
Manufacturer |
Model |
No. of Equipment |
Serial No. |
|
Sound Level Meter |
NTi Audio(2) |
XL2 |
1 |
A2A-17638-E0 |
|
XL3 |
2 |
A3A-01220-F0 A3A-01231-F0 |
||
|
BSWA(1) |
BSWA 308 |
1 |
580017 |
|
|
Acoustic Calibrator |
RION(2) |
NC-75 |
3 |
34724244 35124527 34567799 |
|
NC-74 |
1 |
34615222 |
||
|
SVANTEK(1) |
SV30A |
1 |
24780 |
Remark:
(1) The noise monitoring equipment was used by First Phase ET during the reporting period.
(2) The noise monitoring equipment was used by Remaining Phase Environmental Team during the reporting period.
· The microphone head of the sound level meter and calibrator were regularly cleaned with a soft cloth;
· The sound level meter and acoustic calibrator were calibrated annually; and
· The accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency immediately prior to and following each noise measurement. Measurements were accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.
Table 3.4 Action and Limit Levels for Construction Noise Monitoring
|
Time Period |
Action |
Limit Level |
|
07:00 – 19:00 on normal weekdays |
When one or more documented complaints are received |
75 dB(A) |
Remark:
(1) Time period for construction noise monitoring during normal construction working hour (0700-1900 Monday to Saturday).
(2) If works are to be carried out during restricted hours, the conditions stipulated in the Construction Noise Permit (CNP) issued by the Noise Control Authority have to be followed.
(3) 70 dB(A) and 65 dB(A) for schools during normal teaching periods and school examination periods, respectively.
Table 3.5 Summary of Construction Noise Monitoring Results during the Reporting Month
|
Works Contracts |
Monitoring Stations |
Noise Levels, Leq(30min), dB(A) |
Baseline Levels, dB(A) |
Limit Levels, dB(A) |
|
ND/2024/01, ND/2024/02 |
CP-KTN-NMS1(1)(3) |
48.8 – 62.1 |
65.7 |
75 |
|
CP-KTN-NMS2(1)(2) |
53.9 – 65.8 |
58.6 |
||
|
CP-KTN-NMS3(1)(2) |
54.4 – 59.5 |
51.6 |
||
|
CP-KTN-NMS6(2) |
61.3 – 68.9 |
55.1 |
||
|
CP-KTN-NMS7(1)(3) |
63.5 – 68.2 |
64.6 |
||
|
ND/2024/04 |
CP-FLN-NMS4(A)(1)(3)(4) |
71.0 – 71.9 |
72.4 |
|
|
ND/2024/06, ND/2024/08 |
CP-KTN-NMS5(1)(2) |
52.4 – 66.8 |
57.2 |
|
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1(2) |
65.5 – 68.0 |
69.9 |
|
|
ND/2024/07, ND/2024/08 |
CP-FLN-NMS5(1)(3) |
64.3 – 65.5 |
69.5 |
|
|
CP-FLN-NMS6(3) |
53.3 – 56.6 |
55.0 |
Remarks:
(1) For Free Field measurement, +3 dB(A) was added to the measured results.
(2) The noise monitoring was conducted by First Phase ET during the reporting period.
(3) The noise monitoring was conducted by Remaining Phase Environmental Team during the reporting period.
(4) Alternative monitoring stations to the corresponding original monitoring stations.
Table 3.6 Summary of Observations at Noise Monitoring Stations
|
Works Contracts |
Monitoring Stations |
Location |
Major Noise Sources |
|
ND/2024/01, ND/2024/02 |
CP-KTN-NMS1 |
Residential Building at Ma Tso Lung |
Household noise (dog barking) from nearby village house |
|
CP-KTN-NMS2 |
Residential Building at Ma Tso Lung |
Road Traffic Noise, Large Exhaust Fan |
|
|
CP-KTN-NMS3 |
Fung Kong Garden |
Road Traffic Noise |
|
|
CP-KTN-NMS4 |
Primary School |
N/A(1) |
|
|
CP-KTN-NMS6 |
Ho Sheung Heung, Hau Ku Shek Ancestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery |
Road Traffic Noise |
|
|
CP-KTN-NMS7 |
Oi Lok Home |
Road Traffic Noise |
|
|
ND/2024/04 |
CP-FLN-NMS4(A)(2) |
Choi Ying House, Choi Po Court (Choi Yuen Estate) |
Excavation Works, Road Traffic Noise |
|
ND/2024/06, ND/2024/08 |
CP-KTN-NMS5 |
N/A |
Road Traffic Noise |
|
ND/2024/06, ND/2024/07 |
CP-FLN-NMS1 |
Belair Monte |
Road Traffic Noise |
|
CP-FLN-NMS3 |
Secondary School |
N/A(1) |
|
|
ND/2024/07, ND/2024/08 |
CP-FLN-NMS5 |
Man Kok Village |
Road Traffic Noise |
|
CP-FLN-NMS6 |
Woodland Crest |
No construction activity and other noise source was observed |
Remarks:
(1) No impact noise monitoring was carried out at the monitoring station. Thus, not applicable (N/A).
(2) Alternative monitoring stations to the corresponding original monitoring stations.
Table 4.1 Summary of Water Quality Monitoring Locations
|
New Monitoring Station(s) |
Original Monitoring Station ID(s) |
Description |
Location(s) |
Measurement Period |
|
KTN NDA |
||||
|
KTN-CS1 |
CS1 |
Control Station for KTN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
KTN-IS1 |
IS1 |
Impact Station for KTN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
|
FLN NDA |
||||
|
FLN-CS1 |
CS2 |
Control Station for FLN NDA |
Centreline of river, upstream of the channel |
During construction of channel |
|
FLN-IS1 |
IS2 |
Impact Station for FLN NDA |
Centreline of river, downstream of the channel |
During construction of channel |
Table 6.1 Summary of Monitoring Activities, Relevant Contracts, and Corresponding Transects
|
Monitoring Activity |
Relevant Works Contract(s) |
Relevant Transect(s)/Monitoring Station(s) |
|
|
First Phase ET |
Remaining Phase ET |
||
|
Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung, Sheung Yue, and Shek Sheung Rivers and Long Valley |
ND/2024/01* |
T1, T2, T3, T5 |
- |
|
ND/2024/02* |
T1, T2, T3, T5 |
T4 |
|
|
ND/2024/03* |
T1, T2, T3, T5 |
- |
|
|
ND/2024/04* |
- |
T4 |
|
|
ND/2024/05* |
N/A(1) |
N/A(1) |
|
|
ND/2024/06* |
T1, T2, T3 |
- |
|
|
ND/2024/07* |
T1, T2, T3 |
T4 |
|
|
ND/2024/08* |
T1, T2, T3 |
T4 |
|
|
Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley |
ND/2024/01*^ |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
ND/2024/02*^ |
MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10 |
- |
|
|
ND/2024/03* |
N/A(2) |
N/A(2) |
|
|
ND/2024/04* |
N/A(2) |
N/A(2) |
|
|
ND/2024/05* |
N/A(2) |
N/A(2) |
|
|
ND/2024/06* |
N/A(2) |
N/A(2) |
|
|
ND/2024/07*^ |
MS_11, MS_12, MS_13, MS_14, MS_15 |
- |
|
|
ND/2024/08*^ |
MS_11, MS_12, MS_13, MS_14, MS_15 |
N/A(2) |
|
|
|
|
|
|
|
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution |
ND/2024/01* |
T1 |
- |
|
ND/2024/02* |
T1, T6 |
- |
|
|
ND/2024/03* |
T4 |
- |
|
|
ND/2024/04* |
N/A(3) |
N/A(3) |
|
|
ND/2024/05* |
T4, T6 |
- |
|
|
ND/2024/06* |
- |
T2 |
|
|
ND/2024/07* |
T3 |
- |
|
|
ND/2024/08* |
T3 |
- |
|
Remarks:
(1) Contracts that are located relatively far from river channels.
(2) Contracts that are located relatively far from Ma Tso Lung and Siu Hang San Tsuen streams.
(3) Contracts that are located relatively far from the Ecological Sensitive Habitats as identified in the EIA.
(4) * = active works contracts (ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06, ND/2024/07 and ND/2024/08); ^ = monitoring only in April – October’.
Monitoring Methodology
Monitoring Parameters
· Abundance of birds;
· Types of habitats utilized by birds; and
· Notable bird behaviours such as roosting, feeding, nesting and presence of juveniles.
Monitoring Location
Table 6.2 Summary of Active Works Contracts and Corresponding Transects
|
Monitoring |
Relevant Works Contract(s) |
|||||||
|
ND/2024/01 |
ND/2024/02 |
ND/2024/03 |
ND/2024/04 |
ND/2024/05 |
ND/2024/06 |
ND/2024/07 |
ND/2024/08 |
|
|
T1. Ng Tung River |
✓ |
✓ |
✓ |
|
|
✓ |
✓ |
✓ |
|
T2. Ng Tung River |
✓ |
✓ |
✓ |
|
|
✓ |
✓ |
✓ |
|
T3. Sheung Yue River |
✓ |
✓ |
✓ |
|
|
✓ |
✓ |
✓ |
|
T4. Shek Sheung River |
|
✓ |
|
✓ |
|
|
✓ |
✓ |
|
T5. Long Valley |
✓ |
✓ |
✓ |
|
|
|
|
|
Monitoring Frequency
Table 6.3 Monitoring Programme for Waterbirds Monitoring, August 2026
|
Week |
Date |
Transect(1) |
|
1 |
3 Aug 2026 |
T1, T2, T4 |
|
5 Aug 2026 |
T3, T4, T5 |
|
|
2 |
11 Aug 2026 |
T3, T5 |
|
12 Aug 2026 |
T4 |
|
|
13 Aug 2026 |
T1, T2, T4 |
|
|
3 |
17 Aug 2026 |
T4 |
|
18 Aug 2026 |
T1, T2 |
|
|
19 Aug 2026 |
T3, T4, T5 |
|
|
4 |
24 Aug 2026 |
T4 |
|
25 Aug 2026 |
T3, T5 |
|
|
27 Aug 2026 |
T1, T2, T4 |
Remarks:
(1) Transects T1, T2, T3, and T5 are relevant to Works Contract ND/2024/01 and ND/2024/03; Transect T4 is relevant to Works Contract ND/2024/04; Transects T1, T2, and T3 are relevant to Works Contract ND/2024/06; Transects T1, T2, T3 and T4 are relevant to Works Contract ND/2024/07 and ND/2024/08; Transect T1, T2, T3, T4 and T5 are relevant to Works Contract No. ND/2024/02.
Monitoring Results
Table 6.4 Summary Table of Waterbird Monitoring Results Relative to Corresponding Action and Limit Levels, August, Transects T1, T2, T3, T4 and T5
|
Monitoring Parameter |
Result in Reporting Month |
Baseline Level in Corresponding Month |
Action |
Limit |
|
|
T1, T2 and T3 |
|||||
|
Mean abundance of large waterbirds using Ng Tung River, Sheung Yue River and Shek Sheung River (3) |
52 |
17 |
12 |
8 |
|
|
Mean abundance of Chinese Pond Heron using Ng Tung River, Sheung Yue River and Shek Sheung River |
15 |
13 |
9 |
7 |
|
|
T4 |
|||||
|
Mean abundance of large waterbirds using Shek Sheung River (3) |
15 |
5 |
4 |
3 |
|
|
Mean abundance of Chinese Pond Heron using Shek Sheung River |
5 |
4 |
3 |
2 |
|
|
T5 Long Valley |
|||||
|
Mean Abundance of birds (all species) recorded in LVNP |
703 |
592 |
414 |
296 |
|
|
Mean abundance of the Chinese Pond Heron |
27 |
27 |
19 |
13 |
|
|
Environmental disturbance and damage from activities in LVNP |
- |
- |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
Activity likely to cause unacceptable environmental disturbance or damage noted in LVNP. |
|
Remarks:
(1) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(2) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
(3) Large waterbird species for mean abundance calculation include Great Cormorant (Phalacrocorax carbo); Grey Heron (Ardea cinerea); Great Egret (Ardea alba); Intermediate Egret (Ardea intermedia); Little Egret (Egretta garzetta) and Chinese Egret (Egretta eulophotes).
Monitoring Parameters
· Species composition and abundance;
· Distribution of invertebrates and fish fauna; and
· Specify species of conservation importance, if any.
Monitoring Locations
|
· MS_01 |
· MS_02 |
· MS_03 |
· MS_04 |
· MS_05 |
|
· MS_06 |
· MS_07 |
· MS_08 |
· MS_09 |
· MS_10 |
And the relevant monitoring stations for Works Contract ND/2024/07 and ND/2024/08 are:
|
· MS_11 |
· MS_12 |
· MS_13 |
· MS_14 |
· MS_15 |
Monitoring Frequency
Monitoring Results
Table 6.5 Summary Table of Monitoring Results for Aquatic Invertebrates Relative to Action and Limit Levels, August, Monitoring Station MS_01 – MS_15
|
Monitoring Station |
Result in Reporting Month (August 2026) (1) |
Baseline Level in Corresponding Month (August 2019) (1) |
Action Level(2) |
Limit Level(3) |
|
MS_01 |
0 |
0 |
N/A |
N/A |
|
MS_02 and MS_03 |
2 |
1 |
N/A |
N/A |
|
MS_04, MS_06 and MS_07 |
3 |
1 |
N/A |
N/A |
|
MS_05 |
0 |
0 |
N/A |
N/A |
|
MS_08, MS_09 and MS_10 |
8 |
0 |
N/A |
N/A |
|
MS_11 |
0 |
1 |
N/A |
N/A |
|
MS_12 |
0 |
0 |
N/A |
N/A |
|
MS_13 and MS_14 |
1 |
1 |
N/A |
N/A |
|
MS_15 |
1 |
0 |
N/A |
N/A |
Remarks:
(1) Number of native species (species richness) recorded.
(2) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(3) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
Table 6.6 Summary Table of Monitoring Results for Fish Species Relative to Action and Limit Levels, August, Monitoring Station MS_01 – MS_15
|
Monitoring Station |
Result in Reporting Month (August 2026) (1) |
Baseline Level in Corresponding Month (August 2019) (1) |
Action Level(2) |
Limit Level(3) |
|
MS_01 |
0 |
0 |
N/A |
N/A |
|
MS_02 and MS_03 |
0 |
1 |
N/A |
N/A |
|
MS_04, MS_06 and MS_07 |
0 |
1 |
N/A |
N/A |
|
MS_05 |
0 |
0 |
N/A |
N/A |
|
MS_08, MS_09 and MS_10 |
0 |
1 |
N/A |
N/A |
|
MS_11 |
0 |
0 |
N/A |
N/A |
|
MS_12 |
0 |
0 |
N/A |
N/A |
|
MS_13 and MS_14 |
0 |
0 |
N/A |
N/A |
|
MS_15 |
1 |
2 |
N/A |
1 |
Remarks:
(1) Number of native species (species richness) recorded.
(2) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(3) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution
Monitoring Methodology
Terrestrial Mammal
Herpetofauna (Amphibians and Reptiles)
Butterfly and Odonates
Monitoring Parameters
· Species composition;
· Abundance;
· Distribution for fauna observed; and
· Species of conservation importance would be specified.
Monitoring Location
· T1. Ma Tso Lung riparian zone and associated wetland habitats; green belt areas E1-8, D1-8 and G1-3 in KTN NDA; AGR zone C2-4 and C2-2 in KTN NDA, and area north of Ng Tung River;
· T2. Fanling North Freshwater Service Reservoir
· T3. Area west of Siu Hang San Tsuen Stream;
· T4. South side of Fanling Highway and Castle Peak Road in the vicinity of Pak Shek Au;
· T5. Area west and east of the southern limit of the FLN NDA work area; and
· T6. Areas in the western part of KTN.
Monitoring Frequency
|
Responsible ET |
Date |
Transect(1) |
|
First Phase ET |
17 August 2026 |
T3, T4 |
|
26 August 2026 |
T1, T6 |
|
|
Remaining Phase ET |
26 August 2026 |
T2 |
Remarks:
(1) Transect T1 is relevant to Works Contract ND/2024/01 and Works Contract ND/2024/02; Transect T2 is relevant to Works Contract ND/2024/06; Transect T3 is relevant to Works Contracts ND/2024/07 and ND/2024/08; Transect T4 is relevant to Works Contract ND/2024/03 and ND/2024/05; Transect T6 is relevant to Works Contract ND/2024/02 and ND/2024/05.
Monitoring Results
Terrestrial Mammals
Herpetofauna (Amphibians and Reptiles)
Butterfly and Odonates
Summary of Monitoring Results
Table 6.8 Summary Table of Monitoring Results for Non-aquatic Fauna Relative to Action and Limit Levels, August 2026, Transect T1, T2, T3, T4 and T6
|
Monitoring Parameter |
Result in |
Baseline Level in Corresponding Month (August 2019) (1) |
Action Level(2) |
Limit Level(3) |
|
T1 |
||||
|
Terrestrial Mammals |
1 |
2 |
N/A |
1 |
|
Herpetofauna |
6 |
9 |
6 |
5 |
|
Odonates |
5 |
17 |
12 |
9 |
|
Butterflies |
18 |
23 |
16 |
12 |
|
T2 |
||||
|
Terrestrial Mammals |
7 |
1 |
N/A |
N/A |
|
Herpetofauna |
4 |
4 |
3 |
2 |
|
Odonates |
4 |
5 |
4 |
3 |
|
Butterflies |
14 |
17 |
12 |
9 |
|
T3 |
||||
|
Terrestrial Mammals |
2 |
1 |
N/A |
N/A |
|
Herpetofauna |
5 |
7 |
5 |
4 |
|
Odonates |
2 |
13 |
9 |
7 |
|
Butterflies |
8 |
10 |
7 |
5 |
|
T4 |
||||
|
Terrestrial Mammals |
2 |
1 |
N/A |
N/A |
|
Herpetofauna |
8 |
6 |
4 |
3 |
|
Odonates |
3 |
2 |
N/A |
1 |
|
Butterflies |
10 |
13 |
9 |
7 |
|
T6 |
||||
|
Terrestrial Mammals |
0 |
0 |
N/A |
N/A |
|
Herpetofauna |
6 |
9 |
6 |
5 |
|
Odonates |
4 |
11 |
8 |
6 |
|
Butterflies |
11 |
14 |
10 |
7 |
Remarks:
(1) Number of species (species richness) recorded; the results in the reporting month for terrestrial mammals, herpetofauna and odonates are calculated based on the number of native species recorded along the transects.
(2) Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.
(3) Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.
Details of the Influencing Factors
Survey Summary
· Compendium Method 1O-3.1 Selection, Preparation and Extraction of Filter Material, Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999; and Compendium Method 1O-3.5 determination of Metals in Ambient Particulate Matter using Inductively Coupled Plasma/Mass Spectrometry (ICP/MS., Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999.
Table 8.1 Location of Ambient Arsenic Monitoring station
|
Monitoring Station(s) |
Location(s) |
Works Contract(s) |
|
KTN-DMS4(C)(1)(2) |
Workshop Northwest to Pak Shek Au |
ND/2024/01, ND/2024/03, ND/2024/05 |
Remarks:
(1) The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
(2) Monitoring at the original location of KTN-DMS4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS4(C)) was proposed by First Phase ET to substitute KTN-DMS4 and KTN-DMS4(A) (the previous relocated location for KTN-DMS4). Monitoring have been conducted at KTN-DMS4(C) since 24 July 2026.
Table 8.2 Ambient Arsenic Monitoring Equipment
|
Monitoring Station |
Equipment |
Manufacturer |
Model |
No. of Equipment |
|
KTN-DMS4(C)(1)(2) |
Calibrator |
TISCH |
TE-5025A |
1 |
|
HVS Sampler (RSP) |
TISCH |
TE-6070X |
1 |
Remarks:
(1) The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
(2) Monitoring at the original location of KTN-DMS4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS4(C)) was proposed by First Phase ET to substitute KTN-DMS4 and KTN-DMS4(A) (the previous relocated location for KTN-DMS4). Monitoring have been conducted at KTN-DMS4(C) since 24 July 2026.
Table 8.3 Impact Ambient Arsenic Monitoring Parameters, Frequency and Duration
|
Parameters |
Frequency(1) |
|
24-hour RSP (Ambient Arsenic) |
Once/ 6 days |
Remark:
1. The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.
Instrumentation
· a horizontal platform with appropriate support to secure the samplers against gusty wind was provided;
· no two samplers were placed less than 2 meters apart;
· the distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler;
· a minimum of 2 meters of separation from walls, parapets and penthouses was required for rooftop samplers;
· a minimum of 2 meters separation from any supporting structure, measured horizontally was required;
· no furnace or incinerator flue was nearby;
· airflow around the sampler was unrestricted;
· the sampler was more than 20 meters from the dripline;
· any wire fence and gate, to protect the sampler, were not cause any obstruction during monitoring;
· permission was obtained to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity was needed to operate the samplers
Operating/analytical procedures for the operation of HVS
· Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 1.1 m3 /min. and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50;
· The power supply was checked to ensure the sampler worked properly. On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station;
· The filter holding frame was then removed by loosening the four nuts and a weighted and conditioned filter was carefully centered with the stamped number upwards, on a supporting screen;
· The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame was then tightened to the filter holder with swing bolts. The applied pressure was sufficient to avoid air leakage at the edges;
· The shelter lid was closed and secured with the aluminium strip;
· The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number);
· After sampling, the filter was removed and sent to the Wellab Ltd. for weighing. The elapsed time was also recorded; and
· Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature was between 25°C and 30°C and did not vary by more than ±3°C; the relative humidity (RH) was < 50% and did not vary by more than ±5%. A convenient working RH was 40%. Weighing results were further analysis of RSP concentrations collected by each filter.
· The high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply were in good working condition; and
· High volume samplers were calibrated at bi-monthly intervals using TE-5025A Calibration Kit throughout all stages of the ambient arsenic monitoring.
Table 8.4 Result Summary Against Action and Limit Levels for 24-hour RSP Monitoring Results (Ambient Arsenic)
|
Contract No. |
Monitoring Date |
Monitoring Station |
Concentration (ƞg/m3) |
AL (ƞg/m3) |
LL (ƞg/m3) |
||
|
ND/2024/01 ND/2024/03 ND/2024/05 |
5/8/2026 |
KTN-DMS4(C)* |
4.02 |
9.36 |
11.7 |
||
|
11/8/2026 |
4.69 |
||||||
|
17/8/2026 |
4.78 |
||||||
|
21/8/2026 |
4.36 |
||||||
|
27/8/2026 |
3.82 |
||||||
Remark:
* The 24-hour RSP monitoring for ambient arsenic was conducted by First Phase ET during the reporting period. Monitoring at the original location of KTN-DMS4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS4(C)) was proposed by First Phase ET to substitute KTN-DMS4 and KTN-DMS4(A) (the previous relocated location for KTN-DMS4). Monitoring have been conducted at KTN-DMS4(C) since 24 July 2026.
Ø Excavation Locations: N/A
Ø Manholes and Chambers: N/A
Ø Relocation of monitoring wells: N/A
Ø Any other Confined Spaces: N/A
Table 10.1 Location of Construction Vibration Monitoring
|
EP No. |
Contact No. |
Monitoring Station(s) |
Nature of Cultural Heritage |
Location(s) |
|
Nil. |
Nil. |
Nil. |
Nil. |
Nil. |
Table 10.2 Vibration Monitoring Plan
|
EP No. |
Contact No. |
Monitoring Station(s)* |
Distance with Construction Works |
Monitoring Plan |
|
Nil |
Nil |
NIl |
Within 50m
Within 75m
Within 100m |
Daily assessment is required Bi-daily assessment is required Weekly assessment is required |
Remark:
* Baseline condition survey was conducted for built heritage features at G302, G303, G308, KT26, KT53, KT65 and HKT03 for ND/2024/01 under EP-468/2013/A, G102, G202, G203, G303 and HKT03 for ND/2024/03 under EP-465-2013/A and EP-466/2013/A. As G102, G202, G203, G302, G303, G308, HKT03, KT26, KT 53 and KT65 were not within the assessment area of the related construction work, no construction vibration monitoring was conducted for the built heritage in the reporting month.
Table 10.3 Levels of Alert, Alarm and Actions for Tilting, Vibration and Settlement
|
Monitoring Types |
Alert |
Alarm |
Acton |
|
Tilting |
1:2000 |
1:1500 |
1:1000 |
|
Settlement |
6 mm |
8 mm |
10 mm |
|
Ground Settlement |
15 mm |
20 mm |
25 mm |
|
Vibration (PPV) |
5 mm/s |
6 mm/s |
7.5 mm/s |
Table 11.1 Site Observations at Works Contract No. ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06, ND/2024/07 and ND/2024/08 during the Reporting Period
|
Works Contracts |
Inspection Date |
Key Observations/ Reminders |
Follow-up Action |
|
ND/2024/01 |
4 August 2026 |
Observation:
1. At Portion 25, the Contractor shall collect the general garbage properly and dispose of it regularly. |
1. The general garbage was disposed of properly. Waste collection facility was provided. |
|
Reminder:
Nil |
Nil |
||
|
11 August 2026 |
Observation:
1. At Portion 25, hoarding of not less than 2.4m high should be provided as far as practicable along the site boundary. |
1. Site green barriers have been provided.
|
|
|
Reminder:
1. At Portion 25, general refuse collected should be disposed of regularly. |
Nil |
||
|
20 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
25 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
1. At Portions 5 and 38, the Contractor was reminded to put oil drums on drip tray or stored at proper area. |
Nil. |
||
|
ND/2024/02 |
4 August 2026 |
Observation:
1. At portion 29, the Contractor shall Remove waste in timely manner. 2. At Areas A and B, the Contractor shall display conspicuously a copy of the Environmental Permit on the Project sites entrances. |
1. Waste was removed properly.
2. Copies of the Environmental Permit were displayed at the site entrances.
|
|
Reminder:
Nil |
Nil |
||
|
11 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil. |
Nil. |
||
|
21 August 2026 |
Observation:
1. At Portion 2, soil and dirt on the public road should be removed. Mitigation measures should be provided for the drain gullies to prevent dirt entering the public drainage. |
1. Soil and dirt on public road were removed. Geotextile was provided for the drain gullies.
|
|
|
Reminder:
1. At Portion 2, the tree protection zone on site is reminded to be maintained and materials are reminded to be removed from the protection zone. |
Nil |
||
|
25 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil. |
Nil. |
||
|
ND/2024/03 |
3 August 2026 |
Observation:
Nil |
Nil |
|
Reminder:
Nil. |
Nil. |
||
|
10 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil. |
Nil. |
||
|
18 August 2026 |
Observation:
1. The Contractor should provide proper mitigation measures to prevent surface runoff washing out of site without directing to wastewater treatment facility at Tsung Pak Long. 2. The Contractor should provide drip tray for storing chemical containers at Tsung Pak Long and RW05A. |
1. Mitigation measures were provided at the site boundary to prevent surface runoff washing out of site.
2. Chemical containers not in use were removed from the site properly.
|
|
|
Reminder:
Nil |
Nil |
||
|
24 August 2026 |
Observation:
1. The Contractor was reminded to provide drip tray to the chemical container at Tsung Pak Long. 2. The Contractor was reminded that a proper NRMM label shall be affixed onto the generator at RW05A. |
1. Chemical containers not in use were removed from the site properly.
2. The NRMM label has been affixed onto the generator.
|
|
|
Reminder:
Nil. |
Nil |
||
|
31 August 2026 |
Observation:
1. The Contractor was reminded that temporary drainage system at AB2 should be enhanced and properly in place so as to control the surface runoff effectively. |
1. Mitigation measures was enhanced to avoid seepage of muddy water and to direct the water for treatment. |
|
|
Reminder:
1. The Contractor was reminded to provide drip tray to the chemical container at RW05A. |
Nil. |
||
|
ND/2024/04 |
7 August 2026 |
Observation:
1. At Tsung Pak Long, oil bottles should be well-labelled and stored properly. 2. At Tsung Pak Long, water pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities. 3. At Portion 2, hard copy of the Environmental Permit of the project should be displayed on the Project site entrance. |
1. Oil bottles not in use were removed from the site properly.
2. Water pumped out from trenches or foundation excavations was treated properly before discharged.
3. Hard copy of the Environmental Permit was displayed on the Project site entrance. |
|
Reminder:
Nil. |
Nil |
||
|
12 August 2026 |
Observation:
Nil |
|
|
|
Reminder:
Nil. |
Nil. |
||
|
21 August 2026 |
Observation:
Nil |
|
|
|
Reminder:
Nil |
Nil |
||
|
28 August 2026 |
Observation:
1. At Portion 2 and 3, mitigation measures should be enhanced to prevent muddy water seepage. |
1. Mitigation measures was enhanced to avoid seepage of muddy water and to direct the water for treatment. |
|
|
Reminder:
Nil. |
Nil. |
||
|
ND/2024/05 |
4 August 2026 |
Observation:
1. At Retention Tank Area, the Contractor shall display conspicuously a copy of the Environmental Permit on the Project site entrances. |
1. Hard copy of the Environmental Permit was displayed on the Project site entrance.
|
|
Reminder:
Nil |
Nil |
||
|
11 August 2026 |
Observation:
Nil |
Nil |
|
|
Observation:
Nil |
|
||
|
17 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
26 August 2026 |
Observation:
Nil |
|
|
|
Reminder:
1. At BHD306, the Contractor was reminded to repair the drip tray used for storing oil drums to prevent potential spillage. |
Nil |
||
|
ND/2024/06 |
3 August 2026 |
Observation:
Nil |
|
|
Reminder:
1. At Portion A, the colour of the NRMM label on the track loader was faded, and the contractor was reminded to display it in appropriate colour. |
Nil |
||
|
10 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
17 August 2026 |
Observation:
Nil |
Nil |
|
|
Reminder:
Nil |
Nil |
||
|
27 August 2026 |
Observation:
|
Nil |
|
|
Reminder:
1. The Contractor was reminded that a proper NRMM label shall be affixed onto the excavator at Chuk Yuen. |
Nil |
||
|
31 August 2026 |
Observation:
1. The Contractor was reminded to provide drip tray to the chemical container at Pit B. |
1. The chemical that is not in use was removed from the site properly. |
|
|
Reminder:
|
Nil |
||
|
ND/2024/07 |
6 August 2026 |
Observation:
1. At FB-4(North), impervious sheeting should be provided for placing the breaker head to prevent oil spillage on site. |
1. The breaker head has been wrapped by impervious sheeting. |
|
Reminder:
1. At FB-4(North), the Contractor was reminded to properly cover the stockpile of dusty material entirely by impervious sheeting when no construction work occurred. 2. At Area G, The Contractor was reminded to provide containers for temporary storage of general waste. |
Nil |
||
|
13 August 2026 |
Observation:
|
Nil |
|
|
Reminder:
1. At Area R, the Contractor was reminded to replace the CNP for clearly display on site. |
Nil |
||
|
20 August 2026 |
Observation:
|
Nil |
|
|
Reminder:
|
Nil |
||
|
27 August 2026 |
Observation:
|
Nil |
|
|
Reminder:
1. In Area B, the NRMM label on the excavator had faded. The contractor was reminded to replace it with an appropriate colour. |
Nil |
||
|
ND/2024/08 |
5 August 2026 |
Observation:
|
Nil |
|
Reminder:
1. At Area M1, NRMM label with faded colour is reminded to be replaced. |
Nil |
||
|
12 August 2026 |
Observation:
|
Nil |
|
|
Reminder:
|
Nil |
||
|
19 August 2026 |
Observation:
|
Nil |
|
|
Reminder:
1. At Area V1, the Contractor was reminded to reinstate the tree protection zone for the retained tree. |
Nil |
||
|
26 August 2026 |
Observation:
1. The Contractor was reminded that spent chemical containers at Area T should be recycled as far as practicable or properly disposed of. |
1. The spent chemical containers on site were removed properly. |
|
|
Reminder:
1. The Contractor was reminded that tree protection zone at Area L2 should be maintained in a good condition. |
Nil |
Table 11.2 Photographic Records and Implementation Status of Measures for Ecological Impacts
|
Works Contracts |
EP No. |
Photographic Record |
Implementation Status |
||
|
ND/2024/01 |
EP-467/2013/A (Condition 2.9) |
To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. |
^ |
||
|
EP-468/2013/A (Condition 2.11) |
|||||
|
ND/2024/03 |
EP-465/2013/A (Condition 2.9) |
To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas. |
^ |
||
|
EP-466/2013/A (Condition 2.9) |
|||||
|
EP-467/2013/A (Condition 2.11) |
|
Implementation status: |
^ Mitigation measure was fully implemented |
|
* Observation / reminder was made during site audit but improved / rectified by the contractor |
|
|
# Observation / reminder was made during site audit but not yet improved / rectified by the contractor |
|
|
X Non-compliance of mitigation measure |
|
|
• Non-compliance but rectified by the contractor |
|
|
|
N/A Not Applicable at this stage as no such site activities were conducted in the reporting period |
Works Contract No. ND/2024/01:
· All Site Resumption Area(s)
1. Tree survey
2. Site Clearance
· Portion III (3), IV (4), V (5) and XXXV (35)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
3. Site Formation
· Portion VI (6), VIII (8), Portion XI (11), XII (12), XVI (16), XXII (22), XXIII (23), XXXV (35), XLII (42), XLIV (44) and LIII (53)
1. Site Clearance & Demolition
2. Asbestos Abatement Works
· Portion XVIII (18), XXXVIII (38)
1. Excavation works
2. Construction of CHC Box Culvert
· Portion XI (11), XXIII (23)
1. Formwork Erection, Rebar Fixing, Concreting Works
2. Erection of Substructure of NM Core Exhibition Gallery
3. Fitting out
· Portion XL (40)
1. Drainages System Construction
· Portion LIX (59)
1. Treatment of High Arsenic-Containing Soil (HAS)
2. Erection of Shredding Facilities
· Portion XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)
1. Excavation Works
2. Drainage Pipe Installation
3. ELS Works
· Portion V (5) and XLII (42)
1. Site Clearance
2. Site Formation
3. Construction of CHB Box Culvert
· Portion XXV (25), XXVII (27), XXXIII (33), XLII (42) and XLIV (44)
1. Site Clearance
2. Site Formation
3. Construction of CHB and CHD Box Culvert
· Portion XII (12), XVI (16), XXX (30), XLIV (44)
1. Archaeological Survey
· Portion XX (20)
1. Site Formation
2. Temporary Traffic Arrangement (TTA)
Works Contract No. ND/2024/02:
· Portion 1, 2, 3, 4, 16, 18, 20, 25, 33, 43 & 57
1. Site clearance
· Portion 2, 3 & 20
1. Ground Investigation and Environmental Ground Investigation Works
· Portion 1, 2, 4 and 33
1. Asbestos removal works
· Portion 1, 2, 3, 4, 18 & 33
1. Tree removal works
· Portion 2 & 34
1. Site Formation
Works Contract No. ND/2024/03:
Fanling Highway & Castle Peak Road area
· Pak Sau Road – Po Lau Road
1. Tree Works
2. Watermain DN150
· Po Lau Road – Sheung Yue River
1. Tree Works
2. Box Culvert Bay 37 – Bay 42 New Castle Peak Road & Fanling Highway
· TTA Stage 1 Works
1. Tree Works
2. Demolish of Central Divider & Barrier along FL Highway E/B
New Tsung Pak Long Road
· Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains
1. Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16
· Box culvert Bay 17 to 19 & Drainage/Watermains
1. Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 19
· TTA Stage 1B
1. Box Culvert Bay 3, 5 to 7, 7A ELS
2. Box Culvert Base Slab
· Retaining Wall RW05A
1. RW05A Base Slab and Wall
· Kwu Tung Road Bridge
1. Site clearance and tree works
2. Site formation and cutback the existing slope
3. Foundation & Piling
· Works Areas – WA1, WA2, WA3, WA4 & WA5
1. Temporary Drainage
2. Material/ Segments Storage Yard
Fanling Highway Cross River Bridge (along Sheung Yue River)
· Portion X – West Abutment
1. Site clearance & preparation, survey and tree works
· Road L3 Viaduct
1. Piling Works
2. Pile Cap L3A-01
Kwu Tung Interchange Foundation & Substructure
· Bridge A1
1. Piling Works
2. Excavation
3. Pile Cap
· Bridge B2 & C2
1. ELS
2. Pile Cap
· Bridge B1(NW) & C1(NW)
1. Piling
2. ELS & Pile Cap
· Footbridges No. 3 at TTA Stage 1
1. Clearance
2. Demolishing the existing Footbridge NF157
3. Removal of Temporary Wokrs
· Footbridges No. 4 at TTA Stage 1
1. Ground Investigation
2. Underground Utilities Works
· Footbridges No. 5 at TTA Stage 2
1. Demolishing the existing Footbridge NF156
· Widening of Existing Bridge No.N526
1. Pile Cap
2. Predrilling
Works Contract No. ND/2024/04:
· Portion I
1. Site Clearance
2. Site Establishment
3. Tree Works
4. Ground Investigation
5. Haul Road Construction
6. Existing Sewage Diversion
7. Formworks
8. Demolition of Existing Structures
9. Road Diversion Works
10.Sheet Piling
11.ELS Construction
12.Pipe Cap Construction
13.Slope Works
· Portion II
1. Site Clearance
2. Site Establishment
3. Tree Wroks
4. Trial Pit
5. Haul Road Construction
6. Socket H Piling
7. Pile Cap Construction
· Portion III
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Formworks
5. Haul Road Construction
6. Road Diversion Works
7. Bored Piling
8. Sheet Piling
9. ELS Construction
10.Slope Works
11.Demolition of Existing Structures
· Portion IV
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Pre-drilling
5. Formworks
6. Demolition of Existing Structures
· Portion V
1. Site Clearance
2. Site Establishment
3. Formworks
· Portion VI
1. Site Clearance
2. Site Establishment
3. Demolition of Existing Structures
· Portion VII
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Pre-drilling
5. Socket-H Piling
6. Demolition of Existing Structures
· Portion VIII
1. Site Clearance
2. Site Establishment
3. Trial Pit
4. Socket-H Piling
5. Tree Works
6. Demolition of Existing Structures
Works Contract No. ND/2024/05:
· Portion I
1. Ground Investigation
2. Site Formation Works
· Portion III
1. Tree Felling
2. Site Formation Works
3. Site Clearance
· Portion IIIA
1. Tree Felling Works
2. TTA Set up
· Portion VI
1. Asbestos Removal
2. Site Formation Works
· Portion IX
1. Asbestos Removal
· Portion XI and XII
1. Asbestos Survey & Removal
2. UU Detection
3. Site Clearance & Formation Works
4. Ground Investigation
· Portion XVII
1. Tree Felling
2. UU Detection
3. Site Clearance
4. Ground Investigation
Works Contract No. ND/2024/06:
· Portion A
1. Excavation to +85 mPD
2. Carry Out Soil Nail
· Portion C, E & F
1. Trench and Watermains Laying Works
· Portion D
1. Construction of Pit
· Pit A & C
1. Pre-boring and Sheet-Piling
· Pit B & F
1. Excavation
· Chuk Yuen
1. Construction of Accommodation
Works Contract No. ND/2024/07:
· Area B
1. Drainage and Sewage Construction
2. Open Landscape
· Area D
1. Site Formation
· Area E
1. Site Formation
· Area F
1. Sewerage Construction
2. Tree Felling
3. Site Formation
· Area G
1. Site Clearance
2. Site Formation
· Area H
1. Asbestos Removal
· Area I
1. Asbestos Removal
2. Sewerage Construction
· Area J
1. Road Works
2. Site Clearance
· Area K
1. Site Clearance
2. Asbestos Removal
3. Old Shrine Removal
4. Sewerage Construction
5. Environmental Ground Investigation
· Area M
1. Sewage Pumping Station (SPS4) Construction
· Area N
1. Sewage Construction
2. Road Works
· Area O
1. Site Clearance
2. Asbestos Removal
3. Box Culvert 4 Construction
· Area P
1. Site Formation
2. Drainage Construction
· Area Q
1. Drainage Construction
2. Storm Pipe Construction
3. Box Culvert 5 Construction
· Area R
1. Asbestos Removal
· Area T
1. Asbestos Removal
2. Site Clearance
3. Retaining Wall Construction
4. Site Formation
· Portion 3b
1. Sewerage Construction
2. Drainage Construction
3. Flushing Main Construction
· Portion 6c
1. Improvement of Junction
· Portion 9b
1. Rebar Yard
· Portion H3 and H5
1. Site Clearance
· Footbridge FB-4 (North)
1. Lift Installation
2. ABWF Works
· Footbridge FB-4 (South)
1. ABWF Works
2. Pile Cap Construction
· Footbridge FB-5
1. Lift Tower Construction
2. ABWF Works
3. UHPC Staircase Construction
Works Contract No. ND/2024/08:
· Site Area A
1. Demolition Works
2. Asbestos Abatement
3. Land Decontamination Works
· Site Area B
1. Tree Felling
2. Asbestos Abatement
· Site Area C1 & C2
1. Tree Felling
· Site Area D & E
1. Tree Felling
2. Asbestos Abatement
· Site Area G, H1 & H2
1. Tree Felling
2. Asbestos Abatement
3. Land Decontamination Works
· Site Area I, V2 & V4
1. Tree Felling
2. Asbestos Abatement
3. Land Decontamination Works
· Site Area J
1. Asbestos Investigation
· Site Area L6, K & U
1. Site Formation
2. Asbestos Abatement
3. Tree Felling
4. Road Works
5. UU Works
6. G.I. Works
7. Predrilling Wokrs
· Site Area L1, L2, L3, L4, L5 & L7
1. Site Clearance
2. Predrilling Woks
3. Retaining Wall Construction
4. Bored Pile Works
· Site Area M1, M2, M3, N1, N2, O & P
1. Retaining Wall Construction
2. Tree Felling
3. Rebar Fixing
4. Land Decontamination Works
· Site Area R
1. Tree Feling
2. Site Preparation Works
· Site Area S
1. Site Clearance
2. G.I. Works
· Site Area T
1. Asbestos Abatement
2. Tree Felling
3. Construction of MKT Road
4. Archaeological Rescue Excavation Survey
· Site Area W
1. Asbestos Abatement
2. Tree Felling
3. Land Decontamination Works
· Site Area Q
1. Sewerage Pumping Station Construction
2. Tree Felling
3. Site Preparation Works
· Site Area V1 & V3
1. Site Preparation Works
2. Retaining Wall Construction
Dust
• Regular watering to reduce dust emissions from exposed site surface;
• Stockpile of dusty materials shall be covered entirely by impervious sheeting;
• Provide vehicles washing facilities at all site exits to wash away any dusty materials from vehicle body;
• NRMM Labels should be displayed on the applicable equipment on site by the Contractor;
• Provision of water sprinklers along the haul road for dust suppression.
Noise
• Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and
• Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
• No effluent discharge would be allowed before acquired the effluent discharge license;
• Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;
• Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;
• Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;
• Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and
• Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.
Waste Management
• Provision of sufficient waste disposal points and regular collection of waste;
• Regular cleaning and maintenance programme for drainage system; and
• Chemical containers shall be stored with drip tray underneath.
Landscape and Visual
• Construction activities shall be carefully designed to minimize impact on existing retained trees.
Land Contamination
• Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be properly covered by impermeable sheeting to reduce dust emission during dry season or contaminated run-off during rainy season. Watering should be avoided on stockpiles of soil to minimise runoff.
Landfill Gas Hazard
• “No Smoking” and “No Naked Flame” notices in Chinese and English should be posted prominently around the construction site.
Ecology
• Properly erect and maintain 2m high solid barriers for protection.
• An individual of orchid Eulophia cernua was found growing underneath the pipeline adjacent to the access road leading to the summit of the Table Hill Freshwater Service Reservoir for Contract No. ND/2024/06. The species of conservation importance should be fenced off for protection to minimise the potential impacts aroused from nearby construction activities as far as possible.