Contents

Executive Summary. I

1 Introduction. 1

1.1 Project Background. 1

1.2 Project Organisation. 2

1.3 Construction Works Programme and Construction Works Area. 2

1.4 Summary of Environmental Status. 10

2 Air Quality Monitoring.. 17

2.1 Monitoring Requirement. 17

2.2 Monitoring Location. 17

2.3 Monitoring Parameter and Frequency and Duration. 18

2.4 Monitoring Equipment. 18

2.5 Monitoring Methodology and QA/QC Procedure. 19

2.6 Action and Limit Level for Air Quality Monitoring.. 22

2.7 Results and Observations. 23

2.8 Event and Action Plan. 24

3 Construction Noise Monitoring.. 25

3.1 Monitoring Requirements. 25

3.2 Monitoring Locations. 25

3.3 Noise Monitoring Parameter, Frequency and Duration. 26

3.4 Monitoring Equipment, Methodology and QA / QC Procedure. 27

3.5 Maintenance and Calibration. 28

3.6 Action and Limit Levels. 28

3.7 Results and Observations. 29

3.8 Event and Action Plan. 30

4 Water Quality. 31

4.1 Monitoring Requirement. 31

4.2 Result and Observations. 31

5 Waste Management. 32

6 Ecology. 33

6.1 Introduction. 33

6.2 Monitoring Requirements. 33

6.3 Results and Observations. 35

6.4 Event and Action Plan. 46

7 Landscape and Visual. 47

7.1 Audit Requirements. 47

7.2 Results and Observations. 47

7.3 Event and Action Plan. 47

8 Land Contamination (Ambient Arsenic Monitoring) 48

8.1 Monitoring Requirements. 48

8.2 Monitoring Locations. 48

8.3 Monitoring Equipment. 49

8.4 Monitoring Parameters, Frequency and Duration. 49

8.5 Monitoring Methodology and QA/QC Procedure. 50

8.6 Maintenance/Calibration. 51

8.7 Laboratory Measurement / Analysis. 51

8.8 Result and Observations. 52

8.9 Event and Action Plan. 52

9 Landfill Gas Monitoring.. 53

9.1 Monitoring Requirements. 53

9.2 Monitoring Parameters and Frequency. 53

9.3 Monitoring Locations. 53

9.4 Result and Observations. 54

10 Built Heritage Monitoring.. 55

10.1 Monitoring Requirements. 55

10.2 Monitoring Location. 55

10.3 Monitoring Parameters and Frequency. 55

10.4 Monitoring Equipment. 56

10.5 Result and Observations. 56

10.6 Event and Action Plan. 56

11 Environmental Site Inspection and Audit. 58

11.1 Implementation Status of Environmental Mitigation Measures. 58

12 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions. 66

12.1 Summary of Exceedance. 66

12.2 Summary of Environmental Non-Compliance. 66

12.3 Summary of Environmental Complaint. 66

12.4 Summary of Environmental Summon and Successful Prosecution. 67

13 Future Key Issues. 68

13.1 Works and Potential Environmental Issues in the next Reporting Period. 68

13.2 Recommendation. 76

14 Conclusions. 79

14.1 Conclusion. 79

14.2 Comments/ Recommendations. 80


 

Figures

Figure 1.1 Location and Site Layout Plan (KTN)

Figure 1.2 Location and Site Layout Plan (FLN)

Figure 2.1 Location of Air Quality Monitoring Stations for KTN NDA

Figure 2.2 Location of Air Quality Monitoring Stations for FLN NDA

Figure 3.1 Location of Noise Monitoring Stations for KTN NDA

Figure 3.2 Location of Noise Monitoring Stations for FLN NDA

Figure 6.1 Transect Routes for Non-aquatic Fauna Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution (T1, T4 and T6), Aquatic Fauna Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley (MS_01 - MS_10), and Waterbirds Monitoring of Measures to Minimise Disturbance to Waterbird (T3 and T5) for KTN NDA

Figure 6.2 Transect Routes for Non-aquatic Fauna Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution (T2 and T3), Aquatic Fauna Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley (MS_11 - MS_15), and Waterbirds Monitoring of Measures to Minimise Disturbance to Waterbird (T1, T2 and T4) for FLN NDA

Figure 8.1 Location of Ambient Arsenic Monitoring Stations for KTN NDA

 

Appendices

Appendix 1.1 Construction Programme

Appendix 1.2 Project Organization Chart

Appendix 1.3 Implementation Status of Environmental Mitigation Measure

Appendix 2.1 Impact Monitoring Schedule during the reporting period

Appendix 2.2 Impact Air Quality Monitoring Data & Graphical Presentations & Calibration Certificates

Appendix 2.3 Weather Information during the Reporting Period

Appendix 2.4 Event and Action Plan for Construction Dust

Appendix 3.1 Impact Noise Monitoring Data & Graphical Presentations & Calibration Certificates

Appendix 3.2 Event and Action Plan for Construction Noise

Appendix 5.1 Summary of Monthly Waste Flow Table

Appendix 6.1 Detailed Results of the Ecological Waterbird Monitoring during this Reporting Period

Appendix 6.2 Detailed Results of the Ecological Aquatic Monitoring during this Reporting Period

Appendix 6.3 Detailed Results of the Ecological Non-aquatic Monitoring during this Reporting Period

Appendix 6.4 Event and Action Plan for Ecological Monitoring

Appendix 7.1 Event and Action Plan for Landscape and Visual

Appendix 8.1 Impact Ambient Arsenic Monitoring Data & Graphical Presentations &Calibration Certificates (sourced from the First Phase ET)

Appendix 8.2 Event and Action Plan for Ambient Arsenic Monitoring

Appendix 10.1 Location of Construction Vibration Monitoring

Appendix 10.2 Calibration Certificate for Vibration Monitoring Equipment

Appendix 10.3 Results for Vibration Monitoring 

Appendix 12.1 Statistical Summary of Environmental Complaints, Summons and Prosecution

Appendix 13.1 Impact Monitoring Schedule of Next Reporting Month



Executive Summary

Introduction

A1.     This is the 18th Monthly Environment Monitoring and Audit (EM&A) Report for Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas (the Project) for the reporting period between 1 and 30 June 2026. This report was prepared by Aurecon Hong Kong Limited (Aurecon) under Service Contract No. NDO 05/2024 Remaining Phase Development of Kwu Tung North and Fanling North New Development Areas - Environmental Team (hereinafter called the “Service Contract”).

A2.     Construction works were undertaken under all Works Contracts including Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/05, Works Contract No. ND/2024/06, Works Contract No. ND/2024/07 and Works Contract No. ND/2024/08 during the reporting month. This report documents the findings of EM&A works at Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/05, Works Contract No. ND/2024/06 Works Contract No. ND/2024/07 and Works Contract No. ND/2024/08 under the Project during the reporting period.

A3.     This Project involves eight (8) Environmental Permits (EPs) (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A and EP-476/2013). Details of each EPs are summarised in Table A1.

Table A1 Works Contracts under relevant Environmental Permits in the Reporting Month

Environmental Permit No.

Works Contracts

Title of Designated Project

Designated Project (DP)

EP-465/2013/A

ND/2024/03
ND/2024/04
ND/2024/05

San Tin Highway and Fanling Highway Kwu Tung Section Widening (Between San Tin Interchange and Po Shek Wu Interchange)

DP1

EP-466/2013/A

ND/2024/03
ND/2024/05

Castle Peak Road Diversion

DP2

EP-467/2013/A

ND/2024/01
ND/2024/02
ND/2024/03
ND/2024/05

Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement

DP3

EP-468/2013/A

ND/2024/01
ND/2024/02

Kwu Tung North New Development Area Road D1 to D5

DP4

EP-469/2013

-

Sewage Pumping Stations in Kwu Tung North New Development Area

DP5

EP-470/2013/A

ND/2024/06

Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works

DP7

EP-471/2013/A

ND/2024/04

Po Shek Wu Interchange Improvement

DP8

EP-472/2013/A

ND/2024/08

Fanling Bypass Western Section

DP9

EP-473/2013/A

-

Fanling Bypass Eastern Section

DP10

EP-474/2013

-

Shek Wu Hui Sewage Treatment Works - Further Expansion at Fanling North New Development Area

DP11

EP-476/2013

ND/2024/07

ND/2024/08

Sewage Pumping Stations in Fanling North New Development Area (FLNDA)

DP13

Key Construction Works in the Reporting Period

A4.     The construction works undertaken under Works Contract No. ND/2024/01 commenced since 20 January 2025, construction works under Works Contract No. ND/2024/07 commenced since 27 February 2025, construction works under Works Contract No. ND/2024/06 commenced since 10 March 2025, construction works under Works Contract No. ND/2024/04 commenced since 10 May 2025, construction works under Works Contract No. ND/2024/03 commenced since 2 June 2025, construction works under Works Contract No. ND/2024/02 commenced since 9 February 2026, construction works under Works Contract No. ND/2024/05 commenced since 11 May 2026 and construction works under Works Contract No. ND/2024/08 commenced since 3 June 2026. The commencement dates of each Works Contracts are summarized in Table A2.

Table A2 Commencement Dates of Each Works Contracts

Works Contracts

Commencement Dates

ND/2024/01

20 January 2025

ND/2024/02

9 February 2026

ND/2024/03

1 June 2025

ND/2024/04

10 May 2025

ND/2024/05

11 May 2026

ND/2024/06

10 March 2025

ND/2024/07

27 February 2025 [1]

ND/2024/08

3 June 2026 [2]

[1] According to the contractor’s and supervising team’s confirmation, the project commencement date is 27 February 2025

[2] According to the contractor’s and supervising team’s confirmation, the project commencement date is 3 June 2026

A5.     A summary of construction activities undertaken during the reporting period is presented below:

 

Works Contract No. ND/2024/01:

·  All Site Resumption Area(s)

1.   Tree survey

2.   Site Clearance

·  Portion III (3), IV (4), V (5), VII (7), XX (20) and XXXV (35)

1.   Site Formation

·  Portion VIII (8), XI (11), XII (12), XVI (16), XXIII (23), XXXV (35), XLII (42) and LIII (53)

1.   Site Clearance & Demolition

2.   Asbestos Abatement Works

·  Portion VI (6), XVIII (18) and XXXVIII (38)

1.     Excavation Works

2.     Construction of CHC Box Culvert

·  Portion XI (11), XXIII (23)

1.   Formwork Erection, Rebar Fixing, Concreting Works

2.   Erection of Substructure of Metropolis Community Liaison and Visitor Centre

·  Portion IV (4), V (5), VI (6), XV (15), XVIII (18), XXII (22), XXV (25), XXVII (27), XXXI (31), XXXII (33), XXXV (35), XXXVIII (38), XLII (42), XLIV (44) and LI (51)

1.     Site Clearance

·  Portion XL (40)

1.   Retaining Wall Construction

2.   Drainages System Construction

3.   ELS work

·  Portion LIX (59)

1.   Treatment of High Arsenic-Containing Soil (HAS)

·  Portion XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)

1.   Excavation works

2.   Drainage Pipe Installation

3.   ELS Works

·  Portion XXV (25), XXVII (27), XXXII (33), XLII (42) and XLIV (44)

1.   Site Formation

2.   Construction of CHB and CHD Box Culvert

·  Portion XII (12), XVI (16), XXX (30), XLIV (44)

1.     Archaeological Survey

 

Works Contract No. ND/2024/02:

·  Portion 2, 3, 4, 5, 18, 20 and 43

1.   Site clearance

·  Portion 5

1.   Site formation works

·  Portion 16

1.   Demolition works for Community Sports

·  Portion 2, 4 and 17

1.   Ground investigation works

·  Portion 4 and 18

1.   Asbestos removal works

·  Portion 2, 3, 17 and 20

1.   Tree removal works

 

Works Contract No. ND/2024/03:

Fanling Highway & Castle Peak Road area

 

·  Pak Sau Road – Po Lau Road

1.   Tree Works

2.   Relocation/reprovision/removal of existing TCSS, fire hydrant, signage & streetlighting

3.   Watermain Pak Sau Road – Po Lau Road DN150

·  Po Lau Road – Sheung Yue River

1.   Asbestos Removal Works at Portion IX

2.   Box Culvert Bay 37 – Bay 42 ELS

3.   Tree Works

·  TTA Stage 1 Works

1.   Tree Works

2.   Relocation/Reprovision/removal of existing TCSS, Fire Hydrant, Telecom post, High Voltage Post, Signage & Streetligting

·  New Tsung Pak Long Road

1.   Box Culvert Bay 10 to 12, 14 to 16 Drainage/Watermains

2.   Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16

3.   Box Culvert Bay 14 Base Slab

·  Box Culvert Bay 17 to 19 & Drainage/Watermains

1.   Drainage, sewerage & watermain with backfilling at Box Culvert Bay 19

·  Retaining Wall RW01

1.   Pre-drilling

·  Retaining Wall RW05A

1.   RW05A Bay 11, 13 & 15 Base Slab

2.   RW05A Bay 12, 14 & 16 Wall

3.   RW05A Bay 4, 6, 8 & 10 Wall

·  Kwu Tung Road Bridge

1.   Site clearance and tree works

2.   Site formation and cutback the existing slope

3.   Predrilling

4.   Foundation & Piling

·  Works Areas – WA1, WA2, WA3, WA4 & WA5

1.   Site Clearance, haul road and temporary drainage

2.   Asbestos removal

Fanling Highway Cross River Bridge (along Sheung Yue River)

 

·  Portion XI – RW15 Foundation, Base Slab & Wall

1.   Approach ramp wall RW15-Piling Works

·  Road L3 Viaduct

1.   Pile Cap L3A-02

·  Kwu Tung Interchange Foundation & Substructure - Bridge B1 & C1

1.   Piling Works

·  Widening of Existing Bridge No.N526

1.   Tree Works

2.   Pre-drilling

3.   Piling

 

Works Contract No. ND/2024/04:

·  Portion I

1.   Site Clearance

2.   Site Establishment

3.   Tree Works

4.   Ground Investigation

5.   Haul Road Construction

6.   Existing Sewage Diversion

7.   Demolition of Existing Structures

8.   Road Diversion Works

9.   ELS Construction

10.Pipe Cap Construction

11.Slope Works

·  Portion II

1.   Site Clearance

2.   Site Establishment

3.   Tree Works

4.   Trial Pit

5.   Haul Road Construction

6.   Socket H Piling

·  Portion III

1.   Site Clearance

2.   Site Establishment

3.   Haul Road Construction

4.   Road Diversion Works

5.   Slope Works

·  Portion IV

1.   Site Clearance

2.   Site Establishment

3.   Tree Felling

·  Portion V

1.   Site Clearance

2.   Site Establishment

3.   Trial Pit

·  Portion VII

1.   Site Clearance

2.   Site Establishment

·  Portion VIII

1.   Site Clearance

2.   Site Establishment

3.   Tree Felling

 

Works Contract No. ND/2024/05:

·  Portion I

1.   Tree Survey 

2.   UU Detection

·  Portion III and IIIA

1.   Tree Survey

2.   UU Detection

3.   Site Clearance

·  Portion VI and IX

1.     Asbestos Survey

·  Portion XI and XII

1.     Tree Survey 

2.     Asbestos Survey 

3.     UU Detection 

4.     Site Clearance 

·  Portion XVII

1.     Tree Survey 

2.     UU Detection 

3.     Site Clearance 

 

Works Contract No. ND/2024/06:

·  Portion A

1.   Excavation to +85 mPD of Portion A

2.   Carry Out Soil Nails of Portion A

·  Portion C, Portion D, Portion E and Portion F

1.   Trench and Watermains Laying Works

·  Portion D

1.   Demolition of DN2000 Associated Thrust Blocks

·  Pit C

1.   Pre-boring and Sheet Piling

·  Pit B and Pit F

1.   Sheet-piling

 

Works Contract No. ND/2024/07:

·  Area C

1.   Site Formation

·  Area D

1.   Site Formation

2.   Ground Investigation

·  Area E

1.   Site Formation

·  Area F

1.   Tree Felling

2.   Sewerage Construction

3.   Site Clearance

4.   Site Formation

5.   Ground Investigation

·  Area G

1.   Site Clearance

2.   Site Formation

·  Area I

1.   Asbestos Removal

2.   Sewerage Construction

3.   Ground Investigation

·  Area J

1.   Road Construction

·  Area K

1.   Site Clearance

2.   Asbestos Removal

3.   Sewerage Construction

4.   Environmental Ground Investigation

5.   Road Construction

·  Area M

1.   Site Clearance

2.   Sewage Pumping Station (SPS4) Construction

·  Area O

1.   Asbestos Removal

·  Area P

1.   Site Formation

2.   Drainage Construction

·  Area Q

1.   Drainage Construction

2.   Storm Pipe Construction

3.   Tree Transplantation

4.   Box Culvert 5 Construction

 

·  Portion 1b

1.   Assembly Yard for Bridge Construction

2.   Storage Yard for Concrete Pipe

·  Portion 3b

1.   Sewerage Construction

2.   Drainage Construction

·  Portion 6c

1.   Improvement of Junction

·  Portion 9b

1.   Rebar Yard

·  Footbridge FB-4 (North)

1.   Lift Tower Construction

2.   ABWF Works

3.   Sump Pit Construction

·  Footbridge FB-4 (South)

1.   Pile Cap Construction

2.   ABWF Works

·  Footbridge FB-5

1.   Lift Tower Construction

2.   Sump Pit Construction

3.   ABWF Works

 

Works Contract No. ND/2024/08:

·  Site Area C1 & C2

1.   Site Clearance

·  Site Area D

1.   Tree Felling

2.   Site Clearance

·  Site Area E

1.   Site Clearance

·  Site Area G, H1 & H2

1.   Site Clearance

·  Site Area I, V2 & V4

1.   Site Clearance

2.   Excavation

·  Site Area L6, K & U

1.   Site Clearance

2.   Tree Felling

3.   Road Works

4.   Underground Utilities

·  Site Area L1, L2, L3, L4, L5 & L7

1.   Divert Existing Village Road 

2.   Asbestos Investigation 

·  Site Area M1, M2, M3, N1, N2, O & P

1.   Construction for Box Culvert 

2.   Excavation

3.   Tree Felling

4.   Site Clearance

·  Site Area Q & R

1.   Tree Felling

2.   Excavation

·  Site Area T

1.   Preliminary Works

2.   Site Clearance

·  Site Area W

1.   Tree Felling

Environmental Monitoring and Audit Programme

A6.     The environmental monitoring activities, including 1-hour Total Suspended Particulates (TSP) monitoring, 24-hour TSP monitoring, noise monitoring, ecological survey, 24-hour Respirable Suspended Particulates (RSP) (Ambient Arsenic) monitoring for land contamination and environmental site inspection, were undertaken by Environmental Team (ET) under Service Contract No. NDO 04/2019 (i.e. First Phase ET – Wellab) and under Service Contract No. NDO 05/2024 (i.e. Remaining Phase ET - Aurecon) during the reporting period in accordance with the approved Updated EM&A Manual. A summary of the monitoring and audit activities during the reporting period is presented in Table A3.

 

Table A3 Summary of EM&A Activities in the Reporting Period

EM&A
Activities

Monitoring Station(s)

Works Contract(s)(5)

ND/2024/01

ND/2024/02

ND/2024/03

ND/2024/04

ND/2024/05

ND/2024/06

ND/2024/07

ND/2024/08

1-hour TSP Monitoring(1)

KTN-DMS1(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

KTN-DMS2(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

KTN-DMS3(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

KTN-DMS4(B)(2)(3)

1, 5, 11, 16, 22, 26 June 2026

N/A

1, 5, 11, 16, 22, 26 June 2026

N/A

1, 5, 11, 16, 22, 26 June 2026

N/A

N/A

N/A

FLN-DMS1(2)

N/A

N/A

N/A

N/A

N/A

N/A

2, 8, 12, 17, 23, 29 June 2026

2, 8, 12, 17, 23, 29 June 2026

FLN-DMS2(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-DMS3(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-DMS4(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-DMS5(2)

N/A

N/A

N/A

N/A

N/A

N/A

1, 5, 11, 16, 22, 26 June 2026

1, 5, 11, 16, 22, 26 June 2026

FLN-DMS6(A)(2)(3)

N/A

N/A

3, 9, 15, 20, 26 June 2026 (6)

3, 9, 15, 20, 26 June 2026 (6)

N/A

N/A

N/A

N/A

FLN-DMS7(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

24-hour TSP Monitoring(1)

KTN-DMS1(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

KTN-DMS2(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

KTN-DMS3(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

KTN-DMS4(B)(2)(3)

1, 5, 11, 16, 22, 26 June 2026

N/A

1, 5, 11, 16, 22, 26 June 2026

N/A

1, 5, 11, 16, 22, 26 June 2026

N/A

N/A

N/A

FLN-DMS1(2)

N/A

N/A

N/A

N/A

N/A

N/A

1, 5, 11, 16, 22, 26 June 2026

2, 8, 12, 17, 23, 29 June 2026

FLN-DMS2(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-DMS3(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-DMS4(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-DMS5(A)(2)(3)

N/A

N/A

N/A

N/A

N/A

N/A

1, 5, 11, 16, 22, 26 June 2026

1, 5, 11, 16, 22, 26 June 2026

FLN-DMS6(A)(2)(3)

N/A

N/A

3, 9, 15, 20, 26 June 2026 (6)

3, 9, 15, 20, 26 June 2026 (6)

N/A

N/A

N/A

N/A

FLN-DMS7(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Noise Monitoring(1)

CP-KTN-NMS1(2)

4, 10, 16, 22 June 2026 (6)

4, 10, 16, 22 June 2026 (6)

N/A

N/A

N/A

N/A

N/A

N/A

CP-KTN-NMS2(2)

1, 11, 16, 22 June 2026

1, 11, 16, 22 June 2026

N/A

N/A

N/A

N/A

N/A

N/A

CP-KTN-NMS3(2)

1, 11, 16, 22 June 2026

1, 11, 16, 22 June 2026

N/A

N/A

N/A

N/A

N/A

N/A

CP-KTN-NMS4(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

CP-KTN-NMS5(2)

N/A

N/A

N/A

N/A

N/A

1, 11, 16, 22 June 2026

N/A

1, 11, 16, 22 June 2026

CP-KTN-NMS6(2)

1, 11, 16, 22 June 2026

1, 11, 16, 22 June 2026

N/A

N/A

N/A

N/A

N/A

N/A

CP-KTN-NMS7(2)

4, 10, 16, 22 June 2026 (6)

4, 10, 16, 22 June 2026 (6)

N/A

N/A

N/A

N/A

N/A

N/A

CP-FLN-NMS1(2)

N/A

N/A

N/A

N/A

N/A

2, 8, 17, 23, 29 June 2026

2, 8, 17, 23, 29 June 2026

N/A

CP-FLN-NMS3(2)

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

CP-FLN-NMS4(A)(2)(3)

N/A

N/A

N/A

4, 9, 15, 26 June 2026 (6)

N/A

N/A

N/A

N/A

CP-FLN-NMS5(2)

N/A

N/A

N/A

N/A

N/A

N/A

4, 9, 15, 26 June 2026 (6)

4, 9, 15, 26 June 2026 (6)

CP-FLN-NMS6(2)

N/A

N/A

N/A

N/A

N/A

N/A

4, 9, 15, 26 June 2026 (6)

4, 9, 15, 26 June 2026 (6)

Ecological Monitoring (4)

Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley

Weekly Monitoring: 1, 2, 8, 12, 15, 17, 22, 24 Jun 2026 (Transect T1, T2, T3 and T5)

Weekly Monitoring: 1, 2, 5, 8, 9, 12, 15, 17, 22, 24, 25, 30 Jun 2026 (Transect T1, T2, T3, T4 and T5)

Weekly Monitoring: 1, 2, 8, 12, 15, 17, 22, 24 Jun 2026 (Transect T1, T2, T3 and T5)

Weekly Monitoring: 2, 5, 9, 12, 15, 17, 22, 25, 30 Jun 2026 (Transect T4)

N/A

Weekly Monitoring: 1, 2, 8, 12, 15, 17, 22, 24 Jun 2026 (Transect T1, T2 and T3)

Weekly Monitoring: 1, 2, 5, 8, 9, 12, 15, 17, 22, 24, 25, 30 Jun 2026 (Transect T1, T2, T3, and T4)

Weekly Monitoring: 1, 2, 5, 8, 9, 12, 15, 17, 22, 24, 25, 30 Jun 2026 (Transect T1, T2, T3, and T4)

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream

Monthly Monitoring: 9 Jun 2026 (MS_01 – MS_10)

Monthly Monitoring: 9 Jun 2026 (MS_01 – MS_10)

N/A

N/A

N/A

N/A

Monthly Monitoring: 9 Jun 2026 (MS_11 – MS_15)

Monthly Monitoring: 9 Jun 2026 (MS_11 – MS_15)

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

Monthly Monitoring: 16 Jun 2026 (Transect T1)

Monthly Monitoring: 16 Jun 2026 (Transect T1 and T6)

Monthly Monitoring: 10 Jun 2026 (Transect T4)

N/A

Monthly Monitoring: 10, 16 Jun 2026 (Transect T4 and T6)

Monthly Monitoring: 24 Jun 2026 (Transect T2)

Monthly Monitoring: 10 Jun 2026 (Transect T3)

Monthly Monitoring: 10 Jun 2026 (Transect T3)

24-hour RSP (Ambient Arsenic) Monitoring for Land Contamination (1)

KTN-DMS-4A(2)(3)

1, 5, 11, 16, 22, 26 June 2026

N/A

1, 5, 11, 16, 22, 26 June 2026

N/A

1, 5, 11, 16, 22, 26 June 2026

N/A

N/A

N/A

Water Quality Monitoring(1)

KTN-IS1

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

KTN-CS1

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-IS1

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

FLN-CS1

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Landfill Gas Monitoring

250m Landfill Consultation Zone of Ma Tso Lung Landfill

N/A(7)

N/A(7)

N/A

N/A

N/A

N/A

N/A

N/A

Built Heritage Monitoring

G203

N/A

N/A

1 – 6, 8 – 11, 13, 15 – 17 June 2026

N/A

N/A

N/A

N/A

N/A

G102, G202, G302, G303, G308, KT26, KT53, KT65, HKT03

N/A(8)

N/A

N/A(8)

N/A

N/A

N/A

N/A

N/A

Environmental Site Inspection

Site Area under Works Contract No. ND/2024/01

2, 8, 18, 23, 30 June 2026

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Site Area under Works Contract No. ND/2024/02

N/A

2, 8, 18, 26, 30 June 2026

N/A

N/A

N/A

N/A

N/A

N/A

Site Area under Works Contract No. ND/2024/03

N/A

N/A

1, 8, 17, 22, 29 June 2026

N/A

N/A

N/A

N/A

N/A

Site Area under Works Contract No. ND/2024/04

N/A

N/A

N/A

5, 12, 15, 26 June 2026

N/A

N/A

N/A

N/A

Site Area under Works Contract No. ND/2024/05

N/A

N/A

N/A

N/A

2, 9, 17, 23, 30 June 2026

N/A

N/A

N/A

Site Area under Works Contract No. ND/2024/06

N/A

N/A

N/A

N/A

N/A

1, 12, 15, 22, 29 June 2026

N/A

N/A

Site Area under Works Contract No. ND/2024/07

N/A

N/A

N/A

N/A

N/A

N/A

4, 11, 18, 25 June 2026

N/A

Site Area under Works Contract No. ND/2024/08

N/A

N/A

N/A

N/A

N/A

N/A

N/A

3, 10, 26 June 2026 (9)

 

Remarks:

(1)       For 1-hour and 24-hour TSP & 24-hour RSP (Ambient Arsenic) monitoring, monitoring stations that are specifically within the 500m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.

 

For Noise Monitoring, monitoring stations that are specifically within the 300m buffer area projected from the site boundary of works contract(s) will be considered being the representative monitoring stations for the corresponding works contract(s) and the associated impact monitoring exercises will be kicked off once the nearest works contracts have been commenced and undertaken during the reporting period/month.

 

(2)       New monitoring station IDs are presented. The corresponding monitoring station IDs are as follows:

1-hour and 24-hour TSP / 24-hour RSP (Ambient Arsenic)

KTN-DMS1 = DMS1
KTN-DMS2 = DMS2
KTN-DMS3 = DMS3
KTN-DMS4(A)/4(B) = DMS4
FLN-DMS1 = DMS7
FLN-DMS2 = DMS9
FLN-DMS3 = DMS11
FLN-DMS4 = DMS6
FLN-DMS5/5(A) = DMS8
FLN-DMS6(A) = DMS10
FLN-DMS7 = DMS5

Noise

CP-KTN-NMS1 = CP-NMS1
CP-KTN-NMS2 = CP-NMS2
CP-KTN-NMS3 = CP-NMS3
CP-KTN-NMS4 = CP-NMS5
CP-KTN-NMS5 = CP-NMS7
CP-KTN-NMS6 = N/A

CP-KTN-NMS7 = CP-NMS4
CP-FLN-NMS1 = CP-NMS10
CP-FLN-NMS3 = CP-NMS12
CP-FLN-NMS4(A) = CP-NMS6
CP-FLN-NMS5 = CP-NMS8
CP-FLN-NMS6 = CP-NMS9

 

(3)       Alternative monitoring stations to the corresponding original monitoring stations.

(4)       The monitoring date for the reporting month was conducted by the ET from the First Phase of KTN/FLN NDAs Project, except Transect T4 for the ecological monitoring item Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley, and Transect T2 for the ecological monitoring item Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution. No ecological monitoring was conducted for the Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream for this reporting month as this monitoring is only conducted during wet season (April – October). Detailed divisions of work between First Phase ET and Remaining Phase can be referred to Section 6 and relevant appendix.

(5)       N/A – No relevant monitoring is required according to the approved updated EM&A Manual.

(6)       The monitoring date for the reporting month was conducted by the ET from the Remaining Phase of KTN/FLN NDAs Project.

(7)       As confirmed by the Supervisor Team, no ground disturbance works were carried out in the work area within 250m Landfill Consultation Zone of Ma Tso Lung Landfill including construction of the infrastructure, development works, excavation works and works involve confined spaces. Routine gas monitoring should be undertaken during groundwork construction and in all excavations.

(8)       As confirmed by the Contractors, related works were not conducted within the assessment area in the reporting month.

(9)       For Works Contract ND/2024/08, the originally scheduled weekly environmental site inspection on 18 June 2026 was cancelled, due to the adverse weather conditions.

 

Breaches of Action Levels (AL) and Limit Levels (LL)

A7.     Summary of the environmental exceedances of the reporting period is tabulated in Table A4.


 

Table A4 Summary of Exceedances in the Reporting Period

Environmental Monitoring

Parameter(s)

No. of Exceedances

Total No. of Exceedances

No. of Non-project Related Exceedances

Total No. of Non-project Related Exceedances

No. of Exceedances

Related to the Project

Total No. of Exceedances

Related to the Project

AL

LL

AL

LL

AL

LL

Air Quality

1-hour TSP

0

0

0

0

0

0

0

0

0

24-hourTSP

0

0

0

0

0

0

0

0

0

24-hour RSP

(Ambient Arsenic)

0

0

0

0

0

0

0

0

0

Noise

Leq(30mins)

0

0

0

0

0

0

0

0

0

Ecological Monitoring

Avifauna

0

0

0

0

0

0

0

0

0

Non-aquatic fauna

0

4

4

0

4

4

0

0

0

Built Heritage Monitoring

Tilting

0

0

0

0

0

0

0

0

0

Settlement

0

0

0

0

0

0

0

0

0

Ground Settlement

0

0

0

0

0

0

0

0

0

Vibration (PPV)

0

0

0

0

0

0

0

0

0

 

Air Quality

A8.     No AL or LL exceedance was recorded for air quality monitoring in the reporting period.

 

Noise

A9.     No AL exceedance for construction noise was recorded during the reporting month, corresponding to no noise-related complaint received. No LL exceedance was recorded for construction noise monitoring in the reporting period.

 

Ambient Arsenic

A10.  No AL or LL exceedance was recorded for ambient arsenic monitoring in the reporting period.

 

Ecological Monitoring

A11.  Four LL exceedance were recorded for the monitoring of measures to minimise impacts on ecological sensitive habitats from disturbance and pollution. The exceedance was deemed as non-project related with potential influences by abiotic factors.

 

Built Heritage Monitoring (Vibration Monitoring)

A12.  No exceedance of limits was recorded for vibration monitoring in the reporting period.

Complaint Log

A13.  One environmental complaint was logged during the reporting period. The complaint was regarding muddy water runoff.

A14.  The environmental complaint was related to muddy water accumulated on the footpath and muddy runoff entering the Ng Tung River on 17 June 2026 under works contract ND/2024/07. The complaint was received by the EPD on 17 June 2026 and referred to CEDD, the Resident Engineers’ Team, ET, and IEC on 22 June 2026. The complaint case has been investigated by the Contractor and ET, and the investigation was closed out on 2 July 2026. The investigation findings have shown that there was no direct evidence indicating that the condition was caused by this works contract and non-compliance was observed.

A15.  The details of the complaint and investigation result are shown in Appendix 12.1.

Notification of Summons and Successful Prosecutions

A16.  No notification of summons or successful prosecutions was received in the reporting period.

Reporting Changes

A17.  There was no change to be reported that may affect the on-going EM&A programme.

Future Key Issues

A18.  The major site activities for the next reporting period are summarized below and shown in Appendix 1.1:

 

Works Contract No. ND/2024/01:

·  All Site Resumption Area(s)

1.   Tree survey

2.   Site Clearance

·  Portion III (3), IV (4), V (5) and XXXV (35)

1.   Site Formation

·  Portion VIII (8), XVI (16), XXXII (31), XXXV (35) XLII (42), LIII (53) and LVIII (58)

1.     Site Clearance & Demolition

2.     Asbestos Abatement Works

·  Portion XVIII (18), XXXVIII (38)

1.     Excavation works

2.     Construction of CHC Box Culvert

·  Portion XI (11), XXIII (23)

1.     Formwork Erection, Rebar Fixing, Concreting Works

2.     Erection of Substructure of Metropolis Community Liaison and Visitor Centre

·  Portion XL (40)

1.   Retaining Wall Construction

2.   Drainages System Construction

3.   ELS work

·  Portion LIX (59)

1.   Treatment of High Arsenic-Containing Soil (HAS)

·  Portion XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)

1.   Excavation Works

2.   Drainage Pipe Installation

3.   ELS Works

·  Portion XXV (25), XXVII (27), XXXIII (33), XLII (42) and XLIV (44)

1.   Site Clearance

2.   Site Formation

3.   Construction of CHB and CHD Box Culvert

 

·  Portion XII (12), XXX (30), XLIV (44)

1.   Archaeological Survey

 

Works Contract No. ND/2024/02:

·  Portion 2, 3, 4, 5, 18, 20 and 43

1.   Site clearance

·  Portion 5

1.   Site formation works

·  Portion 2, 3 and 18

1.   Ground investigation works

·  Portion 2, 4 and 25

1.   Asbestos removal works

·  Portion 2 and 3

1.   Tree removal works

 

Works Contract No. ND/2024/03:

Fanling Highway & Castle Peak Road area

 

·  Pak Sau Road – Po Lau Road

1.   Tree Works

2.    Watermain DN150

·  Po Lau Road – Sheung Yue River

1.   Tree Works

2.   Box Culvert Bay 37 – Bay 42 New Castle Peak Road & Fanling Highway

·  TTA Stage 1 Works

1.   Tree Works 

2.   Demolish of Central Divider & Barrier along FL Highway E/B 

·  New Tsung Pak Long Road

1.   Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains

2.   Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16 

·  Box culvert Bay 17 to 19 & Drainage/Watermains

1.   Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 19

·  TTA Stage 1B 

1.   Box Culvert Bay 3, 5 to 7, 7A ELS 

2.   Box Culvert Base Slab 

·  Retaining Wall RW05A

1.   RW05A Base Slab and Wall 

·  Kwu Tung Road Bridge

1.   Site clearance and tree works

2.   Site formation and cutback the existing slope

3.   Foundation & Piling

·  Works Areas – WA1, WA2, WA3, WA4 & WA5

1.   Temporary Drainage 

2.   Material/ Segments Storage Yard

Fanling Highway Cross River Bridge (along Sheung Yue River)

 

·  Portion X – West Abutment

1.   Site clearance & preparation, survey and tree works

·  Road L3 Viaduct

1.   Piling Works

2.   Pile Cap L3A-02

Kwu Tung Interchange Foundation & Substructure

 

·  Bridge B1 & C1

1.   Piling Works

2.   ELS

·  Bridge B2 & C2

1.   Piling Works

·  Footbridges No. 4 at TTA Stage 1 

1.   Ground Investigation 

2.   Underground Utilities Works

3.   Piling

·  Footbridges No. 5 at TTA Stage 2 

1.   Installation of the temporary FB5 

·  Widening of Existing Bridge No.N526

1.   Pilling

 

Works Contract No. ND/2024/04:

·  Portion I

1.   Site Clearance

2.   Site Establishment

3.   Tree Works

4.   Ground Investigation

5.   Haul Road Construction

6.   Existing Sewage Diversion

7.   Demolition of Existing Structures

8.   Road Diversion Works

9.   ELS Construction

10.Pipe Cap Construction

·  Portion II

1.   Site Clearance

2.   Site Establishment

3.   Trial Pit

4.   Bored Pilling

5.   Haul Road Construction

6.   ELS Construction

7.   Socket H Piling

·  Portion III

1.   Site Clearance

2.   Site Establishment

3.   Trial Pit

4.   Ground Investigation

5.   Bored Pilling

6.   Haul Road Construction

7.   Road Diversion Works

·  Portion IV

1.   Site Clearance

2.   Site Establishment

3.   Tree Felling

·  Portion V

1.   Site Clearance

2.   Site Establishment

·  Portion VI

1.   Site Clearance

2.   Site Establishment

3.   Demolition of Existing Structures

·  Portion VII

1.   Site Clearance

2.   Site Establishment

3.   Pre-drilling

·  Portion VIII

1.   Site Clearance

2.   Site Establishment

3.   Demolition of Existing Structures

 

Works Contract No. ND/2024/05:

·  Portion I

1.   Ground Investigation  

2.   UU Detection

·  Portion III and IIIA

1.   Tree Survey

2.   UU Detection

3.   Site Clearance

·  Portion VI and IX

1.   Asbestos Survey

2.   Asbestos Removal

·  Portion XI and XII

1.   Tree Survey 

2.   Asbestos Survey 

3.   Asbestos Removal

4.   UU Detection 

5.   Site Clearance 

6.   Ground Investigation  

·  Portion XVII

1.   Tree Survey 

2.   Tree Felling

3.   UU Detection 

4.   Site Clearance 

5.   Ground Investigation

 

Works Contract No. ND/2024/06:

·  Portion A

1.   Excavation to +84 mPD of Portion A

2.   Carry Out Soil Nail of Portion A

·  Portion C, D, E & F

1.     Trench and Watermans Laying Works

·  Pit A & C

1.     Pre-boring and Sheet-Piling

·  Pit B & F

1.   Sheet-Piling

 

Works Contract No. ND/2024/07:

·  Area C

1.   Site Formation

·  Area D

1.   Site Formation

2.   Ground Investigation

·  Area E

1.   Site Formation

2.   Site Clearance

·  Area F

1.   Site Clearance

2.   Site Formation

3.   Tree Felling

4.   Sewerage Construction

5.   Storm Pipe Construction

·  Area G

1.   Site Clearance

2.   Site Formation

·  Area H

1.   Asbestos Removal

·  Area I

1.   Asbestos Removal

2.   Sewerage Construction

3.   Ground Investigation

·  Area J

1.   Road Works

·  Area K

1.   Site Clearance

2.   Asbestos Removal

3.   Old Shrine Removal

4.   Retaining Wall Construction

5.   Sewerage Construction

6.   Environmental Ground Investigation

7.   Road Construction

·  Area M

1.   Sewage Pumping Station (SPS4) Construction

·  Area O

1.   Site Clearance

2.   Asbestos Removal

3.   Box Culvert 4 Construction

·  Area P

1.   Site Formation

2.   Drainage Construction

·  Area Q

1.   Tree Felling

2.   Tree Transplantation

3.   Drainage Construction

4.   Storm Pipe Construction

5.   Box Culvert 5 Construction

·  Area R

1.   Asbestos Removal

·  Portion 1b

1.   Site Formation

2.   Underground Utilities Construction

3.   Open Landscape

·  Portion 3b

1.   Sewerage Construction

2.   Drainage Construction

3.   Flushing Main Construction

·  Portion 6c

1.   Improvement of Junction

·  Portion 9b

1.   Rebar Yard

·  Footbridge FB-4 (North)

1.   Lift Tower Construction

2.   ABWF Works

3.   Sump Pit Construction

·  Footbridge FB-4 (South)

1.   ABWF Works

2.   Pile Cap and Pier Construction Works

3.   Sump Pit Construction

4.   UHPC Staircase Construction

·  Footbridge FB-5

2.   Lift Tower Construction

3.   Sump Pit Construction

4.   ABWF Works

 

Works Contract No. ND/2024/08:

·  Site A

1.   Asbestos Removal

·  Site B

1.   Asbestos Investigation

·  Site Area C1 & C2

1.   Site Clearance

2.   Tree Felling

3.   Asbestos Removal

4.   Site Formation

·  Site Area D & E

1.   Tree Felling

2.   Site Clearance

·  Site Area G, H1 & H2

1.   Tree Felling

2.   Site Clearance

·  Site Area I, V2 & V4

1.   Tree Felling

2. Excavation

·  Site Area L6, K & U

1.   Site Clearance

2.   Tree Felling

3.   Road Works

4.   Underground Utilities

·  Site Area L1, L2, L3, L4, L5 & L7

1.   Divert Existing Village Road 

·  Site Area M1, M2, M3, N1, N2, O & P

1.   Site Clearance

2.   Tree Felling

3.   Road Works

4.   Underground Utilities

·  Site Area R

1.   Plate Load Test

·  Site Area T

1.   Preliminary Works

2.   Site Clearance

·  Site Area W

1.   Tree Felling

·  Site Area Q

1.   Plate Road Test

 

 


1             Introduction

1.1       Project Background

1.1.1       The Kwu Tung North and Fanling North New Development Areas (KTN and FLN NDAs) development are implemented in two phases, comprising First Phase and Remaining Phase developments.  The construction works for the First Phase development commenced in December 2019. The construction works for the Remaining Phase development (the Project), including site clearance and formation, roads, drainage, sewerage and water supply systems, commenced progressively from the January 2025.

1.1.2       The Project is delivered under eight (8) Works Contracts as below. 

·     Contract No. ND/2024/01: Site Formation and Infrastructure Works (South); 

·     Contract No. ND/2024/02: Site Formation and Infrastructure Works (North); 

·     Contract No. ND/2024/03: Improvement Works of Fanling Highway (Kwu Tung Portion) and Associated Works; 

·     Contract No. ND/2024/04: Improvement Works of Tai Tau Leng Roundabout and Po Shek Wu Road and Associated Works; 

·     Contract No. ND/2024/05: Improvement Works of Fanling Highway (Pak Shek Au Portion) and Associated Works; 

·     Contract No. ND/2024/06: Fresh Water and Flushing Water Service Reservoirs and Associated Works; 

·     Contract No. ND/2024/07: Site Formation and Infrastructure Works (East); and  

·     Contract No. ND/2024/08: Site Formation and Infrastructure Works (West). 

1.1.3       The EIA Report (AEIAR-175/2013) for NENT NDA was approved with conditions under EIAO in 2013. The Environmental Permits for corresponding Designated Projects were also issued by DEP in November 2013. Subsequent to the findings of preliminary design and P&E Review for accommodating additional population in KTN and FLN NDAs, VEP were subsequently applied for eight EPs under the Project (i.e. EP-465/2013/A, EP-466/2013/A, EP-467/2013/A, EP-468/2013/A, EP-470/2013/A, EP-471/2013/A, EP-472/2013/A and EP-476/2013). 

1.1.4       Aurecon was commissioned by Civil Engineering and Development Department (CEDD) to provide EM&A services for the works contracts in relation to the Project pursuant to the requirements as specified in relevant EPs, the EM&A Manual issued in the EIA stage, the Updated EM&A Manual prepared for Contract No. NDO 14/2018 and the approved EIA Report for the Project to discharge the duties of the ET for the Project. 


 

1.1.5       This is the 18th Monthly EM&A Report summarizing the findings of EM&A works at Works Contract No. ND/2024/01 under the Project with EP-467/2013/A and EP-468/2013/A, Works Contract No. ND/2024/02 under the Project with EP-467/2013/A and EP-468/2013/A, Works Contract No. ND/2024/03 under the Project with EP-465/2013/A, EP-466/2013/A and EP-467/2023/A, Works Contract No. ND/2024/04 under the Project with EP-465/2013/A and EP-471/2013/A, Works Contract No. ND/2024/05 under the Project with EP-465/2013/A, EP-466/2013/A and EP-467/2013/A, Works Contract No. ND/2024/06 under Environmental Permit No. EP-470/2013/A, Contract No. ND/2024/07 under Environmental Permit No. EP-476/2013 and Contract No. ND/2024/08 under Environmental Permit No. EP-472/2013/A and EP-476/2013 during the reporting period from 1 to 30 June 2026.

1.2       Project Organisation

1.2.1       Parties with different levels of involvement in the Project organisation for Works Contracts are summarized in Table 1.1.

Table 1.1 Parties Involved in Project Organization for all Works Contracts

 

Works Contract(s)

Parties

ND/2024/01

ND/2024/02

ND/2024/03

ND/2024/04

ND/2024/05

ND/2024/06

ND/2024/07

ND/2024/08

Project Proponent

CEDD

Supervisor / Engineer’s Representative (ER)

AECOM Asia Co. Ltd.

AECOM Asia Co. Ltd.

AECOM Asia Co. Ltd

AECOM Asia Co. Ltd

AECOM Asia Co. Ltd

Binnies Hong Kong Limited

AtkinsRéalis Asia Limited

AtkinsRéalis Asia Limited

Contractor

Build King - Richwell Engineering Joint Venture

Build King – Richwell Civil Joint Venture

 

China State - STEC Joint Venture

CW – CRCC (ND202404) Joint Venture

Lanon – Sinohydro – Excel JV

Wo Hing-Tsun Yip Joint Venture

Build King – Richwell Civil Joint Venture

Gammon - STEC Joint Venture

ET

Aurecon Hong Kong Limited

Independent Environmental Checker (IEC)

Mott MacDonald Hong Kong Limited

1.2.2       The key personnel contact names and contact numbers are summarized in Appendix 1.2.

1.3       Construction Works Programme and Construction Works Area

1.3.1       The construction phase EM&A programme commenced since 20 January 2025 progressively. The construction works programme, and the construction works area of the Project are shown in Appendix 1.1 and Figure 1.1 respectively. A summary of construction activities undertaken during the reporting period is presented below:

 

Works Contract No. ND/2024/01:

·  All Site Resumption Area(s)

1.   Tree survey

2.   Site Clearance

·  Portion III (3), IV (4), V (5), VII (7), XX (20) and XXXV (35)

1.   Site Formation

·  Portion VIII (8), XI (11), XII (12), XVI (16), XXIII (23), XXXV (35), XLII (42) and LIII (53)

1.   Site Clearance & Demolition

2.   Asbestos Abatement Works

·  Portion VI (6), XVIII (18) and XXXVIII (38)

1.   Excavation Works

2.   Construction of CHC Box Culvert

·  Portion XI (11), XXIII (23)

1.   Formwork Erection, Rebar Fixing, Concreting Works

2.   Erection of Substructure of Metropolis Community Liaison and Visitor Centre

·  Portion IV (4), V (5), VI (6), XV (15), XVIII (18), XXII (22), XXV (25), XXVII (27), XXXI (31), XXXII (33), XXXV (35), XXXVIII (38), XLII (42), XLIV (44) and LI (51)

1.   Site Clearance

·  Portion XL (40)

1.   Retaining Wall Construction

2.   Drainages System Construction

3.   ELS work

·  Portion LIX (59)

1.   Treatment of High Arsenic-Containing Soil (HAS)

·  Portion XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)

1.   Excavation works

2.   Drainage Pipe Installation

3.   ELS Works

·  Portion XXV (25), XXVII (27), XXXII (33), XLII (42) and XLIV (44)

1.   Site Formation

2.   Construction of CHB and CHD Box Culvert

·  Portion XII (12), XVI (16), XXX (30), XLIV (44)

1.   Archaeological Survey

 

Works Contract No. ND/2024/02:

·  Portion 2, 3, 4, 5, 18, 20 and 43

1.   Site clearance

·  Portion 5

1.   Site formation works

·  Portion 16

1.   Demolition works for Community Sports

·  Portion 2, 4 and 17

1.   Ground investigation works

·  Portion 4 and 18

1.   Asbestos removal works

·  Portion 2, 3, 17 and 20

1.   Tree removal works

 

Works Contract No. ND/2024/03:

Fanling Highway & Castle Peak Road area

 

·  Pak Sau Road – Po Lau Road

1.   Tree Works

2.   Relocation/reprovision/removal of existing TCSS, fire hydrant, signage & streetlighting

3.   Watermain Pak Sau Road – Po Lau Road DN150

·  Po Lau Road – Sheung Yue River

1.   Asbestos Removal Works at Portion IX

2.   Box Culvert Bay 37 – Bay 42 ELS

3.   Tree Works

·  TTA Stage 1 Works

1.   Tree Works

2.   Relocation/Reprovision/removal of existing TCSS, Fire Hydrant, Telecom post, High Voltage Post, Signage & Streetligting

·  New Tsung Pak Long Road

1.   Box Culvert Bay 10 to 12, 14 to 16 Drainage/Watermains

2.   Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16

3.   Box Culvert Bay 14 Base Slab

·  Box Culvert Bay 17 to 19 & Drainage/Watermains

1.   Drainage, sewerage & watermain with backfilling at Box Culvert Bay 19

·  Retaining Wall RW01

1.   Pre-drilling

·  Retaining Wall RW05A

1.   RW05A Bay 11, 13 & 15 Base Slab

2.   RW05A Bay 12, 14 & 16 Wall

3.   RW05A Bay 4, 6, 8 & 10 Wall

·  Kwu Tung Road Bridge

1.   Site clearance and tree works

2.   Site formation and cutback the existing slope

3.   Predrilling

4.   Foundation & Piling

·  Works Areas – WA1, WA2, WA3, WA4 & WA5

1.   Site Clearance, haul road and temporary drainage

2.   Asbestos removal

Fanling Highway Cross River Bridge (along Sheung Yue River)

 

·  Portion XI – RW15 Foundation, Base Slab & Wall

1.   Approach ramp wall RW15-Piling Works

·  Road L3 Viaduct

1.   Pile Cap L3A-02

·  Kwu Tung Interchange Foundation & Substructure - Bridge B1 & C1

1.   Piling Works

·  Widening of Existing Bridge No.N526

1.   Tree Works

2.   Pre-drilling

3.   Piling

 

Works Contract No. ND/2024/04:

·  Portion I

1.   Site Clearance

2.   Site Establishment

3.   Tree Works

4.   Ground Investigation

5.   Haul Road Construction

6.   Existing Sewage Diversion

7.   Demolition of Existing Structures

8.   Road Diversion Works

9.   ELS Construction

10.Pipe Cap Construction

11.Slope Works

·  Portion II

1.   Site Clearance

2.   Site Establishment

3.   Tree Works

4.   Trial Pit

5.   Haul Road Construction

6.   Socket H Piling

·  Portion III

1.   Site Clearance

2.   Site Establishment

3.   Haul Road Construction

4.   Road Diversion Works

5.   Slope Works

·  Portion IV

1.   Site Clearance

2.   Site Establishment

3.   Tree Felling

·  Portion V

1.   Site Clearance

2.   Site Establishment

3.   Trial Pit

·  Portion VII

1.   Site Clearance

2.   Site Establishment

·  Portion VIII

1.   Site Clearance

2.   Site Establishment

3.   Tree Felling

 

Works Contract No. ND/2024/05:

·  Portion I

1.   Tree Survey 

2.   UU Detection

·  Portion III and IIIA

1.   Tree Survey

2.   UU Detection

3.   Site Clearance

·  Portion VI and IX

1.   Asbestos Survey

·  Portion XI and XII

1.   Tree Survey 

2.   Asbestos Survey 

3.   UU Detection 

4.   Site Clearance 

·  Portion XVII

1.   Tree Survey 

2.   UU Detection 

3.   Site Clearance 

 

Works Contract No. ND/2024/06:

·  Portion A

1.   Excavation to +85 mPD of Portion A

2.   Carry Out Soil Nails of Portion A

·  Portion C, Portion D, Portion E and Portion F

1.   Trench and Watermains Laying Works

·  Portion D

1.   Demolition of DN2000 Associated Thrust Blocks

·  Pit C

1.   Pre-boring and Sheet Piling

·  Pit B and Pit F

1.   Sheet-piling

 

Works Contract No. ND/2024/07:

·  Area C

1.   Site Formation

·  Area D

1.   Site Formation

2.   Ground Investigation

·  Area E

1.   Site Formation

·  Area F

1.   Tree Felling

2.   Sewerage Construction

3.   Site Clearance

4.   Site Formation

5.   Ground Investigation

·  Area G

1.   Site Clearance

2.   Site Formation

·  Area I

1.   Asbestos Removal

2.   Sewerage Construction

3.   Ground Investigation

·  Area J

1.   Road Construction

·  Area K

1.   Site Clearance

2.   Asbestos Removal

3.   Sewerage Construction

4.   Environmental Ground Investigation

5.   Road Construction

·  Area M

1.   Site Clearance

2.   Sewage Pumping Station (SPS4) Construction

·  Area O

1.   Asbestos Removal

·  Area P

1.   Site Formation

2.   Drainage Construction

·  Area Q

1.   Drainage Construction

2.   Storm Pipe Construction

3.   Tree Transplantation

4.   Box Culvert 5 Construction

 

·  Portion 1b

1.   Assembly Yard for Bridge Construction

2.   Storage Yard for Concrete Pipe

·  Portion 3b

1.   Sewerage Construction

2.   Drainage Construction

·  Portion 6c

1.   Improvement of Junction

·  Portion 9b

1.   Rebar Yard

·  Footbridge FB-4 (North)

1.   Lift Tower Construction

2.   ABWF Works

3.   Sump Pit Construction

·  Footbridge FB-4 (South)

1.   Pile Cap Construction

2.   ABWF Works

·  Footbridge FB-5

1.   Lift Tower Construction

2.   Sump Pit Construction

3.   ABWF Works

 

Works Contract No. ND/2024/08:

·  Site Area C1 & C2

1.   Site Clearance

·  Site Area D

1.   Tree Felling

2.   Site Clearance

·  Site Area E

1.   Site Clearance

·  Site Area G, H1 & H2

1.   Site Clearance

·  Site Area I, V2 & V4

1.   Site Clearance

2.   Excavation

·  Site Area L6, K & U

1.   Site Clearance

2.   Tree Felling

3.   Road Works

4.   Underground Utilities

·  Site Area L1, L2, L3, L4, L5 & L7

1.   Divert Existing Village Road 

2.   Asbestos Investigation 

·  Site Area M1, M2, M3, N1, N2, O & P

1.   Construction for Box Culvert 

2.   Excavation

3.   Tree Felling

4.   Site Clearance

·  Site Area Q & R

1.   Tree Felling

2.   Excavation

·  Site Area T

1.   Preliminary Works

2.   Site Clearance

·  Site Area W

1.   Tree Felling

 

1.4       Summary of Environmental Status

1.4.1       A summary of the relevant permits, licences, and/or notifications on environmental protection for the work contracts that are involved in this reporting period is presented in Table 1.2 to Table 1.7.

 

Table 1.2 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/01

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-467/2013/A

27/01/2017

N/A

Valid

EP-468/2013/A

27/01/2017

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

10008709

02/09/2024

N/A

Valid

Billing Account for Disposal of Construction Waste

7052236

20/09/2024

N/A

Valid

Registration of Chemical Waste Producer

WPN: 5213-548-B2781-01

06/12/2024

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WT00045924-2024

15/01/2025

31/01/2030

Valid

WT00046627-2025

03/06/2025

30/06/2030

Valid

WT00046736-2025

10/06/2025

30/06/2030

Valid

WT00046982-2025

03/10/2025

31/10/2030

Valid

WT00047583-2025

19/01/2026

31/01/2031

Valid

WT00048070-2026

28/01/2026

31/01/2031

Valid

WT00048369-2026

14/04/2026

30/04/2031

Valid

WT00048594-2026

08/05/2026

31/05/2031

Valid

Construction Noise Permit (CNP)

 

 

 

GW-RN0390-26

26/03/2026

25/07/2026

Valid

GW-RN1593-25

04/01/2026

30/06/2026

Valid

GW-RN0512-26

20/04/2026

19/07/2026

Valid

GW-RN0709-26

02/06/2026

01/09/2026

Valid

GW-RN0744-26

09/06/2026

26/09/2026

Valid

 

Table 1.3 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/02

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-467/2013/A

27/01/2017

N/A

Valid

EP-468/2013/A

27/01/2017

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

10024940

23/12/2025

N/A

Valid

Billing Account for Disposal of Construction Waste

7057203

05/01/2026

N/A

Valid

Registration of Chemical Waste Producer

WPN:5213-545-B2803-01

11/02/2026

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WT00048304-2026

18/03/2026

31/03/2031

Valid

WT00048375-2026

30/04/2026

30/04/2031

Valid

Construction Noise Permit (CNP)

 

 

 

GW-RN0649-26

15/05/2026

14/08/2026

Valid

 

 

Table 1.4 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/03

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-465/2013/A

20/01/2017

N/A

Valid

EP-466/2013/A

18/08/2022

N/A

Valid

EP-467/2013/A

27/01/2017

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

10008101

15/08/2024

N/A

Valid

Billing Account for Disposal of Construction Waste

7052008

21/08/2024

N/A

Valid

Registration of Chemical Waste Producer

WPN:5213-548-C5047-01

22/01/2025

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WT00046044-2025

07/11/2025

28/02/2030

Valid

Construction Noise Permit (CNP)

 

 

 

GW-RN0655-26

15/05/2026

14/08/2026

Valid

GW-RN0651-26

15/05/2026

14/07/2026

Valid

GW-RN0678-26

22/05/2026

21/07/2026

Valid

GW-RN0786-26

16/06/2026

15/09/2026

Valid

GW-RN0840-26

25/06/2026

24/09/2026

Valid

 

Table 1.5 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/04

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-465/2013/A

20/01/2017

N/A

Valid

EP-471/2013/A

10/10/2022

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

10012919

06/01/2025

N/A

Valid

Billing Account for Disposal of Construction Waste

7053746

13/02/2025

N/A

Valid

Registration of Chemical Waste Producer

WPN:5213-626-C5043-01

28/01/2025

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WT00047165-2025

15/12/2025

31/08/2030

Valid

WT00048247-2026

18/03/2026

31/03/2031

Valid (Variation of WT00048247-2026 was applied on 15 April 2026)

Construction Noise Permit (CNP)

 

 

 

GW-RN0381-26

24/03/2026

23/07/2026

Valid

GW-RN0426-26

01/04/2026

30/06/2026

Valid

GW-RN0401-26

03/04/2026

02/07/2026

Valid

GW-RN0402-26

03/04/2026

02/07/2026

Valid

GW-RN0461-26

07/04/2026

06/07/2026

Valid

GW-RN0580-26

13/05/2026

12/08/2026

Valid

GW-RN0579-26

07/05/2026

06/08/2026

Valid

GW-RN0710-26

01/06/2026

31/08/2026

Valid

GW-RN0708-26

02/06/2026

31/08/2026

Valid

GW-RN0760-26

12/06/2026

11/09/2026

Valid

GW-RN0762-26

12/06/2026

31/08/2026

Valid

 

Table 1.6 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/05

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-465/2013/A

20/01/2017

N/A

Valid

EP-466/2013/A

18/08/2022

N/A

Valid

EP-467/2013/A

27/01/2017

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

100025962

23/01/2026

N/A

Valid

Billing Account for Disposal of Construction Waste

7057565

03/02/2026

N/A

Valid

Registration of Chemical Waste Producer

WPN:5213-545-L3280-01

14/05/2026

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

--

--

--

--

Construction Noise Permit (CNP)

 

 

 

--

--

--

--

 

 

Table 1.7 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/06

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-470/2013/A

13/05/2022

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

10007695

06/08/2024

N/A

Valid

Billing Account for Disposal of Construction Waste

7051899

28/08/2024

N/A

Valid

Registration of Chemical Waste Producer

WPN:5213-624-W3824-01

04/09/2024

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WT00046560-2025

15/05/2025

31/05/2030

Valid

WT00046847-2025

11/07/2025

31/07/2030

Valid

WT00046588-2025

29/05/2025

31/05/2030

Valid

WT00048275-2026

20/04/2026

31/04/2031

Valid

WT00048499-2026

28/05/2026

31/05/2031

Valid

Construction Noise Permit (CNP)

 

 

 

GW-RN0395-26

01/04/2026

30/09/2026

Valid

GW-RN0545-26

04/05/2026

29/07/2026

Valid

GW-RN0592-26

12/05/2026

05/08/2026

Valid

 

Table 1.8 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/07

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-476/2013

21/11/2013

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

10007874

09/08/2024

N/A

Valid

Billing Account for Disposal of Construction Waste

7051974

20/08/2024

N/A

Valid

Registration of Chemical Waste Producer

WPN:5213-625-B2775-01

19/08/2024

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WT00045532-2024

10/12/2024

31/12/2029

Valid

WT00046059-2025 (Part 1)

17/06/2025

28/02/2030

Valid

WT00046059-2025 (Part 2)

17/06/2025

28/02/2030

Valid

WT00046342-2025

15/05/2025

31/05/2030

Valid

WT00046692-2025

29/05/2025

31/05/2030

Valid

WT00046655-2025

03/06/2025

30/06/2030

Valid

WT00046819-2025

31/07/2025

31/07/2030

Valid

WT00047343-2025

29/09/2025

30/09/2030

Valid

WT00047250-2025

12/11/2025

30/11/2030

Valid

WT00048473-2026

17/04/2026

30/04/2031

Valid

WT00048492-2026

30/04/2026

30/04/2031

Valid

Construction Noise Permit (CNP)

 

 

 

GW-RN0069-26

19/01/2026

18/06/2026

Valid until 18/06/2026

GW-RN0168-26

18/02/2026

17/06/2026

Valid until 17/06/2026

GW-RN0179-26

23/02/2026

22/08/2026

Valid

GW-RN0560-26

07/05/2026

31/10/2026

Valid

GW-RN0577-26

15/05/2026

14/08/2026

Valid

GW-RN0602-26

22/05/2026

21/08/2026

Valid

GW-RN0746-26

09/06/2026

08/09/2026

Valid

GW-RN0765-26

19/06/2026

18/12/2026

Valid

 

Table 1.9 Status of Environmental License, Notifications and Permits for Works Contract No. ND/2024/08

Permit / License Name/No.

Valid Period

Status

From

To

Environmental Permit

EP-472/2013/A

21/11/2013

N/A

Valid

EP-476/2013

21/11/2013

N/A

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

10025562

13/01/2026

N/A

Valid

Billing Account for Disposal of Construction Waste

7056971

16/12/2025

N/A

Valid

Registration of Chemical Waste Producer

WPN:5213-625-G3123-01

03/02/2026

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

--

--

--

--

Construction Noise Permit (CNP)

 

 

 

GW-RN0196-26

12/02/2026

08/06/2026

Valid until 08/06/2026

GW-RN0806-26

17/06/2026

16/09/2026

Valid


2             Air Quality Monitoring

2.1       Monitoring Requirement

2.1.1       In accordance with the EM&A Manual, the approved updated EM&A Manual for the First Phase, the ET shall carry out impact monitoring during the construction phase of the Project. 1-hour and 24-hour TSP to monitor the air quality for the Works Contacts.

2.1.2       Impact 1-hour TSP monitoring was conducted for at least three times every 6 days, while the impact 24-hour TSP monitoring was conducted for at least once every 6 days at the designated air quality monitoring stations.

2.2       Monitoring Location

2.2.1       According to the EM&A Manual, the approved updated EM&A Manual for the First Phase, the designated locations for impact air quality monitoring in related to the work contracts in the reporting period are listed in Table 2.1 and their locations are shown in Figure 2.1 and Figure 2.2.

Table 2.1 Summary of Impact Air Quality Monitoring Stations in related to the Works Contracts in the Reporting Period

Monitoring Station(s)

Works Contract(s)

ASR ID in EIA

Planned(3) or Existing

Monitoring Location(s)

KTN-DMS1

ND/2024/01,

ND/2024/02,

ND/2024/03, ND/2024/05

KTN-19

Planned

Nursery Classes and Kindergarten; Post Offices

KTN-DMS2

ND/2024/01,

ND/2024/02

KTN-90

Planned

Nursery Classes and Kindergarten (2 nos); District Elderly Community Centre

KTN-DMS3

ND/2024/01,

ND/2024/02,

ND/2024/03

KTN-326

Planned

Village Resite

KTN-DMS4(B)(1)(2)

ND/2024/01,

ND/2024/03, ND/2024/05

KTN-E70

Existing

Temporary Structure at Pak Shek Au

FLN-DMS1

ND/2024/07, ND/2024/08

FLN-E62

Existing

Scattered Village Houses North of Proposed Potential Ecopark

FLN-DMS2

ND/2024/06, ND/2024/07

FLN-E243

Planned

Residential Building, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre, Residential Home for the Elderly, Post Office

FLN-DMS5, FLN-DMS5(A)

ND/2024/07, ND/2024/08

FLN-E124

Existing

Noble Hill / Good View New Village

FLN-DMS6(A)

ND/2024/03,

ND/2024/04

DMS-10

Existing

Choi Ngan House, Choi Po Court

FLN-DMS7

ND/2024/06, ND/2024/07, ND/2024/08

FLN-20

Planned

Planned premise for Weapon Training Division

Remarks:

(1)    KTN-DMS4(B) is the alternative air monitoring stations proposed to replace KTN-DMS4.

(2)    As KTN-DMS4 - Temporary structure near Fanling Highway (near Pak Shek Au) is no longer as existing ASR, air quality monitoring station should be relocated to the alternative dust monitoring location according to the updated EM&A Manual, Section 2.6.2. According to Figure 3.1 of Approved EIA report and site visits conducted in June 2022, ASR at near KTN-E70 – Temporary Structure near Fanling Highway near Pak Shek Au is considered as the most representative alternative station KTN-DMS4(B) for air quality monitoring for KTN-DMS4 (i.e. KTN-E162).

(3)    Impact monitoring will be carried out when the planned sensitive receivers are commissioned.

 

2.3       Monitoring Parameter and Frequency and Duration

2.3.1       In accordance with the requirements for placement of equipment, as set out of the EM&A Manual of the Project, the approved updated EM&A Manual for the First Phase, the monitoring parameter, frequency and duration of impact air quality monitoring are listed in Table 2.2.

Table 2.2 Parameters Measured in the Impact Air Quality Monitoring

Parameter(s)

Frequency(1)(2)

1-hour TSP

Three times / 6 days

24-hour TSP

Once / 6 days

Remarks:

(1)    The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.

(2)    The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.

2.4       Monitoring Equipment

2.4.1       Direct reading dust meters and High-Volume TSP Samplers were used for measuring the impact air quality monitoring (i.e. 1-hour TSP and 24-hour TSP) during the reporting period in accordance with the Service Contract No. NDO 04/2019 Monthly EM&A Report.  According to Section 2.4.5 of the EM&A Manual, the approved updated EM&A Manual for First Phase ET, the proposed use of direct reading dust meter was submitted to and agreed by the First Phase IEC. HVS for 24-hour TSP monitoring will be adopted once secured supply of electricity become available at FLN-DMS5(A) and KTN-DMS4(B).

2.4.2       Table 2.3 summarizes the equipment used in the air quality monitoring programme. Copies of the calibration certificates for air quality monitoring equipment are shown in Appendix 2.2.

Monitoring

Station(s)

Equipment

Model

Manufacturer

Quantity

KTN-DMS4(B)(1), FLN-DMS5(1), FLN-DMS5(A)(1)

Dust Monitor

(1-hour and 24-hour TSP)

AEROCET-831

Met One Instruments

6

FLN-DMS1(1)

Dust Monitor

(1-hour TSP)

HVS Sampler

(24-hour TSP)

TE-5170

Tisch

1

FLN-DMS6(A)(2)

Dust Monitor

(1-hour and 24-hour TSP)

LD-5R

Sibata

1

Table 2.3 Air Quality Monitoring Equipment

Remarks:

(1)      The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.

(2)      The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.


 

2.5       Monitoring Methodology and QA/QC Procedure

2.5.1       Direct reading dust meter was deployed for the air quality monitoring as shown in Table 2.3.

Instrumentation

(AEROCET-831)

2.5.2       The measuring procedures of the dust meters were in accordance with the Manufacturer’s Instruction Manual as follows:

·       Place the dust meter at least 1.3 meters above ground;

·       Press and hold the Power key momentarily to power on the unit and make sure that the battery level was not flash or in low level;

·       Allow the instrument to stand for about 3 second to display the Sample Screen minutes;

·       Press the START / STOP key to run the internal vacuum pump for 1 minute and be ready to use;

·       Use the select dial to select the PM range and press the START / STOP key to start a measurement;

·       Finally, push the START/STOP key to stop the measurement after 24-hour sampling;

·       Information such as sampling date, time, value and site condition were recorded during the monitoring period; and

·       All data were recorded in the data logger for further data processing.

 

Maintenance/Calibration

2.5.3       The following maintenance/calibration was required for the HVS:

·       Check and calibrate the meters by High Volume Sampler (HVS) to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.

Instrumentation

(TISCH Model: TE-5170 / TE-5170X)

2.5.4       The following guidelines were adopted during the installation of HVS:

·       A horizontal platform with appropriate support was provided to secure the samplers against gusty wind. the dust meter at least 1.3 meters above ground;

·       No two samplers were placed less than 2 metres apart.

·       The distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler.

·       A minimum of 2 metres of separation from walls, parapets and penthouses was required for rooftop samples.

·       A minimum of 2 metres separation from any supporting structure, measured horizontally was required.

·       No furnaces or incineration flues were nearby.

·       Airflow around the sampler was unrestricted.

·       The sampler were more than 20 metres from the drip line.

·       Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.

·       Permission and access to monitoring stations have been obtained to set up the samplers.

·       A secured supply of electricity was provided to operate the samplers.

 

Filters Preparation

2.5.5       Wellab Limited (HOKLAS Registration No. HOKLAS083) is a HOKLAS accredited laboratory and responsible for the preparation of 24-hour conditioned and pre-weighed filter papers for the monitoring team.

2.5.6       All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25°C and not variable by more than ±3°C; the relative humidity (RH) was < 50% and not variable by more than ±5%. A convenient working RH was 40%.

 

Operating/Analytical Procedures

2.5.7       Operating/analytical procedures for the air quality monitoring were highlighted as follows:

·       Prior to the commencement of dust sampling, the flow rate of the HVS was properly set (between 1.1 m3 /min. and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50;

·       The power supply was checked to ensure the sampler worked properly;

·       On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air quality monitoring station;

·       The filter holding frame was then removed by loosening the four nuts and carefully a weighted and conditioned filter was centered with the stamped number upwards, on a supporting screen;

·       The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame was then tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges;

·       The shelter lid was closed and secured with the aluminium strip;

·       The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number);

·       After sampling, the filter was removed and kept in a clean and tightly sealed plastic bag. The filter paper was then returned to the HOKLAS accredited laboratory (Wellab Ltd.) for reconditioning in the humidity-controlled chamber followed by accurate weighting by an electronic balance with a readout down to 0.1mg. The elapsed time was also recorded; and

·       Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature should be between 25°C and 30°C and did not vary by more than ±3°C; the RH should be < 50% and did not vary by more than ±5%. A convenient working RH is 40%. Weighing results were returned for further analysis of TSP concentrations collected by each filter

 

Maintenance/Calibration

2.5.8       The following maintenance/calibration was required for the HVS:

·       The high-volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply are in good working conditions; and

·       All HVS were calibrated (five point calibration) using Calibration Kit prior to the commencement of baseline monitoring and thereafter at bi-monthly intervals.

Instrumentation

(Sibata Model: LD-5R)

2.5.9       The measuring procedures of the dust meters were in accordance with the Manufacturer’s Instruction Manual as follows:

·       Placed the dust meters at least 1.3m above ground

·       Set POWER to “ON” and make sure that the battery level not flashed or in low level;

·       Pulled the air sampling inlet cover up;

·       Pushed the knob at MEASURE position;

·       Set time/mode setting to [BG] by pushing the time setting switch. Then, started the background measurement by pushing the start/stop switch once. It took 6 sec. to complete the background measurement;

·       Turned knob to SENSI. ADJ position and pressed in;

·       Pushed Start/Stop switch once;

·       Gently returned knob to the MEASURE position;

·       Pushed the time setting switch to change the time setting display to [LOG] at the bottom left of the liquid crystal display;

·       Removed the cap and started measurement; and

·       Information such as sampling date, time, count value and site condition were recorded during the monitoring period.

 

 


 

Maintenance/Calibration

2.5.10    The following maintenance/calibration was required for the direct reading dust meter:

·       Direct reading dust meter shall be used in determining 1-hour TSP and 24-hour TSP at air quality monitoring points. The direct reading dust meters have been calibrated against high volume samplers (HVSs) bi-monthly. A 2-day, three 3-hour measurement results per day from direct reading dust meters were taken to compare with the sampling results from the HVSs. The correlation between the direct reading dust meters and the HVSs were then concluded. By accounting for the correlation factor, the direct reading dust meters are considered to achieve comparable results as that of the HVSs.

·       The HVS used to calibrate the direct dust monitor will need to be calibrated bi-monthly. Details of maintenance and calibration for the HVS refers to Section 2.5.8. Calibration for the air quality monitoring equipment is attached to the Appendix 2.2.

2.6       Action and Limit Level for Air Quality Monitoring

2.6.1          The baseline monitoring results formed the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 1-hour TSP and 24-hour TSP. Based on the baseline dust monitoring data and the derivation criteria specified above, the Action/Limit Levels for 1-hour TSP and 24-hour TSP are presented in Table 2.4 and Table 2.5 respectively.

Table 2.4 Action and Limit Levels for 1-hour TSP Air Quality Monitoring

Monitoring Station

AL (μg/m3)

LL (μg/m3)

KTN-DMS4(B)

297

500

FLN-DMS1

303

500

FLN-DMS5

279

500

FLN-DMS6(A)

286

500

 

Table 2.5 Action and Limit Levels for 24-hour of TSP Air Quality Monitoring

Monitoring Station

AL (μg/m3)

LL (μg/m3)

KTN-DMS4(B)

192

260

FLN-DMS1

150

260

FLN-DMS5(A)

153

260

FLN-DMS6(A)

157

260

 

2.7       Results and Observations

2.7.1       Air quality monitoring was conducted as scheduled in the reporting period. The air quality monitoring schedule during the reporting period is shown in the Appendix 2.1.

The 1-hour and 24-hour TSP air quality monitoring result in the reporting period are summarized in Table 2.6 and 2.7. No Action or Limit levels exceedance was recorded in the reporting period. Details of the results and graphical presentation are shown in Appendix 2.2.The weather information during the reporting period is presented in Appendix 2.3.

Table 2.6 Summary Table of 1-hour TSP Monitoring Result during the Reporting Month

Monitoring

Station

Averaged Measured Value (μg/m3)

Maximum Measured

Value (μg/m3)

Minimum Measured Value (μg/m3)

Action Level (μg/m3)

Limit Level, (μg/m3)

KTN-DMS4(B)(1)

39

65

20

297

500

FLN-DMS1(1)

43

61

26

303

500

FLN-DMS5(1)

47

68

31

279

500

FLN-DMS6(A)(2)

58

82

41

286

500

Remarks:

(1)      The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.

(2)      The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.

 

Table 2.7 Summary Table of 24-hour TSP Monitoring Result during the Reporting Month

Monitoring

Station

Averaged Measured Value (μg/m3)

Maximum Measured

Value (μg/m3)

Minimum Measured

Value (μg/m3)

Action Level (μg/m3)

Limit Level, (μg/m3)

KTN-DMS4(B)(1)

42

74

21

192

260

FLN-DMS1(1)

22

34

15

150

260

FLN-DMS5(A) (1)

54

78

31

153

260

FLN-DMS6(A)(2)

62

76

52

157

260

Remarks:

(1)      The air quality monitoring (1-hour and 24-hour TSP) was conducted by First Phase ET during the reporting period.

(2)      The air quality monitoring (1-hour and 24-hour TSP) was conducted by Remaining Phase ET during the reporting period.

2.7.2       According to the observation record from Monthly EM&A Report (June 2026) prepared under Service Contract No. NDO 04/2019, the major dust source KTN-DMS4(B), FLN-DMS1, FLN-DMS5 and FLN-DMS5(A) included excavator, dump truck, roller and road traffic etc. For station conducted by Remaining Phase ET, the major dust source for FLN-DMS6(A) is from road traffic.


 

2.8       Event and Action Plan

2.8.1       Should any non-compliance of the criteria occur, action in accordance with the Event and Action Plan in Appendix 2.4 shall be followed. Investigation of the exceedances of environmental quality performance limits should be conducted, and the ET will immediately notify the IEC and EPD, as appropriate. The notification should be followed up with advice to the IEC and EPD on the results of the investigation, proposed actions and success of the action taken, with any necessary follow-up proposals.


3             Construction Noise Monitoring

3.1       Monitoring Requirements

3.1.1       In accordance with the approved Updated EM&A Manual, the ET shall carry out impact monitoring during the construction phase of the Project in terms of the A-weighted equivalent continuous sound pressure level (Leq) to monitor the construction noise arising from the construction activities. The regular monitoring frequency for each monitoring station was on a weekly basis and one set of measurements between 0700 and 1900 hours on normal weekdays shall be conducted.

3.2       Monitoring Locations

3.2.1       According to the approved Updated EM&A Manual, the monitoring designated locations for construction noise monitoring in related to the works contracts in the reporting period are listed in Table 3.1 and shown in Figure 3.1 and Figure 3.2.

Table 3.1 Construction Noise Monitoring Stations near in related to the Works Contracts in the Reporting period

Monitoring Station(s)

Works Contract(s)

NSR

EIA ID(s)

Location(s)

Planned(2)

Or

Existing

Type of Measurement

CP-KTN-NMS1

ND/2024/01,

ND/2024/02

CP-NMS1

Residential Building at Ma Tso Lung

Existing

Free-Field(1)

CP-KTN-NMS2

ND/2024/01,

ND/2024/02

CP-NMS2

Residential Building at Ma Tso Lung

Existing

Free-Field(1)

CP-KTN-NMS3

ND/2024/01,

ND/2024/02

CP-NMS3

Fung Kong Garden

Existing

CP-KTN-NMS4(3)

ND/2024/01,

ND/2024/02,

ND/2024/03, ND/2024/05

CP-NMS5

Primary School

Planned

CP-KTN-NMS5

ND/2024/06, ND/2024/08

CP-NMS7

N/A

Existing

Free-Field(1)

CP-KTN-NMS6

ND/2024/01,

ND/2024/02

N/A

Ho Sheung Heung, Hau Ku ShekAncestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery

Existing

Façade

CP-KTN-NMS7

ND/2024/01, ND/2024/02

CP-NMS4

Oi Lok Home

Existing

Free-Field(1)

CP-FLN-NMS4(A)(4)

ND/2024/04

CP-NMS6

Choi Ying House,

Choi Po Court

(Choi Yuen Estate)

Existing

Free-Field(1)

CP-FLN-NMS1

ND/2024/06, ND/2024/07

CP-NMS10

Belair Monte

Existing

Facade

CP-FLN-NMS3(3)

ND/2024/06,

ND/2024/07

CP-NMS12

Secondary School

Planned

Free-Field(1)

CP-FLN-NMS5

ND/2024/07, ND/2024/08

CP-NMS8

Man Kok Village

Existing

Free-Field(1)

CP-FLN-NMS6

ND/2024/07, ND/2024/08

CP-NMS9

Woodland Crest

Existing

Façade

Remarks:

(1)      For Free Field measurement, +3 dB(A) should be added to the measured results.

(2)      Impact monitoring will be carried out when the planned sensitive receivers are commissioned.

(3)      As confirmed with Engineer Representative, the planned school at CP-KTN-NMS4 and CP-FLN-NMS3 are not constructed yet. Thus, the impact noise monitoring will be carried out at monitoring station CP-KTN-NMS4 and CP-FLN-NMS3 after the construction and occupation of the planned school. No noise monitoring of the mentioned station was carried out in this reporting period.

(4)      Alternative monitoring stations to the corresponding original monitoring stations.

 

 

3.3       Noise Monitoring Parameter, Frequency and Duration

3.3.1       Construction noise level was measured by the ET and measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq(30mins) used as the monitoring parameter for the construction noise monitoring.

3.3.2       As supplementary information for data auditing, statistical results such as L10 and L90 were also obtained for reference.

3.3.3       Table 3.2 summarizes the monitoring parameters, duration, and frequency of construction noise monitoring.

 

Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration

Monitoring Station

Parameter

Frequency and Duration

CP-KTN-NMS1(2), CP-KTN-NMS2(1), CP-KTN-NMS3(1), CP-KTN-NMS5(1), CP-KTN-NMS6(1),CP-KTN-NMS7(2),CP-FLN-NMS1(1), CP-FLN-NMS4(A)(2), CP-FLN-NMS5(2), CP-FLN-NMS6(2)

Leq(30mins), L10 and

L90 (as six consecutive Leq,5min readings)

Once every week throughout the construction phase

Remark:

(1)      The noise monitoring was conducted by First Phase ET during the reporting period.

(2)      The noise monitoring was conducted by Remaining Phase Environmental Team during the reporting period.

3.4       Monitoring Equipment, Methodology and QA / QC Procedure

3.4.1       As referred to the technical memorandum issued under the Noise Control Ordinance (NCO), sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications were used for carrying out the construction noise monitoring.

3.4.2       Noise measurements were not made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed was checked with a portable wind speed meter capable of measuring the wind speed in m/s.

3.4.3       Sufficient numbers of noise measuring equipment and associated instrumentation were prepared by the ET. All the equipment and associated instrumentation were clearly labelled.

3.4.4       The monitoring procedures are as follows:

·       For façade measurement, the monitoring station was set at a point 1 m from the exterior of the sensitive receivers building façade and set at a position 1.2 m above the ground. For free-field measurement, the monitoring station was set at a position 1.2 m above the ground.

·       The battery condition was checked to ensure good functioning of the meter.

·       Parameters such as frequency weighting, the time weighting and the interval were set as follows:

-       Frequency weighting: A

-       Time weighting: Fast

-       Interval: 30 minutes (Leq(30mins))

·       Prior to and after each noise measurement, the meter was calibrated using an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement will be required after re-calibration or repair the equipment.

·       At the end of the monitoring period, the values of Leq, L10 and L90 were recorded. In addition, noise sources were recorded on a standard record sheet.

3.4.5       Table 3.3 summarizes the noise monitoring equipment used during the reporting period. Copies of the calibration certificates for noise monitoring are shown in Appendix 3.1


 

Table 3.3 Construction Noise Monitoring Equipment

Equipment

Manufacturer

Model

No. of Equipment

Serial No.

Sound Level Meter

NTi Audio(2)

XL2

1

A2A-17638-E0

XL3

1

A3A-01220-F0

BSWA(1)

BSWA 308

2

580011

580017

Acoustic Calibrator

RION(2)

NC-75

3

34724244

35124527

35124530

SVANTEK(1)

SV30A

1

24791

Remark:

(1)    The noise monitoring equipment was used by First Phase ET during the reporting period.

(2)    The noise monitoring equipment was used by Remaining Phase Environmental Team during the reporting period.

3.5       Maintenance and Calibration

3.5.1       Maintenance and calibration procedures are as follows:

·       The microphone head of the sound level meter and calibrator were regularly cleaned with a soft cloth;

·       The sound level meter and acoustic calibrator were calibrated annually; and

·       The accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency immediately prior to and following each noise measurement. Measurements were accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.6       Action and Limit Levels

3.6.1       The Action and Limit levels were established in accordance with the Updated EM&A Manual. Table 3.4 presents the Action and Limit Levels for construction noise. Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan presented in Appendix 3.2 shall be carried out.

Table 3.4 Action and Limit Levels for Construction Noise Monitoring

Time Period

Action

Limit Level

07:00 – 19:00 on normal weekdays

When one or more documented complaints are received

75 dB(A)

Remark:

(1)    Time period for construction noise monitoring during normal construction working hour (0700-1900 Monday to Saturday).

(2)    If works are to be carried out during restricted hours, the conditions stipulated in the Construction Noise Permit (CNP) issued by the Noise Control Authority have to be followed.

(3)    70 dB(A) and 65 dB(A) for schools during normal teaching periods and school examination periods, respectively.

 

 

 


 

3.7       Results and Observations

3.7.1       All noise monitoring was conducted as scheduled in the reporting month. The noise monitoring schedule during the reporting period is shown in the Appendix 2.1.

3.7.2       No Action Level exceedance for construction noise was recorded during the reporting month, corresponding to no noise-related complaint received. No Limit Level exceedance was recorded for construction noise monitoring in the reporting period. Details of the results and graphical presentation are shown in Appendix 3.1. The construction noise monitoring results are summarized in Table 3.5. The major noise sources observed during impact noise monitoring are summarized in Table 3.6.

Table 3.5 Summary of Construction Noise Monitoring Results during the Reporting Month

Works Contracts

Monitoring Stations

Noise Levels, Leq(30min), dB(A)

Baseline Levels, dB(A)

Limit Levels, dB(A)

ND/2024/01, ND/2024/02

CP-KTN-NMS1(1)(3)

53.3 – 58.5

65.7

75

CP-KTN-NMS2(1)(2)

48.5 – 58.4

58.6

CP-KTN-NMS3(1)(2)

48.0 – 54.2

51.6

CP-KTN-NMS6(2)

58.2 – 69.3

55.1

CP-KTN-NMS7(1)(3)

64.6 – 67.0

64.6

ND/2024/04

CP-FLN-NMS4(A)(1)(3)(4)

69.5 – 71.2

72.4

ND/2024/06, ND/2024/08

CP-KTN-NMS5(1)(2)

55.6 – 70.0

57.2

ND/2024/06, ND/2024/07

CP-FLN-NMS1(2)

67.2 – 70.5

69.9

ND/2024/07, ND/2024/08

CP-FLN-NMS5(1)(3)

65.3 – 68.0

69.5

CP-FLN-NMS6(3)

53.2 – 59.8

55.0

Remarks:

(1)      For Free Field measurement, +3 dB(A) was added to the measured results.

(2)      The noise monitoring was conducted by First Phase ET during the reporting period.

(3)      The noise monitoring was conducted by Remaining Phase Environmental Team during the reporting period.

(4)      Alternative monitoring stations to the corresponding original monitoring stations.

 

 

Table 3.6 Summary of Observations at Noise Monitoring Stations

Works Contracts

Monitoring Stations

Location

Major Noise Sources

ND/2024/01, ND/2024/02

CP-KTN-NMS1

Residential Building at Ma Tso Lung

Household noise (dog barking) from nearby village house

CP-KTN-NMS2

Residential Building at Ma Tso Lung

Road Traffic Noise

CP-KTN-NMS3

Fung Kong Garden

Road Traffic Noise

CP-KTN-NMS4

Primary School

N/A(1)

CP-KTN-NMS6

Ho Sheung Heung, Hau Ku Shek Ancestral Hall, Hung Shing Temple & Pai Fung Temple and Sin Wai Nunnery

Road Traffic Noise

CP-KTN-NMS7

Oi Lok Home

Road Traffic Noise

ND/2024/04

CP-FLN-NMS4(A)(2)

Choi Ying House,

Choi Po Court

(Choi Yuen Estate)

Road Traffic Noise

ND/2024/06, ND/2024/08

CP-KTN-NMS5

N/A

Road Traffic Noise

ND/2024/06, ND/2024/07

CP-FLN-NMS1

Belair Monte

Road Traffic Noise, Large Exhaust Fan

CP-FLN-NMS3

Secondary School

N/A(1)

ND/2024/07, ND/2024/08

CP-FLN-NMS5

Man Kok Village

Road Traffic Noise

CP-FLN-NMS6

Woodland Crest

No construction activity and other noise source was observed

Remarks:

(1)       No impact noise monitoring was carried out at the monitoring station. Thus, not applicable (N/A).

(2)       Alternative monitoring stations to the corresponding original monitoring stations.

3.7.3       No noise related complaint was received during the reporting period.

3.8       Event and Action Plan

3.8.1       Should non-compliance of the noise monitoring criteria occur, actions in accordance with the Event and Action Plan in Appendix 3.4 shall be carried out.


 

4             Water Quality

4.1       Monitoring Requirement

4.1.1       In accordance with the approved Updated EM&A Manual and EM&A Manual, impact water quality monitoring shall be carried out three days per week at all the designated monitoring stations during the construction of channel. The measurement periods are specified in Table 4.1. The interval between two sets of monitoring shall not be less than 36 hours.

Table 4.1 Summary of Water Quality Monitoring Locations

New Monitoring Station(s)

Original Monitoring Station ID(s)

Description

Location(s)

Measurement

Period

KTN NDA

KTN-CS1

CS1

Control Station for KTN NDA

Centreline of river, upstream of the channel

During construction of channel

KTN-IS1

IS1

Impact Station for KTN NDA

Centreline of river, downstream of the channel

During construction of channel

FLN NDA

FLN-CS1

CS2

Control Station for FLN NDA

Centreline of river, upstream of the channel

During construction of channel

FLN-IS1

IS2

Impact Station for FLN NDA

Centreline of river, downstream of the channel

During construction of channel

4.2       Result and Observations

4.2.1       No construction of channelisation work between KTN-CS1, KTN-IS1, FLN-CS1 and FLN-IS1 were undertaken during the reporting period. Therefore, no water quality monitoring was carried out.

 

 


5             Waste Management

5.1.1       Waste generated from the Project include inert construction and demolition (C&D) materials and non-inert C&D wastes in the reporting period. The cumulative waste flow table of the Project was presented in in Appendix 5.1.

5.1.2       Sorting of construction and demolition (C&D) materials was carried out on site. Sufficient numbers of receptacles were provided for general refuse collection and sorting. Excavated inert C&D materials were reused to minimize the disposal of C&D waste to public fill.

5.1.3       The Contractor is advised to minimize the wastes generated through recycling or reusing. All applicable mitigation measures stipulated in the Updated EM&A Manual and waste management plans will be fully implemented.


6             Ecology

6.1       Introduction

6.1.1       This section was derived from the ecological monitoring conducted during the construction phase by the Remaining Phase ET, supplemented with findings retrieved from the First Phase ET under Service Contract No. NDO 04/2019 Environmental Team for Environmental Monitoring and Audit Works in Construction Phase for the First Phase Development of Kwu Tung North and Fanling North New Development Areas. This approach was undertaken to prevent redundancy in survey efforts.

6.2       Monitoring Requirements

Weekly Site Inspection

6.2.1       Weekly site inspections by the ET from the First Phase of the KTN/FLN NDAs Project for ecological mitigation measures are conducted as part of the overall weekly environmental site inspections. These inspections audit the ecological mitigation measures implemented within the active works area to ensure that the activities do not significantly impact the ecologically sensitive receivers in the active works areas.

Monitoring of Measures to Minimise Disturbance to Water Birds in Ng Tung River, Sheung Yue River, Shek Sheung River and Long Valley

6.2.2       As stipulated in Section 12.3.2.5 of the Updated EM&A Manual, if development under the NDAs project occurs within 200m of Sheung Yue River, Ng Tung River, Shek Sheung River and Long Valley, weekly transect monitoring at high and low tides (above/below 1.5m at Tsim Bei Tsui Station) should be conducted. The monitoring aims to identify and count bird species in the river channels and Long Valley Nature Park (LVNP) and detect any disturbances from construction activities, following the methodology in Table 12.1 of the Updated EM&A Manual. Monitoring in Long Valley should follow the Hong Kong Bird Watching Society (HKBWS) bird monitoring programme's methodology for comparable and comprehensive results.

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley

6.2.3       As stipulated in Section 12.3.2.14 of the Updated EM&A Manual, aquatic fauna monitoring should be conducted monthly during the wet season (April – October) of the construction phase.


 

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

6.2.4       As stipulated in Section 12.3.2.17 of the Updated EM&A Manual, measures to minimize impacts should be monitored during the construction phase. The purpose of these surveys is to assess the effectiveness of measures aimed at reducing disturbances and pollution in ecologically sensitive habitats through standard fauna transect surveys.

6.2.5       For this reporting month, only transects that are relevant to the active works of Works Contract ND/2024/01, Contract No. ND/2024/02, Contract No. ND/2024/03, Contract No. ND/2024/04, Contract No. ND/2024/06, Contract No. ND/2024/07 and Contract No. ND/2024/08, were included. The active works for the mentioned contracts are described in Section 1.3.1 of this report and shown in Figure 1.1 and Figure 1.2.

6.2.6       Table 6.1 summarizes the relevant transects and monitoring station to each contract under the remaining phase, categorised under the column “First Phase ET” and “Remaining Phase ET” according to the current survey efforts. The locations of these contracts relative to the monitoring locations are shown in Figure 6.1 and Figure 6.2.

Table 6.1 Summary of Monitoring Activities, Relevant Contracts, and Corresponding Transects

Monitoring Activity

Relevant Works Contract(s)

Relevant Transect(s)/Monitoring Station(s)

First Phase ET

Remaining Phase ET

Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung, Sheung Yue, and Shek Sheung Rivers and Long Valley

ND/2024/01*

T1, T2, T3, T5

-

ND/2024/02*

T1, T2, T3, T5

T4

ND/2024/03*

T1, T2, T3, T5

-

ND/2024/04*

-

T4

ND/2024/05*

N/A(1)

N/A(1)

ND/2024/06*

T1, T2, T3

-

ND/2024/07*

T1, T2, T3

T4

ND/2024/08*

T1, T2, T3

T4

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley

ND/2024/01*^

MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10

-

ND/2024/02*^

MS_01, MS_02, MS_03, MS_04, MS_05, MS_06, MS_07, MS_08, MS_09, MS_10

-

ND/2024/03*

N/A(2)

N/A(2)

ND/2024/04*

N/A(2)

N/A(2)

ND/2024/05*

N/A(2)

N/A(2)

ND/2024/06*

N/A(2)

N/A(2)

ND/2024/07*^

MS_11, MS_12, MS_13, MS_14, MS_15

-

ND/2024/08*^

MS_11, MS_12, MS_13, MS_14, MS_15

N/A(2)

 

 

 

 

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

ND/2024/01*

T1

-

ND/2024/02*

T1, T6

-

ND/2024/03*

T4

-

ND/2024/04*

N/A(3)

N/A(3)

ND/2024/05*

T4, T6

-

ND/2024/06*

-

T2

ND/2024/07*

T3

-

ND/2024/08*

T3

-

Remarks:

(1)      Contracts that are located relatively far from river channels.

(2)      Contracts that are located relatively far from Ma Tso Lung and Siu Hang San Tsuen streams.

(3)      Contracts that are located relatively far from the Ecological Sensitive Habitats as identified in the EIA.

(4)      * = active works contracts (ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06, ND/2024/07 and ND/2024/08); ^ = monitoring only in April – October’.

6.2.7       The details of the relevant monitoring activities are discussed in the succeeding sections.

6.3       Results and Observations

Monitoring of Measures to Minimise Disturbance to Water Birds in Ng Tung River, Sheung Yue River, Shek Sheung River and Long Valley

Monitoring Methodology

6.3.1       Birds identified by their calls but not visually located were recorded as "heard", while those observed flying over the survey area were noted as "in flight." Species of conservation importance were also specified. Additional information at the time of the survey, such as weather conditions, tidal conditions, tide levels, and noticeable natural or anthropogenic activities, were documented. For the avifauna survey, ornithological nomenclature referenced The Avifauna of Hong Kong (Carey et al., 2001), The Birds of Hong Kong and South China (Viney et al., 2005), and the most recent updated lists from other sources (e.g., Hong Kong Bird Watching Society).

 

Monitoring Parameters

6.3.2       The monitoring parameters are as follows:

·       Abundance of birds;

·       Types of habitats utilized by birds; and

·       Notable bird behaviours such as roosting, feeding, nesting and presence of juveniles.

 

Monitoring Location

6.3.3       For this reporting month, First Phase ET conducted avifauna monitoring at Ng Tung River, Sheung Yue River, and Long Valley, while the Remaining Phase ET conducted avifauna monitoring at Shek Sheung River. Relevant transect routes are summarized in Table 6.2 and illustrated in Figure 6.1 and Figure 6.2. As the sensitive receivers are large waterbirds and are easily visible, the transect routes only needed to follow one riverbank.

Table 6.2 Summary of Active Works Contracts and Corresponding Transects

Monitoring
Transect(s)

Relevant Works Contract(s)

ND/2024/01

ND/2024/02

ND/2024/03

ND/2024/04

ND/2024/05

ND/2024/06

ND/2024/07

ND/2024/08

T1. Ng Tung River

✓

✓

✓

 

 

✓

✓

✓

T2. Ng Tung River

✓

✓

✓

 

 

✓

✓

✓

T3. Sheung Yue River

✓

✓

✓

 

 

✓

✓

✓

T4. Shek Sheung River

 

✓

 

✓

 

 

✓

✓

T5. Long Valley

✓

✓

✓

 

 

 

 

 

Monitoring Frequency

6.3.4       Avifauna monitoring at high and low tides should be conducted weekly. Additionally, nighttime monitoring in Long Valley should be conducted twice a month from September to April, which is not required for the reporting month.

6.3.5       For this reporting month, waterbird monitoring was conducted by both the First Phase ET (T1, T2, T3 and T5) and Remaining Phase ET (T4). Survey date for each monitoring is shown in Table 6.3.

Table 6.3 Monitoring Programme for Waterbirds Monitoring, June 2026

Week

Date

Transect(1)

1

1 June 2026

T1, T2

2 June 2026

T3, T4, T5

5 June 2026

T4

2

8 June 2026

T1, T2

9 June 2026

T4

12 June 2026

T3, T4, T5

3

15 June 2026

T1, T2, T4

17 June 2026

T3, T4, T5

4

22 June 2026

T3, T4, T5

24 June 2026

T1, T2

25 June 2026

T4

5

30 June 2026

T4

Remarks:

(1)    Transects T1, T2, T3, and T5 are relevant to Works Contract ND/2024/01 and ND/2024/03; Transect T4 is relevant to Works Contract ND/2024/04; Transects T1, T2, and T3 are relevant to Works Contract ND/2024/06; Transects T1, T2, T3 and T4 are relevant to Works Contract ND/2024/07 and ND/2024/08; Transect T1, T2, T3, T4 and T5 are relevant to Works Contract No. ND/2024/02.

Monitoring Results

6.3.6       For this reporting month, only monitoring results in Transects T1, T2, T3, T4 and T5 are reported as not all of these monitoring data are relevant to active Works Contract ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/06, ND/2024/07 and ND/2024/08 as summarised in Table 6.1.

6.3.7       Transect T1 and T2 were conducted along the Ng Tung River. For Transect T1, a total of 3 species of large waterbirds, namely Grey Heron (3 individuals), Great Egret (9 individuals) and Little Egret (32 individuals), were recorded in the reporting month. For Transect T2, a total of 3 species of large waterbirds, namely Grey Heron (5 individuals), Great Egret (9 individuals) and Little Egret (29 individuals), were recorded in the reporting month.

6.3.8       Transect T3 was conducted along the Sheung Yue River. A total of 3 species of large waterbirds, namely Grey Heron (7 individuals), Great Egret (10 individuals) and Little Egret (75 individuals), were recorded for the reporting month.

6.3.9       Transect T4 was conducted along the Shek Sheung River. A total of 3 species of large waterbirds, namely Grey Heron (15 individuals), Great Egret (9 individuals) and Little Egret (53 individuals), were recorded during the reporting month.

6.3.10    Transect T5 was conducted in Long Valley Nature Park with the highest species diversity and abundance recorded. A total of 3 species of large waterbirds, namely Grey Heron (5 individuals), Great Egret (12 individuals) and Little Egret (79 individuals), were also found to utilise the habitat.

6.3.11    Chinese Pond Heron, the most abundant waterbird species recorded during the baseline survey, which is strictly associated with wetlands, was widely noted across different transect routes in the reporting month 189 individuals recorded in total. 31 individuals were noted along Transect T1, 38 individuals along Transect T2, 37 individuals along Transect T3, 15 individuals along Transect T4, and 68 individuals were noted along Transect T5.

6.3.12    Relevant results of the avifauna monitoring conducted by the First Phase ET during this reporting month are detailed in Appendix 6.1a to Appendix 6.1h. Findings of surveys conducted by the Remaining Phase ET during this reporting month are detailed in Appendix 6.1i to Appendix 6.1m.

6.3.13    Table 6.4 summarizes the results of the monitoring of measures to minimize disturbance to waterbirds in Ng Tung River, Sheung Yue River, Shek Sheung River and Long Valley of the reporting month.


 

Table 6.4 Summary Table of Waterbird Monitoring Results Relative to Corresponding Action and Limit Levels, June, Transects T1, T2, T3, T4 and T5

Monitoring Parameter

Result in Reporting Month
(June 2026)

Baseline Level in Corresponding Month
(June 2020)

Action
Level (1)

Limit
Level (2)

T1, T2 and T3

Mean abundance of large waterbirds using Ng Tung River, Sheung Yue River and Shek Sheung River (3)

45

19

13

9

Mean abundance of Chinese Pond Heron using Ng Tung River, Sheung Yue River and Shek Sheung River

27

11

8

6

T4

Mean abundance of large waterbirds using Shek Sheung River (3)

15

3

2

2

Mean abundance of Chinese Pond Heron using Shek Sheung River

3

3

2

1

T5 Long Valley

Mean Abundance of birds (all species) recorded in LVNP

309

440

308

220

Mean abundance of the Chinese Pond Heron

17

21

15

11

Environmental disturbance and damage from activities in LVNP

-

-

Activity likely to cause unacceptable

environmental

disturbance or

damage noted in LVNP.

Activity likely to cause unacceptable

environmental

disturbance or

damage noted in LVNP.

Remarks:

(1)      Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.

(2)      Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.

(3)      Large waterbird species for mean abundance calculation include Great Cormorant (Phalacrocorax carbo); Grey Heron (Ardea cinerea); Great Egret (Ardea alba); Intermediate Egret (Ardea intermedia); Little Egret (Egretta garzetta) and Chinese Egret (Egretta eulophotes).

 

6.3.14    No exceedance in Action or Limit Level was recorded for the reporting month.


 

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream, and Long Valley

6.3.15    Monitoring of larger organisms such as fish species will be carried out through direct counting, while sampling aquatic invertebrates will involve kick-netting and sweep-netting. Three replicates will be conducted for invertebrate sampling at each sampling point. During kick-netting, the net will be positioned at a location with the opening facing the water current while disturbing the substrate through kicking to dislodge organisms from the stream bed. Sweep-netting will be applied to water bodies without water current according to on-site conditions. Species observed will be identified to the lowest possible taxonomic level with their relative abundance recorded, with the use of dissecting microscope especially for small organisms not identifiable through the naked eye.

Monitoring Parameters

6.3.16    The monitoring parameters are as follows:

·       Species composition and abundance;

·       Distribution of invertebrates and fish fauna; and

·       Specify species of conservation importance, if any.

Monitoring Locations

6.3.17    For this reporting month, the First Phase ET conducted the aquatic fauna monitoring along Ma Tso Lung Stream and Siu Hang Sang Tsuen Stream. Specifically, the monitoring stations relevant for the active works under Works Contract ND/2024/01 and ND/2024/02 are:

·       MS_01

·       MS_02

·       MS_03

·       MS_04

·       MS_05

·       MS_06

·       MS_07

·       MS_08

·       MS_09

·       MS_10

And the relevant monitoring stations for Works Contract ND/2024/07 and ND/2024/08 are:

·       MS_11

·       MS_12

·       MS_13

·       MS_14

·       MS_15

6.3.18    The above monitoring stations are shown in Figure 6.1 and Figure 6.2.

Monitoring Frequency

6.3.19    As stated in Section 12.3.2.14 of the Updated EM&A Manual, aquatic fauna monitoring should be conducted monthly during the wet season (April – October) during the construction phase.

6.3.20    For this reporting month, aquatic fauna monitoring was conducted by the First Phase ET on 9 June 2026.


 

Monitoring Results

6.3.21    A total of 16 species of aquatic invertebrates and 5 species of fish were recorded along the Ma Tso Lung Stream and Siu Hang San Tsuen Stream for the reporting month. One native fish species of conservation importance (Predaceous Chub) was noted for the reporting month, according to the findings of the First Phase ET. A complete species list is enclosed as Appendix 6.2.

6.3.22    1 monitoring station, namely MS_05, was found to be dried-up. Thus, no aquatic fauna species were recorded.

6.3.23    Table 6.5 and Table 6.6 summarized the aquatic monitoring results for the reporting month.

Table 6.5 Summary Table of Monitoring Results for Aquatic Invertebrates Relative to Action and Limit Levels, June, Monitoring Station MS_01 – MS_15

Monitoring Station

Result in Reporting Month (June 2026) (1)

Baseline Level in Corresponding Month (June 2020) (1)

Action Level(2)

Limit Level(3)

MS_01

0

0

N/A

N/A

MS_02 and MS_03

2

3

2

1

MS_04, MS_06 and MS_07

4

3

2

1

MS_05

0

0

N/A

N/A

MS_08, MS_09 and MS_10

2

3

2

1

MS_11

0

0

N/A

N/A

MS_12

0

0

N/A

N/A

MS_13 and MS_14

2

1

N/A

N/A

MS_15

1

0

N/A

N/A

Remarks:

(1)      Number of native species (species richness) recorded.

(2)      Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.

(3)      Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.

Table 6.6 Summary Table of Monitoring Results for Fish Species Relative to Action and Limit Levels, June, Monitoring Station MS_01 – MS_15

Monitoring Station

Result in Reporting Month (June 2026) (1)

Baseline Level in Corresponding Month (June 2020) (1)

Action Level(2)

Limit Level(3)

MS_01

0

0

N/A

N/A

MS_02 and MS_03

0

1

N/A

N/A

MS_04, MS_06 and MS_07

2

3

2

1

MS_05

0

0

N/A

N/A

MS_08, MS_09 and MS_10

0

0

N/A

N/A

MS_11

0

0

N/A

N/A

MS_12

0

0

N/A

N/A

MS_13 and MS_14

0

0

N/A

N/A

MS_15

0

1

N/A

N/A

Remarks:

(1)    Number of native species (species richness) recorded.

(2)      Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.

(3)      Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.

6.3.24    No exceedance in Action or Limit Level was recorded for the reporting month.

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

Monitoring Methodology

Terrestrial Mammal

6.3.25    Mammal surveys were conducted both during the day and at night along transect routes that may be potentially utilized by terrestrial mammals. Observations included field signs such as droppings, footprints, diggings, and burrows left by larger terrestrial mammals. Any mammals directly observed were recorded, and identification was as accurate as possible based on the field signs.

6.3.26    Bat surveys were conducted along the transect routes shortly after sunset using a bat detector to record echolocation calls. The relative abundance of the species encountered were estimated with reference to the baseline monitoring results, using a scale from one (species recorded within transect routes) to three (dominant species within transect routes), for comparison between baseline and current monitoring results. Mammal nomenclature followed Shek (2006).

6.3.27    Echolocation calls of bats were recorded using a bat detector, which listed possible bat species with similar call patterns and frequencies. The structure of the recorded echolocation calls was later analysed to identify species as accurately as possible. Due to the lack of literature on echolocation call structures, field identification of some bat species in Hong Kong is challenging, and some species could only be identified to the genus level or remain unidentified from the recordings.

6.3.28    Identification of bat species encountered in the surveys was made by considering the possible species suggested by the bat detector, their distribution in Hong Kong, previous records in the EIA Report and Baseline Monitoring Report, and the structure of the echolocation calls (including call structure, frequency, duration, and inter-pulse interval) with reference to relevant literature.

Herpetofauna (Amphibians and Reptiles)

6.3.29    Both daytime and nighttime amphibian surveys were conducted whenever possible following or during periods of rainfall, focusing on areas suitable for amphibians (e.g., forests, shrublands, grasslands, streams, ponds, marshes, etc.). Calling amphibians were recorded, supplemented by visual observations of eggs, tadpoles, adult frogs, and toads.

6.3.30    Active searches of appropriate microhabitats, such as stones, pond bunds, crevices, and leaf debris, was primarily conducted. Observations of exposed, basking, and foraging reptiles were also carried out. Nomenclature for amphibians and reptiles followed Chan et al. (2005) and Karsen et al. (1998), respectively.

Butterfly and Odonates

6.3.31    Butterflies and dragonflies observed along the transects were identified and counted. Special attention was given to their preferred habitats, such as watercourses, fishponds, and vegetated areas. Nomenclature and protection status of the species followed Lo et al. (2005) for butterflies and Tam et al. (2011) for dragonflies.

Monitoring Parameters

6.3.32    The monitoring parameters are as follows:

·       Species composition;

·       Abundance;

·       Distribution for fauna observed; and

·       Species of conservation importance would be specified.

Monitoring Location

6.3.33    According to the Updated EM&A Manual, the transect routes for monitoring of ecologically sensitive receivers should follow the following:

·       T1. Ma Tso Lung riparian zone and associated wetland habitats; green belt areas E1-8, D1-8 and G1-3 in KTN NDA; AGR zone C2-4 and C2-2 in KTN NDA, and area north of Ng Tung River;

·       T2. Fanling North Freshwater Service Reservoir

·       T3. Area west of Siu Hang San Tsuen Stream;

·       T4. South side of Fanling Highway and Castle Peak Road in the vicinity of Pak Shek Au;

·       T5. Area west and east of the southern limit of the FLN NDA work area; and

·       T6. Areas in the western part of KTN.

6.3.34    The above transects are shown in Figure 6.1 and Figure 6.2. Relevant transect to Works Contract ND/2024/01 is Transect T1 which covers areas of Ma Tso Lung riparian zone and associated wetland habitats, green belt areas E1-8, D1-8 and G1-3 in KTN NDA, AGR zone C2-4 and C2-2 in KTN NDA, and areas North of Ng Tung River; relevant transects to Works Contract ND/2024/02 are Transect T1 and T6, of which the latter covers areas to the west of the KTN NDA work area; relevant transect to Works Contract ND/2024/03 is Transect T4 which covers the south side of the Fanling Highway and Castle Peak Toad in the vicinity of Pak Shek Au; relevant transect to Works Contract ND/2024/06 is Transect T2 which covers areas of the Fanling North Freshwater Service Reservoir; Works Contract ND/2024/07 involves Transect T3 which covers the area west of Siu Hang San Tsuen stream; and Works Contract ND/2024/08 involves Transect T3 as well.

Monitoring Frequency

6.3.35    Monthly monitoring should be conducted for non-aquatic fauna, including terrestrial mammals, insects (butterflies and odonates), and herpetofauna. For this reporting month, monthly monitoring for non-aquatic fauna were conducted by both the First Phase ET (T1, T3, T4 and T6) and Remaining Phase ET (T2). Survey dates for each monitoring are shown in Table 6.7.

Table 6.7 Monitoring Programme for Non-aquatic Fauna Monitoring, June 2026

Responsible ET

Date

Transect(1)

First Phase ET

10 June 2026

T3, T4

16 June 2026

T1, T6

Remaining Phase ET

24 June 2026

T2

Remarks:

(1)    Transect T1 is relevant to Works Contract ND/2024/01 and Works Contract ND/2024/02; Transect T2 is relevant to Works Contract ND/2024/06; Transect T3 is relevant to Works Contracts ND/2024/07 and ND/2024/08; Transect T4 is relevant to Works Contract ND/2024/03 and ND/2024/05; Transect T6 is relevant to Works Contract ND/2024/02 and ND/2024/05.

 

Monitoring Results

Terrestrial Mammals

6.3.36    A total of 2 species of terrestrial mammals (1 native and 1 introduced) were recorded along Transect T1. Japanese Pipistrelle recorded during the survey is a native species of conservation importance. 5 native bat species of conservation importance, namely Himalayan Leaf-nosed Bat, Chinese Noctule, Japanese Pipistrelle, Least Pipistrelle and Lesser Yellow Bat, were recorded along Transect T2 for the reporting month. 2 native bat species of conservation importance, namely Japanese Pipistrelle and Short-nosed Fruit Bat, were recorded along Transect T3. A total of 2 species of terrestrial mammals (1 native and 1 introduced) were recorded along Transect T6. Japanese Pipistrelle recorded during the survey is a native species of conservation importance. No terrestrial mammals were noted along Transect T4 for the reporting month. A complete species list is enclosed as Appendix 6.3.

Herpetofauna (Amphibians and Reptiles)

6.3.37    A total of 6 herpetofauna species (6 amphibians) were recorded along Transect T1, with 1 species, namely the Spotted Narrow-mouthed Frog, is of conservation importance. Other species noted are all common, widespread natives. 5 native herpetofauna species (2 amphibians and 3 reptile species) were recorded along Transect T2, of which all are considered common and widespread locally. 4 native species of herpetofauna species (3 amphibians and 1 reptiles) were recorded along Transect T3 for the reporting month. All species are widespread and locally common. A total of 3 native herpetofauna species (2 amphibians and 1 reptile species) were recorded along Transect T4, with no species of conservation importance noted. 4 native and widespread herpetofauna species (3 amphibians and 1 reptile) were recorded along Transect T6. A complete species list is enclosed as Appendix 6.3.


 

Butterfly and Odonates

6.3.38    A total of 11 butterfly and 3 odonate species were recorded along Transect T1. All species recorded are considered as common, widespread natives. 15 butterfly species were recorded along Transect T2 for the reporting month, with 1 species, namely the Swallowtail, is of conservation importance. 4 odonate species were recorded during the monitoring for the reporting month, with 1 species, namely the Blue Chaser, is of conservation importance, along with other common, widespread natives. A total of 11 butterfly and 1 odonate species were recorded along Transect T3 with no species of conservation importance noted. 15 butterfly species and 1 odonate species were recorded along Transect T4. All species recorded are considered as locally widespread natives. 9 butterflies species were recorded along Transect T6 for the reporting month. No odonates species were noted for the reporting month. A complete species list is enclosed as Appendix 6.3.

Summary of Monitoring Results

6.3.39    Monitoring for non-aquatic (terrestrial mammals, butterflies, dragonflies, and herpetofauna) taxa was conducted by both the First Phase and Remaining Phase ETs. Relevant results of the non-aquatic fauna monitoring conducted by the First Phase ET during this reporting month are detailed in Appendix 6.3a to Appendix 6.3d. Findings of surveys conducted by the Remaining Phase ET during this reporting month are detailed in Appendix 6.3e to Appendix 6.3h.

6.3.40    Tables 6.8 summarizes the monitoring results of Transect T1, T2, T3, T4 and T6 for this reporting month.

Table 6.8 Summary Table of Monitoring Results for Non-aquatic Fauna Relative to Action and Limit Levels, June 2026, Transect T1, T2, T3, T4 and T6

Monitoring Parameter

Result in
Reporting Month
(June 2026) (1)

Baseline Level in Corresponding Month (June 2020) (1)

Action Level(2)

Limit Level(3)

T1

Terrestrial Mammals

1

1

N/A

N/A

Herpetofauna

6

8

6

4

Odonates

3

10

7

5

Butterflies

11

14

10

7

T2

Terrestrial Mammals

5

0

N/A

N/A

Herpetofauna

5

2

N/A

1

Odonates

4

0

N/A

N/A

Butterflies

15

5

4

3

T3

Terrestrial Mammals

2

0

N/A

N/A

Herpetofauna

4

6

4

3

Odonates

1

8

6

4

Butterflies

11

6

4

3

T4

Terrestrial Mammals

0

0

N/A

N/A

Herpetofauna

3

4

3

2

Odonates

1

6

4

3

Butterflies

15

8

6

4

T6

Terrestrial Mammals

1

1

N/A

N/A

Herpetofauna

4

5

4

3

Odonates

0

6

4

3

Butterflies

9

13

9

7

Remarks:

(1)      Number of species (species richness) recorded; the results in the reporting month for terrestrial mammals, herpetofauna and odonates are calculated based on the number of native species recorded along the transects.

(2)      Exceedance of Action Level occurs when the monitoring result is lower than the Action Level.

(3)      Exceedance of Limit Level occurs when the monitoring result is lower than the Limit Level.

6.3.41    Four Limit Level exceedances (Odonates for Transect T1, T3, T4 and T6) were recorded for Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution during the reporting month. All exceedances were considered non-project related, as no evidence suggested it was associated with project activities. Additionally, the low species diversity of odonate species was potentially impacted by the adverse weather conditions recorded throughout the reporting month. Territory-wide rainstorms were noted across the scheduled survey days, events such as thunderstorms and heavy rains had potentially inhibited the emergence and movement of adult odonates species, leading to a significantly lower species diversity observed. As a result, the exceedances recorded can be explained as a temporary effect of the weather events, rather than representing a long-term decline.

Details of the Influencing Factors

6.3.42    The details of the influencing factors were adopted from the observations of the First Phase ET. During the monitoring of measures to minimize disturbance to waterbirds in Long Valley and Sheung Yue River, anthropogenic activities such as excavation and other construction activities were observed near Long Valley. It should also be noted that the Long Valley Nature Park has been opened to the public since 09 November 2024. Potential increase in people visiting the park may potentially impact the habitats in Long Valley and cause disturbances to the bird communities in this area. Construction works were also observed along Sheung Yue Riverr.

6.3.43    During the monitoring of measures to minimize disturbance to waterbirds in Ng Tung River, various anthropogenic activities were observed, such as construction works along Transect T2, recreational use of remote-control boats and toy helicopters in both Transects T1 and T2, and recreational fishing along these two transects.


 

Survey Summary

6.3.44    All ecological monitoring surveys for the reporting month have been carried out as scheduled, with 4 exceedances in Limit Level were reported for odonate species during the non-aquatic fauna survey conducted by the First Phase ET. All exceedances were considered as non-project related.

6.4       Event and Action Plan

6.4.1       Should non-compliance of the ecological monitoring criteria occur, actions in accordance with the Event and Action Plan in Appendix 6.4 shall be carried out.


 

7             Landscape and Visual

7.1       Audit Requirements

7.1.1       According to the approved EM&A manual and Updated EM&A Manual for the First Phase, site audits should be undertaken at least once every two weeks during the construction period, by the Environmental Team. Particularly, to check that the proposed landscape and visual mitigation measures are properly implemented and maintained as per their intended objectives. Mitigation measures recommended in the EIA Report as the audit requirements including, preservation of existing vegetation, transplanting of affected trees, compensatory tree planting, control of night-time lighting glare, erection of decorative screen hoarding and management of construction activities and facilities.

7.2       Results and Observations

7.2.1       Bi-weekly landscape and visual site audits were carried out by the ET during the reporting period. Inspections were carried out on 08 and 23 June 2026 for ND/2024/01, 8 and 26 June 2026 for ND/2024/02, 8 and 22 June 2026 for ND/2024/03, 5 and 15 June 2026 for ND/2024/04, 9 and 23 June 2026 for ND/2024/05, 1, 15 and 22 June 2026 for ND/2024/06, 4 and 18 June 2026 for ND/2024/07, 10 and 26 June 2026 for ND/2024/08. No particular observation was recorded in this reporting period.

7.3       Event and Action Plan

7.3.1       Should any non-compliance of the criteria occur, action in accordance with the Event and Action Plan in Appendix 7.1 shall be followed.


 

8             Land Contamination (Ambient Arsenic Monitoring)

8.1       Monitoring Requirements

8.1.1       According to the approved EM&A Manual and Updated EM&A Manual for the First Phase, an ambient arsenic monitoring is required to be conducted in KTN during the clean-up processes of arsenic containing soil and the construction phase.

8.1.2       The RSP concentration was measured by HVS equipped with PM10 selector (PM10 HVS) following the "Reference Method for the Determination of Particulate Matter as PM10 in the Atmosphere" Part 50 Chapter 1 Appendix J, Title 40 of the Code of Federal Regulations of the USEPA.

8.1.3       The Dust-laden air was drawn through PM10 HVS fitted with a conditioned pre-weighting filter paper, at a controlled rate. After sampling for 24-hour, the filter paper with retained PM10 particulates was collected and returned to the laboratory for drying in a desiccator followed by accurate weighting. 24-hour average RSP levels were calculated from the ratio of the mass of PM10 particulates retained on the filter paper to the total volume of air sampled.

8.1.4       The weighted filter paper was prepared for arsenic testing through a "Hot Acid Extraction Procedure". The extracted material was tested for arsenic by using Inductively Coupled Plasma/Mass Spectrometry (ICP/MS). The extraction and testing were referenced to the following methods:

·       Compendium Method 1O-3.1 Selection, Preparation and Extraction of Filter Material, Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999; and Compendium Method 1O-3.5 determination of Metals in Ambient Particulate Matter using Inductively Coupled Plasma/Mass Spectrometry (ICP/MS., Center for Environmental Research Information, Office of Research and Development, USEPA, June 1999.

8.2       Monitoring Locations

8.2.1       Ambient arsenic monitoring was conducted at the monitoring station(s) under the Work Contract(s), as shown in Table 8.1 describes the location of the ambient arsenic monitoring station. The location of the ambient arsenic monitoring station is presented in Figure 8.1.

Table 8.1 Location of Ambient Arsenic Monitoring station

Monitoring Station(s)

Location(s)

Works Contract(s)

KTN-DMS-4A(1)(2)

Temporary Structure at Pak Shek Au

ND/2024/01

Remarks:

(1)    Monitoring at the original location of KTN-DMS-4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS-4A) was proposed by First Phase ET.

(2)    The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.

8.3       Monitoring Equipment

8.3.1       Table 8.2 summarises the equipment used in the ambient arsenic monitoring. Copies of the calibration certificates for ambient arsenic monitoring are shown in Appendix 8.1

Table 8.2 Ambient Arsenic Monitoring Equipment

Monitoring

Station

Equipment

Manufacturer

Model

No. of Equipment

KTN-DMS-4A(1)(2)

Calibrator

TISCH

TE-5025A

1

HVS Sampler (RSP)

TISCH

TE-6070X

1

Remarks:

(1)    Monitoring at the original location of KTN-DMS-4 (originally proposed in the approved EM&A Manual) was denied as there was no electricity supply. An alternative location (KTN-DMS-4A) was proposed by First Phase ET.

(2)    The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.

8.4       Monitoring Parameters, Frequency and Duration

8.4.1       Table 8.3 summarises the monitoring parameters and frequencies of ambient arsenic during the clean-up processes of arsenic-containing soil and construction. The ambient arsenic monitoring schedule for the reporting month shown in Appendix 2.1.

Table 8.3 Impact Ambient Arsenic Monitoring Parameters, Frequency and Duration

Parameters

Frequency(1)

24-hour RSP (Ambient Arsenic)

Once/ 6 days

Remark:

1.      The ambient arsenic monitoring was conducted by First Phase ET during the reporting period.


 

8.5       Monitoring Methodology and QA/QC Procedure

 

Instrumentation

8.5.1       HVS (GMW PM10 (TE6070X)) complete with appropriate sampling inlets was employed for 24-hour RSP monitoring. The sampler was composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complied with that required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50).

8.5.2       The following guidelines were adopted during the installation of HVS:

·       a horizontal platform with appropriate support to secure the samplers against gusty wind was provided;

·       no two samplers were placed less than 2 meters apart;

·       the distance between the sampler and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler;

·       a minimum of 2 meters of separation from walls, parapets and penthouses was required for rooftop samplers;

·       a minimum of 2 meters separation from any supporting structure, measured horizontally was required;

·       no furnace or incinerator flue was nearby;

·       airflow around the sampler was unrestricted;

·       the sampler was more than 20 meters from the dripline;

·       any wire fence and gate, to protect the sampler, were not cause any obstruction during monitoring;

·       permission was obtained to set up the samplers and to obtain access to the monitoring stations; and

·       a secured supply of electricity was needed to operate the samplers

 

Operating/analytical procedures for the operation of HVS

 

·         Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 1.1 m3 /min. and 1.4 m3 /min.) in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50;

·         The power supply was checked to ensure the sampler worked properly. On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station;

·         The filter holding frame was then removed by loosening the four nuts and a weighted and conditioned filter was carefully centered with the stamped number upwards, on a supporting screen;

·       The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame was then tightened to the filter holder with swing bolts. The applied pressure was sufficient to avoid air leakage at the edges;

·       The shelter lid was closed and secured with the aluminium strip;

·       The timer was then programmed. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number);

·       After sampling, the filter was removed and sent to the Wellab Ltd. for weighing. The elapsed time was also recorded; and

·       Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature was between 25°C and 30°C and did not vary by more than ±3°C; the relative humidity (RH) was < 50% and did not vary by more than ±5%. A convenient working RH was 40%. Weighing results were further analysis of RSP concentrations collected by each filter.

8.6       Maintenance/Calibration

8.6.1       The following maintenance/calibration was required for the HVS:

·       The high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply were in good working condition; and

·       High volume samplers were calibrated at bi-monthly intervals using TE-5025A Calibration Kit throughout all stages of the ambient arsenic monitoring.

8.7       Laboratory Measurement / Analysis

8.7.1       Quartz filters of size 8” x 10” were labelled before sampling. A HOKLAS accredited laboratory, Wellab Ltd., was responsible for the preparation of 24-hour conditioned and pre-weighed filter papers for the monitoring team. The balance for weighting filter paper was regularly calibrated against a traceable standard.

8.7.2       All filters, which were prepared and equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C; the relative humidity (RH) was < 50% and not variable by more than ±5%. A convenient working RH was 40%.

8.7.3       Wellab Ltd. (HOKLAS Registration No. HOKLAS083), was responsible for the extraction and testing procedure for Arsenic and comprehensive quality assurance and quality control programmes were conducted.

 

 

8.8       Result and Observations

8.8.1       The ambient arsenic monitoring results are summarised in Table 8.4.

Table 8.4 Result Summary Against Action and Limit Levels for 24-hour RSP Monitoring Results (Ambient Arsenic)

Contract No.

Monitoring

Date

Monitoring

Station

Concentration

(ƞg/m3)

AL

(ƞg/m3)

LL

(ƞg/m3)

ND/2024/01

1/6/2026

KTN-DMS4A*

3.06

9.36

11.7

5/6/2026

3.77

11/6/2026

3.38

16/6/2026

3.99

22/6/2026

3.84

26/6/2026

3.12

Remark:

* The 24-hour RSP monitoring for ambient arsenic was conducted by First Phase ET during the reporting period.

8.8.2       All ambient arsenic monitoring was conducted as scheduled in the reporting month. During the reporting month, 212.71m3 of arsenic soil transported to soil treatment plant and treated. No AL or LL exceedances were recorded.

8.9       Event and Action Plan

8.9.1       Should any non-compliance of the criteria occur, actions in accordance with the Event/Action Plan in Appendix 8.2 shall be carried out.

 

 


9             Landfill Gas Monitoring

9.1       Monitoring Requirements

9.1.1       In accordance with the updated EM&A Manual, monitoring of landfill gas (LFG) is required for the construction works within the 250m Landfill Consultation Zone of Ma Tso Lung (MTLL, close to KTN NDA) during the construction phase. This section presents the results of landfill gas measurements performed by the Contractor.

9.1.2       The MTLL is situated in the vicinity of the KTN NDA. A portion of the development falls within the 250m Landfill Consultation Zone of MTLL.

9.2       Monitoring Parameters and Frequency

9.2.1       Monitoring parameters for Landfill gas monitoring include Methane, Carbon dioxide and Oxygen.

9.2.2       Monitoring According to the mitigation measures of the updated EM&A Manual, measurements of the following frequencies should be carried out according to the monitoring requirements and procedures specified in Paragraphs 8.23 to 8.28 of EPD's Guidance Note, “LANDFILL GAS HAZARD ASSESSMENT GUIDANCE NOTE”.

9.2.3       The frequency of monitoring of LFG was made reference to the updated EM&A Manual - Monitoring of any LFG which may be migrated to the site should be undertaken during construction of the infrastructure and the development within the Consultation Zone and within MTLL when the works involve confined spaces. Routine gas monitoring should be undertaken during groundwork construction and in all excavations. Monthly gas monitoring should also be conducted for set up on site such as offices, stores etc.

9.3       Monitoring Locations

9.3.1       As confirmed by the Supervisor Team, no ground disturbance works were carried out in the work area within 250m Landfill Consultation Zone of Ma Tso Lung Landfill including construction of the infrastructure, development works, excavation works and works involve confined spaces. Routine gas monitoring should be undertaken during groundwork construction and in all excavations. Thus, in this reporting month, the area is not required to be monitored for landfill gas are shown below.

 

Ø     Excavation Locations: N/A

Ø     Manholes and Chambers: N/A

Ø     Relocation of monitoring wells: N/A

Ø     Any other Confined Spaces: N/A

9.4       Result and Observations

9.4.1       As confirmed by the Supervisor Team, no ground disturbance works were carried out in the work area within 250m Landfill Consultation Zone of Ma Tso Lung Landfill including construction of the infrastructure, development works, excavation works and works involve confined spaces. Routine gas monitoring should be undertaken during groundwork construction and in all excavations. Therefore, no landfill gas monitoring was carried out.


 

10       Built Heritage Monitoring

10.1   Monitoring Requirements

10.1.1    In accordance with the updated EM&A Manual, baseline condition survey and baseline vibration impact assessment shall be conducted for identified built heritage prior to the commencement of construction works. Baseline condition survey and baseline vibration impact assessment shall be conducted by a qualified building surveyor or qualified structural engineer to define the vibration limit (a vibration limit at 7.5mm/s and 15mm/s could be adopted for graded historical buildings and historical buildings respectively) and to evaluate if construction vibration monitoring and structural strengthening measures are required during construction phase to ensure the construction performance meets the vibration standard stated in the EIA report.

10.1.2    According to the condition survey report from cultural heritage condition survey for ND/2024/01 under EP-468/2013A and for ND/2024/03 under EP-465/2013A and EP-466/2013A a vibration monitoring plan was proposed for the surveyed cultural heritage, the Alert/Alarm/Action (3As) levels was adopted as recommended by the Antiquities and Monuments Office (AMO). This section presents the results of built heritage monitoring performed by the Contractor according to the proposed monitoring plan in baseline condition survey report.

10.2   Monitoring Location

10.2.1    In the reporting month, construction vibration monitoring was conducted for built heritage features at G203 when vibration-induced site activities (e.g. excavation, sheet piling, etc.) were conducted within assessment area of the construction works. The location of the construction vibration monitoring stations was summarised in Table 10.1 and shown in Appendix 10.1.

Table 10.1 Location of Construction Vibration Monitoring

EP No.

Contact No.

Monitoring Station(s)

Nature of Cultural Heritage

Location(s)

EP-465/2013A, EP-466/2013A and EP-467/2013A

ND/2024/03

G203*

Enchi Lodge

Castle Peak Road – Kwu Tung

Remark:

* Since the access right to the original vibration monitoring points at Enchi Lodge was formally declined, alternative monitoring station were proposed within the construction site area of ND/2024/03 and accepted by Antiquities and Monuments Office (AMO).

10.3   Monitoring Parameters and Frequency

10.3.1    Table 10.2 summarises the vibration monitoring plan for surveyed cultural heritage under the Works Contracts. Vibration monitoring was conducted for surveyed built heritage when vibration-induced site activities (e.g. excavation, sheet piling, etc.) were conducted within the assessment area of construction works.


 

Table 10.2 Vibration Monitoring Plan

EP No.

Contact No.

Monitoring Station(s)*

Distance with Construction Works

Monitoring Plan

EP-465/2013A, EP-466/2013A and EP-467/2013A

ND/2024/03

G203

Within 50m

 

Within 75m

 

Within 100m

Daily assessment is required

Bi-daily assessment is required

Weekly assessment is required

Remark:

* Baseline condition survey was conducted for built heritage features at G302, G303, G308, KT26, KT53, KT65 and HKT03 for ND/2024/01 under EP-468/2013/A, G102, G202, G203, G303 and HKT03 for ND/2024/03 under EP-465-2013A and EP-466/2013A. As G102, G202, G203, G302, G303, G308, HKT03, KT26, KT 53 and KT65 were not within the assessment area of the related construction work, no construction vibration monitoring was conducted for the built heritage in the reporting month.

10.3.2    The construction vibration monitoring is planned to be conducted throughout each event of the vibration-induced site activities (e.g. excavation, sheet piling, etc.) on daily / bi-daily / weekly basis. The effect of ground-borne vibration from piling works on the surveyed built heritage was assessed by the maximum peak particle velocity (ppv), which was obtained from the maximum value of measurement of all vibration-induced site activities (e.g. excavation, sheet piling, etc.).

10.4   Monitoring Equipment

10.4.1    Copies of calibration certificates of the monitoring equipment employed by the Contractor of the construction vibration monitoring are attached in Appendix 10.2.

10.5   Result and Observations

10.5.1    In the reporting month, construction vibration monitoring was carried out by the Contractor for the built heritage features at G203 on a daily basis when vibration-induced site activities (e.g. excavation, sheet piling, etc.) were conducted within 50m of the construction work. No Limit Level exceedance for construction vibration monitoring was recorded in the reporting month. The monitoring results are provided in Appendix 10.3.

10.6   Event and Action Plan

10.6.1    Table 10.3 summarises the vibration limits for construction vibration monitoring for surveyed cultural heritage under ND/2024/01 and ND/2024/03, based on the Alert/Alarm/Action (3As) levels as recommended by the AMO.

Table 10.3 Levels of Alert, Alarm and Actions for Tilting, Vibration and Settlement

Monitoring Types

Alert

Alarm

Acton

Tilting

1:2000

1:1500

1:1000

Settlement

6 mm

8 mm

10 mm

Ground Settlement

15 mm

20 mm

25 mm

Vibration (PPV)

5 mm/s

6 mm/s

7.5 mm/s

10.6.2    If any exceedance of limits is found or damage to either structural or non-structural elements of the historic buildings is identified, the construction works should be stopped immediately and structural engineers’ advice should be sought for any remedial work.

 

 


 

11       Environmental Site Inspection and Audit

11.1   Implementation Status of Environmental Mitigation Measures

11.1.1    Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, Works Contract No. ND/2024/01 on 2, 8, 18, 23, 30 June 2026. For Works Contact No. ND/2024/02 were carried out on 2, 8, 18, 26, 30 June 2026. For Works Contact No. ND/2024/03 were carried out on 1, 8, 17, 22, 29 June 2026. For Works Contact No. ND/2024/04 were carried out on 5, 12, 15, 26 June 2026. For Works Contact No. ND/2024/05 were carried out on 2, 9, 17, 23, 30 June 2026. For Works Contact No. ND/2024/06 were carried out on 1, 12, 15, 22, 29 June 2026. For Works Contract No. ND/2024/07 were carried out on 4, 11, 18, 25 June 2026. For Works Contract No. ND/2024/08 were carried out on 3, 10, 26 June 2026, the originally scheduled weekly environmental site inspection on 18 June 2026 was cancelled, due to the adverse weather conditions.

11.1.2    Some major environmental deficiencies were observed during weekly site inspection in the report period and some general reminders regarding environmental aspects were given to the Contractor. Key observations and reminders observed during the site inspections at Works Contract No. ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06, ND/2024/07 and ND/2024/08 in the reporting period are summarized in Table 11.1.

Table 11.1 Site Observations at Works Contract No. ND/2024/01, ND/2024/02, ND/2024/03, ND/2024/04, ND/2024/05, ND/2024/06, ND/2024/07 and ND/2024/08 during the Reporting Period

Works Contracts

Inspection Date

Key Observations/ Reminders

Follow-up Action

ND/2024/01

2 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

Nil

Nil

8 June 2026

Observation:

 

1. Water and dirt accumulated near the site barrier should be removed at Portion 25.

 

2. Chemical container on site should be placed on drip trays, or to be properly removed if it is empty at Portion 25.

 

 

1. Water and dirt near the site barrier were removed.

 

2. The chemical container was removed.

 

Reminder:

 

1. The NRMM label with faded colour is reminded to be replaced at Portion 25.

 

Nil

18 June 2026

Observation:

 

1. At Portion 59, chemical container on site should be placed on drip tray and labelled. Or it should be removed properly if it is no longer in use.

 

 

1. The chemical container was removed.

Reminder:

 

Nil

Nil

23 June 2026

Observation:

 

1. At Portion 25, frequency of watering should be increased to avoid dusty conditions.

 

 

1. Regular watering was enhanced.

Reminder:

 

1. At portion 25, the Contractor was reminded to regularly dispose of general refuse collected.

 

2. At portion 40, the Contractor was reminded that the portion of any road leading only to construction site should be kept clear of dusty materials.

Nil

30 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

Nil

Nil

ND/2024/02

2 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

8 June 2026

Observation:

 

Nil

Nil

Reminder:

 

1. The Contractor is reminded to ensure that the haul road near the site entrance and wheel washing bay is cleaned regularly at Portion 5.

Nil

18 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

26 June 2026

Observation:

 

Nil

Nil

Reminder:

 

1. At Area D, the haul road between the site exit and the wheel-washing facility is reminded to be cleaned often.

Nil

30 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

ND/2024/03

1 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

1. At new site office location, NRMM label should be posted conspicuously on the Non-Road Mobile Machinery.

Nil

8 June 2026

Observation:

 

1. The contractor was reminded that any excavated material or stockpile of dusty material should be removed when no construction work occurred at R526.

 

 

1. The stockpile was removed.

Reminder:

 

Nil

Nil

17 June 2026

Observation:

 

1. Muddy water and scattered mud were observed on the access road in front of Site Office and Contract ND/2024/05 WA2 after rainfall. The contractor was reminded to clean the access road promptly to prevent mud from being carried outside the construction site.

 

 

1. The access road and WA2 area was cleaned up.

Reminder:

 

Nil

Nil

22 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

29 June 2026

Observation:

 

Nil

Nil

Reminder:

1. At Iron Work Field (鐵場), the Contractor was reminded to treat all site wastewater using silt removal facilities to meet the required discharge licence standards before disposal.

Nil

ND/2024/04

5 June 2026

Observation:

 

1. At portion 2, muddy water seepage was observed leaking outside the site boundary. The Contractor was reminded to enhance mitigation measures to avoid any seepages and clear the muddy water immediately

 

 

1. The muddy water seepage was cleaned up.

Reminder:

 

1. At portion area ABC and portion 2, the colour of the NRMM label posted on the Non-Road Mobile Machineries was faded.

Nil

12 June 2026

Observation:

 

1. At portion 1, stockpiles should be covered or removed to avoid overflow of muddy water from entering nearby stream.

 

2. At portion 2, mitigation measures should be enhanced to ensure no seepages of muddy water to area outside site boundary.

 

 

1.The stockpile was removed.

 

 

 

 

2. Sandbags were deployed at the edge of the site boundary.

Reminder:

 

Nil

Nil

15 June 2026

Observation:

 

Nil



Nil

Reminder:

 

1. At Portion 1, the NRMM label on site with faded colour should be replaced.

 

2. At portions 1 and 5, the drainage facilities on site are reminded to be properly maintained, and runoff is reminded to be properly treated before discharge according to the discharge license.

Nil

26 June 2026

Observation:

 

Nil

Nil

Reminder:

 

1. At Portion 2, the temporary drainage system and wheel washing facilities are reminded to be properly maintained. Regular cleaning is also reminded to be carried out at site exits as often as necessary.

 

2. At portions 1 (Near Tai Tau Leng Playground), geotextile or sandbags are reminded to be provided to the storm drains on site.

Nil

ND/2024/05

2 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

9 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

17 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

23 June 2026

Observation:

 

Nil



Nil

Reminder:

 

1. At WA2, the Contractor was reminded to enhance the mitigation measures to avoid seepages of muddy water outside site boundary at the entrance.

Nil

30 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

ND/2024/06

1 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

1. At portion D, the colour of the NRMM label posted on the Non-Road Mobile Machinery faded.

Nil

12 June 2026

Observation:

 

1. At portion A, sediment in the settling pit should be removed.

 

 

1. The sediment was removed.

 

Reminder:

 

Nil

Nil

15 June 2026

Observation:

 

1. At portion C, broken sandbags should be replaced.

 

 

1. The broken sandbags were replaced.

Reminder:

 

1. At portion A, the contractor was reminded to ensure the NRMM label was securely affixed to the machinery.

Nil

22 June 2026

Observation:


1. Oil stains should be cleaned up properly at Area C. The Contractor was reminded to provide impervious sheeting for placing the breaker head to avoid contamination.

 

 

1. The oil stain was removed, and impervious sheeting was provided under the breaker head.

Reminder:


1. Stagnant water inside the drip tray was observed at Portion D. The contractor was reminded to clear the stagnant water after raining.

Nil

29 June 2026

Observation:

 

1. Black smoke emission from the generator should be avoided. The Contractor was reminded to regularly check the condition of the air filter inside the machinery equipment used on site at Portion A.

 

2. NRMM labels should be displayed on excavators at Portion A.

 

 

1. The generators were checked, no further black smoke emission was observed.

 

 

 

 

2.NRMM labels were displayed on the excavators.

Reminder:


1. The contractor was reminded to regularly direct site runoff to wastewater treatment facility especially after raining at Pit F.

Nil

ND/2024/07

4 June 2026

Observation:

 

Nil

Nil

Reminder:


1. At Area C, breaker should be wrapped with acoustic blanket.

Nil

11 June 2026

Observation:


Nil

Nil

Reminder:


Nil

Nil

18 June 2026

Observation:


Nil

Nil

Reminder:


Nil

Nil

25 June 2026

Observation:


Nil

Nil

Reminder:


1. At L2 road, the Contractor was reminded to regularly dispose of the general refuse collected.

 

2. At Area K, the Contractor was reminded to affix the NRMM label onto the Non-road Mobile Machinery.

Nil

ND/2024/08

3 June 2026

Observation:


Nil

Nil

Reminder:


1. The Permit Holder shall display conspicuously a copy of the Environmental Permit on the Project site(s) and other relevant environmental license(s) / permit(s) at all vehicular site entrances/exits or at a convenient location for public information at all times.

 

2. General refuse collected should be disposed of regularly.

 

3. At Area C, regular watering under a good site practice should be adopted to avoid dust nuisance

Nil

10 June 2026

Observation:


1. The Contractor was reminded that spent chemicals at Area L3 should be disposed of properly.

 

 

1. The spent chemicals were removed and disposed.

Reminder:


Nil

Nil

26 June 2026

Observation:


Nil

Nil

Reminder:


Nil

Nil

Works Contracts

Inspection Date

Key Observations/ Reminders

Follow-up Action

ND/2024/01

2 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

Nil

Nil

8 June 2026

Observation:

 

1. Water and dirt accumulated near the site barrier should be removed at Portion 25.

 

2. Chemical container on site should be placed on drip trays, or to be properly removed if it is empty at Portion 25.



1. Water and dirt near the site barrier were removed.

 

 

2. The chemical container was removed.

 

Reminder:

 

1. The NRMM label with faded colour is reminded to be replaced at Portion 25.

 

Nil

18 June 2026

Observation:

 

1. At Portion 59, chemical container on site should be placed on drip tray and labelled. Or it should be removed properly if it is no longer in use.

 

 

1. The chemical container was removed.

Reminder:

 

Nil

Nil

23 June 2026

Observation:

 

1. At Portion 25, frequency of watering should be increased to avoid dusty conditions.

 

 

1. Regular watering was enhanced.

Reminder:

 

1. At portion 25, the Contractor was reminded to regularly dispose of general refuse collected.

 

2. At portion 40, the Contractor was reminded that the portion of any road leading only to construction site should be kept clear of dusty materials.

Nil

30 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

Nil

Nil

ND/2024/02

2 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

8 June 2026

Observation:

 

Nil

Nil

Reminder:

 

1. The Contractor is reminded to ensure that the haul road near the site entrance and wheel washing bay is cleaned regularly at Portion 5.

Nil

18 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

26 June 2026

Observation:

 

Nil

Nil

Reminder:

 

1. At Area D, the haul road between the site exit and the wheel-washing facility is reminded to be cleaned often.

Nil

30 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

ND/2024/03

1 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

1. At new site office location, NRMM label should be posted conspicuously on the Non-Road Mobile Machinery.

Nil

8 June 2026

Observation:

 

1. The contractor was reminded that any excavated material or stockpile of dusty material should be removed when no construction work occurred at R526.

 

 

1. The stockpile was removed.

Reminder:

 

Nil

Nil

17 June 2026

Observation:

 

1. Muddy water and scattered mud were observed on the access road in front of Site Office and Contract ND/2024/05 WA2 after rainfall. The contractor was reminded to clean the access road promptly to prevent mud from being carried outside the construction site.

 

 

1. The access road and WA2 area was cleaned up.

Reminder:

 

Nil

Nil

22 June 2026

Observation:

 

Nil

Nil

Reminder:

 

Nil

Nil

29 June 2026

Observation:

 

Nil

Nil

Reminder:

1. At Iron Work Field (鐵場), the Contractor was reminded to treat all site wastewater using silt removal facilities to meet the required discharge licence standards before disposal.

Nil

ND/2024/04

5 June 2026

Observation:

 

1. At portion 2, muddy water seepage was observed leaking outside the site boundary. The Contractor was reminded to enhance mitigation measures to avoid any seepages and clear the muddy water immediately

 

 

1. The muddy water seepage was cleaned up.

Reminder:

 

1. At portion area ABC and portion 2, the colour of the NRMM label posted on the Non-Road Mobile Machineries was faded.

Nil

12 June 2026

Observation:

 

1. At portion 1, stockpiles should be covered or removed to avoid overflow of muddy water from entering nearby stream.

 

2. At portion 2, mitigation measures should be enhanced to ensure no seepages of muddy water to area outside site boundary.

 

 

1.The stockpile was removed.

 

 

 

 

2. Sandbags were deployed at the edge of the site boundary.

Reminder:

 

Nil

Nil

15 June 2026

Observation:

 

Nil



Nil

Reminder:

 

1. At Portion 1, the NRMM label on site with faded colour should be replaced.

 

2. At portions 1 and 5, the drainage facilities on site are reminded to be properly maintained, and runoff is reminded to be properly treated before discharge according to the discharge license.

Nil

26 June 2026

Observation:

 

Nil

Nil

Reminder:

 

1. At Portion 2, the temporary drainage system and wheel washing facilities are reminded to be properly maintained. Regular cleaning is also reminded to be carried out at site exits as often as necessary.

 

2. At portions 1 (Near Tai Tau Leng Playground), geotextile or sandbags are reminded to be provided to the storm drains on site.

Nil

ND/2024/05

2 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

9 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

17 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

23 June 2026

Observation:

 

Nil



Nil

Reminder:

 

1. At WA2, the Contractor was reminded to enhance the mitigation measures to avoid seepages of muddy water outside site boundary at the entrance.

Nil

30 June 2026

Observation:

 

Nil



Nil

Reminder:

 

Nil

Nil

ND/2024/06

1 June 2026

Observation:

 

Nil

 

 

Nil

Reminder:

 

1. At portion D, the colour of the NRMM label posted on the Non-Road Mobile Machinery faded.

Nil

12 June 2026

Observation:

 

1. At portion A, sediment in the settling pit should be removed.

 

 

1. The sediment was removed.

 

Reminder:

 

Nil

Nil

15 June 2026

Observation:

 

1. At portion C, broken sandbags should be replaced.

 

 

1. The broken sandbags were replaced.

Reminder:

 

1. At portion A, the contractor was reminded to ensure the NRMM label was securely affixed to the machinery.

Nil

22 June 2026

Observation:


1. Oil stains should be cleaned up properly at Area C. The Contractor was reminded to provide impervious sheeting for placing the breaker head to avoid contamination.

 

 

1. The oil stain was removed, and impervious sheeting was provided under the breaker head.

Reminder:


1. Stagnant water inside the drip tray was observed at Portion D. The contractor was reminded to clear the stagnant water after raining.

Nil

29 June 2026

Observation:

 

1. Black smoke emission from the generator should be avoided. The Contractor was reminded to regularly check the condition of the air filter inside the machinery equipment used on site at Portion A.

 

2. NRMM labels should be displayed on excavators at Portion A.

 

 

1. The generators were checked, no further black smoke emission was observed.

 

 

 

 

2.NRMM labels were displayed on the excavators.

Reminder:


1. The contractor was reminded to regularly direct site runoff to wastewater treatment facility especially after raining at Pit F.

Nil

ND/2024/07

4 June 2026

Observation:

 

Nil

Nil

Reminder:


1. At Area C, breaker should be wrapped with acoustic blanket.

Nil

11 June 2026

Observation:


Nil

Nil

Reminder:


Nil

Nil

18 June 2026

Observation:


Nil

Nil

Reminder:


Nil

Nil

25 June 2028

Observation:


Nil

Nil

Reminder:


1. At L2 road, the Contractor was reminded to regularly dispose of the general refuse collected.

 

2. At Area K, the Contractor was reminded to affix the NRMM label onto the Non-road Mobile Machinery.

Nil

ND/2024/08

3 June 2026

Observation:


Nil

Nil

Reminder:


1. The Permit Holder shall display conspicuously a copy of the Environmental Permit on the Project site(s) and other relevant environmental license(s) / permit(s) at all vehicular site entrances/exits or at a convenient location for public information at all times.

 

2. General refuse collected should be disposed of regularly.

 

3. At Area C, regular watering under a good site practice should be adopted to avoid dust nuisance

Nil

10 June 2026

Observation:


1. The Contractor was reminded that spent chemicals at Area L3 should be disposed of properly.

 

 

1. The spent chemicals were removed and disposed.

Reminder:


Nil

Nil

26 June 2026

Observation:


Nil

Nil

Reminder:


Nil

Nil

11.1.3    According to the EIA Study Report, Environmental Permit, contract documents and Updated EM&A Manual, the mitigation measures detailed in the documents should be implemented as much as practical during the reporting period. An updated implementation status of environmental mitigation measures is provided in Appendix 1.3. The photographic records of measures as stipulated in EPs to mitigate ecological impacts in the reporting month are presented in Table 11.2.

 

 

 

Table 11.2 Photographic Records and Implementation Status of Measures for Ecological Impacts

Works Contracts

EP No.

Photographic Record

Implementation Status

ND/2024/01

EP-467/2013/A (Condition 2.9)

 

 

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^

EP-468/2013/A

(Condition 2.11)

ND/2024/03

EP-465/2013/A

(Condition 2.9)

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^

EP-466/2013/A

(Condition 2.9)

EP-467/2013/A

(Condition 2.11)

Implementation status:

^ Mitigation measure was fully implemented

* Observation / reminder was made during site audit but improved / rectified by the contractor

# Observation / reminder was made during site audit but not yet improved / rectified by the contractor

X Non-compliance of mitigation measure

• Non-compliance but rectified by the contractor

 

N/A Not Applicable at this stage as no such site activities were conducted in the reporting period


 

12       Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions

12.1   Summary of Exceedance

12.1.1    No Action Level or Limit Level exceedance was recorded for air quality monitoring in the reporting period.

12.1.2    No Action Level exceedance for construction noise was recorded during the reporting month, corresponding to no noise-related complaint received. No Limit Level exceedance was recorded for construction noise monitoring in the reporting period.

12.1.3    No Action Level or Limit Level exceedance was recorded for ambient arsenic monitoring in the reporting period.

12.1.4    Four Limit Level exceedances were recorded for the monitoring of measures to minimise impacts on ecological sensitive habitats from disturbance and pollution. All exceedances were deemed as non-project related with potential influences by abiotic factors.

12.1.5    No Action Level or Limit Level exceedance was recorded for built heritage monitoring (vibration monitoring) in the reporting period.

12.2   Summary of Environmental Non-Compliance

12.2.1    No environmental non-compliance was recorded in the reporting period.

12.3   Summary of Environmental Complaint

12.3.1    One environmental complaint was logged during the reporting period. The complaint was regarding muddy water runoff.

12.3.2    The environmental complaint was related to muddy water accumulated on the footpath and muddy runoff entering the Ng Tung River on 17 June 2026 under works contract ND/2024/07. The complaint was received by the EPD on 17 June 2026 and referred to CEDD, the Resident Engineers’ Team, ET, and IEC on 22 June 2026. The complaint case has been investigated by the Contractor and ET, and the investigation was closed out on 2 July 2026. The investigation findings have shown that there was no direct evidence indicating that the condition was caused by this work contract and non-compliance was observed.

12.3.3    The details of the complaint and investigation result are shown in Appendix 12.1.

12.4   Summary of Environmental Summon and Successful Prosecution

12.4.1    There was no successful environmental prosecution or notification of summons received since the Project commencement. The summary of environmental summon and successful prosecution is presented in Appendix 12.1.


13       Future Key Issues

13.1   Works and Potential Environmental Issues in the next Reporting Period

13.1.1    The upcoming construction works programme, and the construction works area of the Project are presented in Appendix 1.1. Works to be undertaken in the next reporting period are summarized below:

Works Contract No. ND/2024/01:

·  All Site Resumption Area(s)

1.   Tree survey

2.   Site Clearance

·  Portion III (3), IV (4), V (5), and XXXV (35)

1.   Site Formation

·  Portion VIII (8), XVI (16), XXXII (31), XXXV (35) XLII (42), LIII (53) and LVIII (58)

1.   Site Clearance & Demolition

2.   Asbestos Abatement Works

·  Portion XVIII (18), XXXVIII (38)

1.   Excavation works

2.   Construction of CHC Box Culvert

·  Portion XI (11), XXIII (23)

1.   Formwork Erection, Rebar Fixing, Concreting Works

2.   Erection of Substructure of Metropolis Community Liaison and Visitor Centre

·  Portion XL (40)

1.   Retaining Wall Construction

2.   Drainages System Construction

3.   ELS work

·  Portion LIX (59)

1.   Treatment of High Arsenic-Containing Soil (HAS)

·  Portion XVII (17), XVII (18), XXI (21), XXXIV (34), XXXV (35), XLI (41), XLII (42)

1.   Excavation Works

2.   Drainage Pipe Installation

3.   ELS Works

·  Portion XXV (25), XXVII (27), XXXIII (33), XLII (42) and XLIV (44)

1.   Site Clearance

2.   Site Formation

3.   Construction of CHB and CHD Box Culvert

 

·  Portion XII (12), XXX (30), XLIV (44)

1.   Archaeological Survey

 

Works Contract No. ND/2024/02:

·  Portion 2, 3, 4, 5, 18, 20 and 43

1.   Site clearance

·  Portion 5

1.   Site formation works

·  Portion 2, 3 and 18

1.   Ground investigation works

·  Portion 2, 4 and 25

1.   Asbestos removal works

·  Portion 2 and 3

1.   Tree removal works

 

Works Contract No. ND/2024/03:

Fanling Highway & Castle Peak Road area

 

·  Pak Sau Road – Po Lau Road

1.   Tree Works

2.    Watermain DN150

·  Po Lau Road – Sheung Yue River

1.   Tree Works

2.   Box Culvert Bay 37 – Bay 42 New Castle Peak Road & Fanling Highway

·  TTA Stage 1 Works

1.   Tree Works 

2.   Demolish of Central Divider & Barrier along FL Highway E/B 

·  New Tsung Pak Long Road

1.   Box culvert Bay 10 to 12, 14 to 16 Drainage/Watermains

2.   Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 15 & 16 

·  Box culvert Bay 17 to 19 & Drainage/Watermains

1.   Drainage, Sewerage & Watermain with Backfilling at Box Culvert Bay 19

·  TTA Stage 1B 

1.   Box Culvert Bay 3, 5 to 7, 7A ELS 

2.   Box Culvert Base Slab 

·  Retaining Wall RW05A

1.   RW05A Base Slab and Wall 

·  Kwu Tung Road Bridge

1.   Site clearance and tree works

2.   Site formation and cutback the existing slope

3.   Foundation & Piling

·  Works Areas – WA1, WA2, WA3, WA4 & WA5

1.   Temporary Drainage 

2.   Material/ Segments Storage Yard

Fanling Highway Cross River Bridge (along Sheung Yue River)

 

·  Portion X – West Abutment

1.   Site clearance & preparation, survey and tree works

·  Road L3 Viaduct

1.   Piling Works

2.   Pile Cap L3A-02

Kwu Tung Interchange Foundation & Substructure

 

·  Bridge B1 & C1

1.   Piling Works

2.   ELS

·  Bridge B2 & C2

1.   Piling Works

·  Footbridges No. 4 at TTA Stage 1 

1.   Ground Investigation 

2.   Underground Utilities Works

3.   Piling

·  Footbridges No. 5 at TTA Stage 2 

1.   Installation of the temporary FB5 

·  Widening of Existing Bridge No.N526

1.   Pilling

 

Works Contract No. ND/2024/04:

·  Portion I

1.   Site Clearance

2.   Site Establishment

3.   Tree Works

4.   Ground Investigation

5.   Haul Road Construction

6.   Existing Sewage Diversion

7.   Demolition of Existing Structures

8.   Road Diversion Works

9.   ELS Construction

10.Pipe Cap Construction

·  Portion II

1.   Site Clearance

2.   Site Establishment

3.   Trial Pit

4.   Bored Pilling

5.   Haul Road Construction

6.   ELS Construction

7.   Socket H Piling

·  Portion III

1.   Site Clearance

2.   Site Establishment

3.   Trial Pit

4.   Ground Investigation

5.   Bored Pilling

6.   Haul Road Construction

7.   Road Diversion Works

·  Portion IV

1.   Site Clearance

2.   Site Establishment

3.   Tree Felling

·  Portion V

1.   Site Clearance

2.   Site Establishment

·  Portion VI

1.   Site Clearance

2.   Site Establishment

3.   Demolition of Existing Structures

·  Portion VII

1.   Site Clearance

2.   Site Establishment

3.   Pre-drilling

·  Portion VIII

1.   Site Clearance

2.   Site Establishment

3.   Demolition of Existing Structures

 

Works Contract No. ND/2024/05:

·  Portion I

1.   Ground Investigation  

2.   UU Detection

·  Portion III and IIIA

1.   Tree Survey

2.   UU Detection

3.   Site Clearance

·  Portion VI and IX

1.   Asbestos Survey

2.   Asbestos Removal

·  Portion XI and XII

1.   Tree Survey 

2.   Asbestos Survey 

3.   Asbestos Removal

4.   UU Detection 

5.   Site Clearance 

6.   Ground Investigation  

·  Portion XVII

1.   Tree Survey 

2.   Tree Felling

3.   UU Detection 

4.   Site Clearance 

5.   Ground Investigation

 

Works Contract No. ND/2024/06:

·  Portion A

1.   Excavation to +84 mPD of Portion A

2.   Carry Out Soil Nail of Portion A

·  Portion C, D, E & F

1.   Trench and Watermans Laying Works

·  Pit A & C

1.   Pre-boring and Sheet-Piling

·  Pit B & F

1.   Sheet-Piling

 

Works Contract No. ND/2024/07:

·  Area C

1.   Site Formation

·  Area D

1.   Site Formation

2.   Ground Investigation

·  Area E

1.   Site Formation

2.   Site Clearance

·  Area F

1.   Site Clearance

2.   Site Formation

3.   Tree Felling

4.   Sewerage Construction

5.   Storm Pipe Construction

·  Area G

1.   Site Clearance

2.   Site Formation

·  Area H

1.   Asbestos Removal

·  Area I

1.   Asbestos Removal

2.   Sewerage Construction

3.   Ground Investigation

·  Area J

1.   Road Works

·  Area K

1.   Site Clearance

2.   Asbestos Removal

3.   Old Shrine Removal

4.   Retaining Wall Construction

5.   Sewerage Construction

6.   Environmental Ground Investigation

7.   Road Construction

·  Area M

1.   Sewage Pumping Station (SPS4) Construction

 

·  Area O

1.   Site Clearance

2.   Asbestos Removal

3.   Box Culvert 4 Construction

·  Area P

1.   Site Formation

2.   Drainage Construction

·  Area Q

1.   Tree Felling

2.   Tree Transplantation

3.   Drainage Construction

4.   Storm Pipe Construction

5.   Box Culvert 5 Construction

·  Area R

1.   Asbestos Removal

·  Portion 1b

1.   Site Formation

2.   Underground Utilities Construction

3.   Open Landscape

·  Portion 3b

1.   Sewerage Construction

2.   Drainage Construction

3.   Flushing Main Construction

·  Portion 6c

1.   Improvement of Junction

·  Portion 9b

1.   Rebar Yard

·  Footbridge FB-4 (North)

1.   Lift Tower Construction

2.   ABWF Works

3.   Sump Pit Construction

·  Footbridge FB-4 (South)

1.   ABWF Works

2.   Pile Cap and Pier Construction Works

3.   Sump Pit Construction

4.   UHPC Staircase Construction

·  Footbridge FB-5

1.   Lift Tower Construction

2.   Sump Pit Construction

3.   ABWF Works

 

Works Contract No. ND/2024/08:

·  Site A

1.   Asbestos Removal

·  Site B

1.   Asbestos Investigation

·  Site Area C1 & C2

1.   Site Clearance

2.   Tree Felling

3.   Asbestos Removal

4.   Site Formation

·  Site Area D & E

1.   Tree Felling

2.   Site Clearance

·  Site Area G, H1 & H2

1.   Tree Felling

2.   Site Clearance

·  Site Area I, V2 & V4

1.   Tree Felling

2. Excavation

·  Site Area L6, K & U

1.   Site Clearance

2.   Tree Felling

3.   Road Works

4.   Underground Utilities

·  Site Area L1, L2, L3, L4, L5 & L7

1.   Divert Existing Village Road 

·  Site Area M1, M2, M3, N1, N2, O & P

1.   Site Clearance

2.   Tree Felling

3.   Road Works

4.   Underground Utilities

·  Site Area R

1.   Plate Load Test

·  Site Area T

1.   Preliminary Works

2.   Site Clearance

·  Site Area W

1.   Tree Felling

·  Site Area Q

1.   Plate Road Test

13.1.2    Potential environmental impacts arising from the above construction activities are mainly associated with construction noise impact, water quality impact, ecological impact, waste management, and landscape and visual.

13.2   Recommendation

13.2.1    The key environmental mitigation measures for the Project in the coming reporting period expected to be associated with the construction activities include:

Dust

 

•        Regular watering to reduce dust emissions from exposed site surface;

•        Stockpile of dusty materials shall be covered entirely by impervious sheeting;

•        Provide vehicles washing facilities at all site exits to wash away any dusty materials from vehicle body;

•        NRMM Labels should be displayed on the applicable equipment on site by the Contractor;

•        Provision of water sprinklers along the haul road for dust suppression.

 

Noise

 

•        Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and

•        Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.

 

Water Quality

 

•        No effluent discharge would be allowed before acquired the effluent discharge license;

•        Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;

•        Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;

•        Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;

•        Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and

•        Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.

 

Waste Management

 

•        Provision of sufficient waste disposal points and regular collection of waste;

•        Regular cleaning and maintenance programme for drainage system; and

•        Chemical containers shall be stored with drip tray underneath.

 

Landscape and Visual

 

•        Construction activities shall be carefully designed to minimize impact on existing retained trees.

 

Land Contamination

 

•        Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be properly covered by impermeable sheeting to reduce dust emission during dry season or contaminated run-off during rainy season. Watering should be avoided on stockpiles of soil to minimise runoff.

 

Landfill Gas Hazard

•        “No Smoking” and “No Naked Flame” notices in Chinese and English should be posted prominently around the construction site.

 

Ecology

 

•        Properly erect and maintain 2m high solid barriers for protection.

•        An individual of orchid Eulophia cernua was found growing underneath the pipeline adjacent to the access road leading to the summit of the Table Hill Freshwater Service Reservoir for Contract No. ND/2024/06. The species of conservation importance should be fenced off for protection to minimise the potential impacts aroused from nearby construction activities as far as possible.

13.2.2    The tentative impact monitoring schedule for the next reporting period is shown in the Appendix 13.1. The regular impact monitoring will be conducted at the same monitoring locations in the next reporting period.

 

14       Conclusions

14.1   Conclusion

14.1.1    This is the 18th Monthly EM&A Report summarizing the findings of EM&A works at Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/05, Works Contract No. ND/2024/06, Works Contract No. ND/2024/07 and Works Contract No. ND/2024/08 during the reporting month, this report documents the findings of EM&A works at Works Contract No. ND/2024/01, Works Contract No. ND/2024/02, Works Contract No. ND/2024/03, Works Contract No. ND/2024/04, Works Contract No. ND/2024/05, Works Contract No. ND/2024/06 and Works Contract No. ND/2024/07 and Works Contract No. ND/2024/08 under the Project during the reporting period.

14.1.2    All air quality monitoring was conducted as scheduled in the report period. No Action Level or Limit Level exceedance was recorded for air quality monitoring in the reporting period.

14.1.3    All construction noise monitoring was conducted as scheduled in the report period. No Action Level exceedance for construction noise was recorded during the reporting month, corresponding to no noise-related complaint received. No Limit Level exceedance was recorded for construction noise monitoring in the reporting period.

14.1.4    All ambient arsenic monitoring was conducted as scheduled in the reporting period. No Action or Limit Level exceedance was recorded during ambient arsenic monitoring in the reporting period.

14.1.5    All ecological monitoring was conducted as scheduled in the reporting period. 4 Limit Level exceedances were recorded for the monitoring measures to minimise impacts on ecological sensitive habitats from disturbance and pollution. All exceedances were deemed as non-project related with potential influences by abiotic factors.

14.1.6    No exceedance of limits was recorded for built heritage monitoring (vibration monitoring) in the reporting period.

14.1.7    Environmental site inspections were conducted at Works Contract No. ND/2024/01 on 2, 8, 18, 23, 30 June 2026. For Works Contact No. ND/2024/02 were carried out on 2, 8, 18, 26, 30 June 2026. For Works Contact No. ND/2024/03 were carried out on 1, 8, 17, 22, 29 June 2026. For Works Contact No. ND/2024/04 were carried out 5, 12, 15, 26 June 2026. For Works Contact No. ND/2024/05 were carried out on 2, 9, 17, 23, 30 June 2026. For Works Contact No. ND/2024/06 were carried out on 1, 12, 15, 22, 29 June 2026. For Works Contract No. ND/2024/07 were carried out on 4, 11, 18, 25 June 2026. For Works Contract No. ND/2024/08 were carried out on 3, 10, 26 June 2026, the originally scheduled weekly environmental site inspection on 18 June 2026 was cancelled, due to the adverse weather conditions.

14.1.8    No notification of summons and prosecution was received in the reporting period.

14.1.9    The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

14.1.10 No change to the EM&A programme was made in this reporting period.

14.2   Comments/ Recommendations

14.2.1    The proposed mitigation measures were properly implemented and were considered effective and efficient in pollution control.